ALAN CUSTOM HOMES INC V KENNETH KROL
Annotate this Case
Download PDF
STATE OF MICHIGAN
COURT OF APPEALS
ALAN CUSTOM HOMES, INC.,
FOR PUBLICATION
May 8, 2003
9:00 a.m.
Plaintiff/CounterdefendantAppellee,
v
No. 237138
Oakland Circuit Court
LC No. 00-022056-CK
KENNETH KROL and KAREN KROL,
Defendants/CounterplaintiffsAppellants.
Updated Copy
June 20, 2003
Before: Hoekstra, P.J., and Smolenski and Fort Hood, JJ.
SMOLENSKI, J.
In this case involving breach of contract and a construction lien, defendants Kenneth and
Karen Krol appeal as of right the judgment entered in favor of plaintiff Alan Custom Homes,
Inc., following a bench trial. Plaintiff was awarded $42,763 plus interest, fees, and costs, for a
total judgment of $57,512.62 against defendants. We affirm.
On October 24, 1998, defendants and plaintiff entered into a cost-plus contract1 for
plaintiff to build a custom home for defendants, at a cost of $262,466. Construction was delayed
by waiting for permits, inclement weather, problems with draws, and changes in design. On
January 4, 2000, defendants locked plaintiff 's workers out of the house, alleging that plaintiff had
breached their contract by not completing the house in a timely manner. On January 18, 2000,
defendants formally terminated plaintiff 's services by letter. At that time, the house was ninetyfive percent complete. Defendants acted as a general contractor to complete the house
themselves.
1
A cost-plus construction contract is "[o]ne which fixes the amount to be paid the contractor on
a basis, generally, of the cost of the material and labor, plus an agreed percentage thereof as
profits. Such contracts are used when costs of production or construction are unknown or
difficult to ascertain in advance." Black's Law Dictionary (6th ed).
-1-
On appeal, defendants claim that the trial court erred by denying their motion for
summary disposition regarding plaintiff 's claim for foreclosure of the construction lien. We
disagree. This Court reviews a trial court's grant or denial of summary disposition de novo.
Spiek v Dep't of Transportation, 456 Mich 331, 337; 572 NW2d 201 (1998). Likewise, this
Court reviews questions of statutory construction de novo. Roberts v Mecosta Co Gen Hosp, 466
Mich 57, 62; 642 NW2d 663 (2002).
The trial court apparently considered both MCR 2.116(C)(8) and (C)(10) as grounds for
its summary-disposition decision. A motion for summary disposition under MCR 2.116(C)(8)
tests the legal sufficiency of the claim on the pleadings alone to determine whether the plaintiff
has stated a claim on which relief may be granted. Spiek, supra at 337. A court must accept all
factual allegations in the pleadings in support of the claim as true, as well as any reasonable
inferences or conclusions that can be drawn from the facts, and construe those facts in the light
most favorable to the nonmoving party. Maiden v Rozwood, 461 Mich 109, 119; 597 NW2d 817
(1999). A motion under MCR 2.116(C)(10) tests the factual support of a plaintiff 's claim.
Spiek, supra at 337. When deciding a motion under MCR 2.116(C)(10), a court must consider
the pleadings, affidavits, depositions, admissions, and other documentary evidence submitted in
the light most favorable to the nonmoving party. Ritchie-Gamester v Berkley, 461 Mich 73, 76;
597 NW2d 517 (1999).
Resolution of this issue requires us to interpret § 110 of the Construction Lien Act (CLA),
MCL 570.1101 et seq. In Vugterveen Sys, Inc v Olde Millpond Corp, 454 Mich 119, 121; 560
NW2d 43 (1997), our Supreme Court discussed the purpose and interpretation of the CLA and
stated that the act "was intended to protect the interests of contractors, workers, and suppliers
through construction liens, while protecting owners from excessive costs." The Court further
stated that the act is to be "liberally construed to effectuate these purposes." Id.
MCL 570.1110(8) states:
If a contractor fails to provide a sworn statement to the owner or lessee
before recording the contractor's claim of lien, the contractor's construction lien is
not invalid. However, the contractor is not entitled to any payment, and a
complaint, cross-claim, or counterclaim may not be filed to enforce the
construction lien, until the sworn statement has been provided.
Defendants contend that this provision bars plaintiff 's foreclosure claim.
While a strict reading of MCL 570.1110(8) supports defendants' argument that plaintiff 's
claim is barred, only "substantial compliance" with this provision is required. In Northern
Concrete Pipe, Inc v Sinacola Cos-Midwest, Inc, 461 Mich 316; 603 NW2d 257 (1999), our
Supreme Court recently addressed when it is appropriate to use the CLA's "substantial
-2-
compliance" provision.2 The Court recognized that in Vugterveen, supra, it stated that the
"substantial compliance" provision applied to part one of the CLA, but noted that Vugterveen did
not examine whether the provision was applicable to "every word of every provision within part
one." Id. at 321 n 15 (internal citations omitted). Therefore, the Court in Northern Concrete
Pipe instructed that
[t]he scope of a statutory "substantial compliance" provision requires an analysis,
on a case-by-case basis, of the following logically relevant factors among others:
the overall purpose of the statute; the potential for prejudice or unfairness when
the apparent clarity of a statutory provision is replaced by the uncertainty of a
"substantial compliance" clause; the interests of future litigants and the public; the
extent to which a court can reasonably determine what constitutes "substantial
compliance" within a particular context; and, of course, the specific language of
the "substantial compliance" and other provisions of the statute. [Id. at 321-322.]
While Northern Concrete Pipe dealt with the applicability of the "substantial compliance"
provision to the filing requirement of MCL 570.1111(1), the Supreme Court noted that
application of the "substantial compliance" provision was well suited to notice provisions where
the purpose of the requirement is to ensure that notice was received, citing Vugterveen's
application of the "substantial compliance" provision to the notice requirement in MCL
570.1109. Id. at 323. Likewise, we hold that the CLA's "substantial compliance" provision is
applicable to the notice requirement in MCL 570.1110(8).
In this case, application of the CLA's "substantial compliance" provision supports
plaintiff 's contention that its provision of unverified statements to the title company during
construction and of a verified sworn statement to defendants before the summary-disposition
hearing satisfied the notice requirement of MCL 570.1110(8). The purpose of the contractor
providing the property owner with a sworn statement is "to enable the homeowner 'to retain out
of any money due or to become due to the contractor an amount sufficient to pay the
subcontractors . . . .'" ERB Lumber, Inc v Gidley, 234 Mich App 387, 399 n 5; 594 NW2d 81
(1999), quoting Nurmi v Beardsley, 275 Mich 328, 329; 266 NW 368 (1936). That a statement is
not sworn before a notary does not defeat the notice purpose of the statement. It still gives the
owner notice of who the subcontractors are and the amount owing to each for the materials and
labor supplied.
2
The "substantial compliance" provision of the CLA, MCL 570.1302(1), states:
This act is declared to be a remedial statute, and shall be liberally
construed to secure the beneficial results, intents, and purposes of this act.
Substantial compliance with the provisions of this act shall be sufficient for the
validity of the construction liens provided for in this act, and to give jurisdiction
to the court to enforce them.
-3-
Therefore, we find that the unverified statements plaintiff gave to the title company to
obtain draws substantially complied with the statutory notice requirement of MCL 570.1110(8).
Moreover, we find that although plaintiff filed the present cause of action, including its claim for
foreclosure of the lien, before giving defendants a verified sworn statement, plaintiff 's provision
of the verified sworn statement to them in February 2001, before the summary-disposition
hearing was held,3 also constituted substantial compliance with MCL 570.1110(8).
In addition, plaintiff was entitled to maintain a cause of action against defendants for
breach of contract, independent of any claim for foreclosure of the lien. MCL 570.1302(2).4
Although plaintiff 's inclusion of the lien-foreclosure claim in plaintiff 's complaint and first
amended complaint was premature under MCL 570.1110(8), the trial court could have allowed
plaintiff to amend the complaint to include the lien-foreclosure claim after the verified sworn
statement was delivered to defendants, but before the summary-disposition motion was heard.
Because the claim was properly before the trial court when the summary disposition motion was
heard, we hold that the trial court did not err in denying defendants' motion under MCR
2.116(C)(8). We further hold that because there were genuine issues of material fact regarding
whether defendants requested a sworn statement from plaintiff at an earlier date, summary
disposition was properly denied under MCR 2.116(C)(10).
Defendants next contend that the trial court erred by dismissing their counterclaim for
breach of contract without evaluating whether plaintiff 's failure to provide accountings to them
was a material breach. Again, we disagree. This Court reviews a trial court's findings of fact in a
bench trial for clear error and its conclusions of law de novo. MCR 2.613(C); Chapdelaine v
Sochocki, 247 Mich App 167, 169; 635 NW2d 339 (2001). A finding is clearly erroneous where,
after reviewing the entire record, this Court is left with a definite and firm conviction that a
mistake has been made. Walters v Snyder, 239 Mich App 453, 456; 608 NW2d 97 (2000).
A careful reading of the trial court's findings indicates that the court did not find it
necessary to decide whether plaintiff materially breached the contract before defendants locked
plaintiff out, because defendants did not prove any damages from plaintiff 's alleged breach. The
party asserting a breach of contract has the burden of proving its damages with reasonable
certainty, and may recover only those damages that are the direct, natural, and proximate result of
the breach. In re F Yeager Bridge & Culvert Co, 150 Mich App 386, 401; 389 NW2d 99 (1986).
Here, the trial court found that plaintiff did not cause defendants' damages, i.e., the cost of
completing the project, because plaintiff would have completed the project had defendants not
locked plaintiff out, and defendants would have had to pay plaintiff the cost of completion.
Therefore, defendants' counterclaim for breach of contract was properly dismissed.
3
We note that defendants' motion for summary disposition was filed one month before plaintiff
delivered the sworn statement to defendants, but that the motion hearing was held three months
after the sworn statement was delivered.
4
MCL 570.1302(2) states, "[t]his act shall not be construed to prevent a lien claimant from
maintaining a separate action on a contract."
-4-
Defendants also argue that the trial court clearly erred in upholding plaintiff 's claim of
lien where the claim was excessive and made in bad faith. However, this issue was not
addressed by the trial court and is not properly before this Court. Fast Air, Inc v Knight, 235
Mich 541, 549; 599 NW2d 489 (1999). Regardless, no bad faith is evident from the record, and
the trial court reduced to the proper amount the lien-claim amount in excess of the actual
damages. Tempo, Inc v Rapid Electric Sales & Service, Inc, 132 Mich App 93, 104; 347 NW2d
728 (1984). Therefore, defendants' argument is without merit.
Finally, defendants claim the trial court erred by not restricting the amount of the lien
claim to the difference between the original price in the written contract and the amount
defendants actually paid plaintiff. In connection with that argument, defendants also claim that
the trial court erroneously awarded plaintiff damages for "extras" not included in the contract.
We disagree. This Court reviews the trial court's determination of damages following a bench
trial for clear error. Marshall Lasser, PC v George, 252 Mich App 104, 110; 651 NW2d 158
(2002).
Defendants rely on MCL 570.1107 and MCL 570.1114 to support their argument that
plaintiff 's claim of lien is restricted to the difference between the written-contract price and the
amount defendants already paid plaintiff. MCL 570.1107 states, in pertinent part:
(1) Each contractor, subcontractor, supplier, or laborer who provides an
improvement to real property shall have a construction lien upon the interest of
the owner or lessee who contracted for the improvement to the real property, as
described in the notice of commencement provided for by section 108 or 108a, the
interest of an owner who has subordinated his or her interest to the mortgage for
the improvement of the real property, and the interest of an owner who has
required the improvement. A construction lien acquired pursuant to this act shall
not exceed the amount of the lien claimant's contract less payments made on the
contract. [Emphasis added.]
MCL 570.1114 states, in pertinent part:
A contractor shall not have a right to a construction lien upon the interest
of any owner or lessee in a residential structure unless the contractor has provided
an improvement to the residential structure pursuant to a written contract between
the owner or lessee and the contractor and any amendments or additions to the
contract also shall be in writing. [Emphasis added.]
The reference in MCL 570.1114 to a written-contract requirement regarding liens on
residential structures is contrary to the CLA's broad definition of contract.5 In interpreting the
5
MCL 570.1103(4) states:
(continued…)
-5-
term "written contract" in MCL 570.1114, we are guided by the following principles. Omission
of a phrase in one portion of a statute that is included in another should be construed as
intentional. Farrington v Total Petroleum, Inc, 442 Mich 201, 210; 501 NW2d 76 (1993). Also,
this Court assumes that every word used in a statute has meaning, and, therefore, this Court must
avoid any construction which would render a statute or any part of it surplusage or nugatory.
Hoste v Shanty Creek Mgt, Inc, 459 Mich 561, 574; 592 NW2d 360 (1999). Therefore, we
conclude that the term "written contract" in MCL 570.1114 must be strictly construed.
Furthermore, as plaintiff points out, the requirement of a written contract, and written
amendments thereto, in MCL 570.1114 does not include a signature requirement. Plaintiff
submitted written change orders and statements to defendants documenting the orally agreed to
contract amendments. Defendants did not object to these changes and accepted their benefits.
Therefore, the requirement of a writing for additions and amendments to a written contract was
fulfilled.
Defendants also assert that their contract with plaintiff required that any modifications be
in writing and executed by all the parties. The contract stated:
It is further agreed that this agreement and any written amendments or
addenda attached hereto contain all the representations and obligations of the
respective parties and any modifications or changes herein shall be made in
writing and executed by all the parties to this agreement otherwise the same shall
not be binding upon the other party hereto.
But the addendum to the contract, executed at the same time as the contract, stated, "[i]f the
actual cost of any individual line item(s) shall exceed the estimate provided on this list by Seller,
these additional costs shall be the sole responsibility of the purchaser." Defendants do not
dispute that many of the cost overruns were due to their choice of fixtures and changes in design.
Therefore, the written addendum, executed by both parties at the same time as the original
contract, obligated defendants to pay for the expenses over the allowances estimated by plaintiff.
Accordingly, plaintiff 's claim of lien was supported by a written contract, as required by MCL
570.1114. Further, because the lien-award amount was not in excess of the difference between
the amended contract price and the amount defendants already paid plaintiff, it complied with
MCL 570.1107.
In addition, we hold that the award of $17,000 for "extras" was not clearly erroneous
inasmuch as the trial court indicated that it had "considered all the evidence relating to those
'extras'" and "determined that the preponderance of the evidence supports the balance of $17,000
worth of 'extras' after credits to defendants." It appears that the trial court "was aware of the
(…continued)
"Contract" means a contract, of whatever nature, for the providing of
improvements to real property, including any and all additions to, deletions from,
and amendments to the contract.
-6-
issues in the case and correctly applied the law." Triple E Produce Corp v Mastronardi Produce,
Ltd, 209 Mich App 165, 176; 530 NW2d 772 (1995). Further, because plaintiff claimed $28,095
in "extras," and defendants claimed that all the "extras" were included in the original contract
price, the damage award was within the range of the evidence presented. Id. at 177.
Affirmed.
/s/ Michael R. Smolenski
/s/ Joel P. Hoekstra
/s/ Karen M. Fort Hood