ENVIROPOWER, LLC v. PUBLIC SERVICE COMMISSION OF KENTUCKY, EAST KENTUCKY POWER COOPERATIVE, INC., GREGORY D. STUMBO, ATTORNEY GENERAL OF KENTUCKY, AND GALLATIN STEEL COMPANY
Annotate this Case
Download PDF
RENDERED:
FEBRUARY 2, 2007; 2:00 P.M.
NOT TO BE PUBLISHED
Commonwealth of Kentucky
Court of Appeals
NO.
2005-CA-001792-MR
ENVIROPOWER, LLC
APPELLANT
APPEAL FROM FRANKLIN CIRCUIT COURT
HONORABLE ROGER L. CRITTENDEN, JUDGE
ACTION NO. 05-CI-00553
v.
PUBLIC SERVICE COMMISSION OF KENTUCKY,
EAST KENTUCKY POWER COOPERATIVE, INC.,
GREGORY D. STUMBO, ATTORNEY GENERAL OF
KENTUCKY, AND GALLATIN STEEL COMPANY
APPELLEE
OPINION
AFFIRMING
** ** ** ** **
BEFORE:
BARBER1 AND DIXON, JUDGES; PAISLEY, SENIOR JUDGE.2
DIXON, JUDGE:
EnviroPower, LLC, appeals the Franklin Circuit
Court’s dismissal of its case challenging a Public Service
Commission (“PSC”) order denying intervention.
1
Judge David A. Barber concurred in this opinion prior to the expiration of
his term of office on December 31, 2006. Release of the opinion was delayed
by administrative handling.
2
Senior Judge Lewis G. Paisley, sitting as Special Judge by assignment of the
Chief Justice pursuant to Section 110(5)(b) of the Kentucky Constitution and
KRS 21.580.
The PSC denied EnviroPower’s Motion for Intervention in a
Certificate of Public Convenience and Necessity (“CON”) hearing.
The hearing was initiated by East Kentucky Power Cooperative,
Inc's., (“EKPC”) application to the PSC for permission to selfconstruct a 278 MW coal-fired generating plant at its Spurlock
Station site in Maysville, Kentucky.
Prior to making the CON application to begin
construction, EKPC had issued a “Request for Proposals (“RFP”)
in April 2004, for various contractors to bid on supplying the
necessary power. EKPC anticipated a need to substantially
increase its power generation capacity to serve a new retail
customer and sought proposals from outside power suppliers to
determine whether it was more economically feasible for EKPC to
self-build a new power facility or purchase power from other
suppliers.
Ultimately, the lowest bid was EKPC’s proposal to
construct the facility itself.
KRS 278.020 requires a CON
certificate be issued before construction begins.
The CON application was docketed as PSC Case No.
2004-00423 (“CON Case”).
Intervention was granted to the Office
of the Attorney General and Gallatin Steel, the largest electric
consumer of EKPC power.
The PSC established a procedural
schedule and a hearing was initially scheduled on February 18,
2005.
-2-
EnviroPower was one of thirty-nine (39) unsuccessful
bidders in the earlier RFP request for power supply bids issued
by EKPC.
EnviroPower owns no electric generating facilities,
but it proposed to construct a merchant generating plant and
sell the output to EKPC.
In mid-September 2004, EKPC informed
EnviroPower that its bid had been rejected.
On January 14,
2005, EnvrioPower filed its first request to intervene at the
PSC to challenge EKPC's
process.
bid solicitation and evaluation
By PSC order dated February 3, 2005, EnviroPower’s
first request to intervene was denied upon the findings that:
(1) it was not a ratepayer of EKPC, but a rejected bidder whose
interests were not identical to rate- payers; and (2)
EnviroPower had a legal duty to its members to maximize profits;
a far different goal from protection of the ratepayers.
EnviroPower’s interest would be served by challenging any bid
evaluation process that rejected its bid and, that interest did
not coincide with the interests of ratepayers.
Although
intervention was denied, EnviroPower’s name was added to the
service list so it could monitor the proceedings, submit further
information, and even comment upon the issues.
EnviroPower
filed neither a timely request for rehearing at the PSC under
KRS 278.400, nor a timely action for review in the Franklin
Circuit Court under KRS 278.410(1).
-3-
On the same date that the PSC denied EnviroPower’s
first request to intervene, the PSC issued another order in the
CON Case initiating a full investigation of EKPC’s bidding
procedures and evaluation process.
The PSC directed EKPC to
file supplemental testimony that included, but was not limited
to the following issues:
1. A detailed description of the nature and
extent of participation by East Kentucky
Power’s distribution cooperatives and Warren
Rural Electric Cooperative Corporation in
the bid evaluation process;
2. The details of each discussion with each
bidder regarding revisions to any provision
of that bidder’s bid; and
3. Sufficient details to enable the
Commission to objectively determine whether
the capital cost and the base load
requirement price for the EnviroPower bid
was lower than those of the East Kentucky
Power self-construct bid.
The PSC also required testimony to be filed by
EnerVision, Inc., an outside consultant retained by EKPC to
assist in the evaluation and economic rankings of the power
supply bids.
The consultant was directed to file detailed
testimony on the following issues:
1. Its role in evaluating and ranking the
power supply bids;
2. The extent to which its role was
performed independently of East Kentucky
Power;
-4-
3. Whether its economic rankings of the
power supply bids coincide with those of
East Kentucky Power as shown in Application
Exhibit 4, p. 7; and
4. Any other information necessary or
appropriate for a full and complete
understanding of the bid evaluation process.
That PSC order further required EKPC to respond to a number of
requests for information, including the filing of a complete
copy of each of the thirty-nine (39) power supply bids
received.
Each of the bids, including EnviroPower’s, was filed
under seal and EnviroPower has never seen the details of EKPC’s
bid. All of the testimony and information required by the PSC’s
February 3, 2005, order was filed.
EnviroPower filed extensive
comments in the form of prepared testimony.
On April 11, 2005, EnviroPower filed a second
petition to intervene at the PSC.
Finding no change in
circumstances since the first petition had been deniedEnviroPower was not a ratepayer and had no interest in either
the “rates” or “service” of EKPC- the PSC denied EnviroPower’s
second intervention petition by order dated April 18, 2005. That
order also found that EnviroPower was unlikely to present issues
or develop facts to assist in the consideration of the CON
Case.
The PSC explained “EnviroPower had no role in either the
development of EKPC’s bidding procedures or the evaluation of
-5-
the bids received.
Only East Kentucky Power and its consultants
were involved in those activities.”
EnviroPower then filed on April 19, 2005, an action
in the Franklin Circuit Court requesting injunctive and
declaratory relief.
The Court held a brief hearing that same
day and issued a restraining order which among other things,
prohibited the PSC from holding its scheduled hearing.
Subsequently, the Court issued its May 6, 2005, Order, which
among other things, dissolved the restraining order, rejected
all of EnviroPower’s challenges to the PSC’s denial of
intervention, and denied a temporary injunction to prohibit a
PSC hearing in the CON Case.
EnviroPower requested
interlocutory relief in the Court of Appeals, which was denied
by Order entered May 31, 2005, and then interlocutory relief in
the Kentucky Supreme Court, which was denied by Order entered
June 7, 2005.
After further briefing and oral argument, the
circuit court dismissed EnviroPower’s action by reaffirming the
findings and conclusions in its May 6, 2005, order that
EnviroPower did not have a legally protected interest which
would entitle it to intervene in the CON Case, and the PSC did
not abuse its discretion by denying intervention.
-6-
STANDARD OF REVIEW
At the outset, EnviroPower asserts this Court should
review the PSC’s decision de novo citing cases from other
agencies.
EnviroPower argues these cases establish a standard
for review of PSC's decision
support EnviroPower's
We find however, the cases do not
conclusion..
The Court’s standard for review of a decision by the
PSC is set forth by statute.
KRS 278.410(1) provides that an
order of the PSC can be vacated or set aside only if it is found
to be unlawful or unreasonable.
As Kentucky’s highest Court
declared in Kentucky Utilities Co. v. Farmers RECC, 361 S.W.2d
300, 301 (Ky. 1962), a PSC order may be appealed only when there
has been strict compliance with KRS 278.410(1) because, “this
statute provides the exclusive method by which an order of the
commission can be reviewed by the circuit court.”
The strict
compliance standard found in KRS 278.410(1) was subsequently
reaffirmed in American Beauty Homes Corp. v. Louisville and
Jefferson County Planning and Zoning Commission, 379 S.W.2d 450
(Ky. 1964).
Moreover, this Court has previously reviewed denials
of intervention in PSC proceedings.
In Inter-County Rural
Electric Cooperative Corporation v. Public Service Commission,
407 S.W.2d 127 (Ky. 1966), this Court held the PSC decision to
-7-
deny intervention was reviewed only for an abuse of discretion.
We find this appeal is governed by KRS 278.410(1), and the
commission’s decisions are reviewed only for an abuse of
discretion.
ARGUMENTS FOR REVERSAL
EnviroPower makes three arguments for reversal of
the circuit court:
(1) PSC's denial of intervention was
arbitrary and unlawful; (2) PSC's denial of intervention was
error because EnviroPower alleged fraud in award of bid; and (3)
denial of intervention deprived EnviroPower of procedural due
process and equal protection of the laws.
I.
Denial of Intervention as Arbitrary
EnviroPower argues it had a right to intervene in
this action under KRS 278.0201(1):
Upon the filing of an application for a
certificate, and after any public hearing
which the commission may in its discretion
conduct for all interested parties, the
commission may issue or refuse to issue the
certificate…(Emphasis added).
From this language EnviroPower insists it is an interested party
within the meaning of this statute and, as such, has a right to
intervene.
The Court does not read this statute in the manner
suggested by EnviroPower.
The statute is clear on its face and
it does not establish any specific rules defining an “interested
-8-
party.”
Furthermore, the controlling statute here is KRS
278.310(2), which requires the PSC to adopt rules governing
hearings and investigations before the commission.
The PSC has
acted to adopt specific rules governing all commission
proceedings.
Intervention is specifically addressed in 807 KAR
5:001, Section 3(8).
Under this regulation, the PSC retains the
power in its discretion to grant or deny a motion for
intervention.
The Kentucky Attorney General has a statutory
right to intervene.
KRS 367.150(8)(b).
The PSC’s exercise of discretion in determining
permissive intervention is, of course, not unlimited.
First,
there is the statutory limitation under KRS 278.040(2) that the
person seeking intervention must have an interest in the “rates”
or “service” of a utility, since those are the only two subjects
under the jurisdiction of the PSC.
Second, there is the
limitation in the PSC intervention regulation, 807 KAR 5:001,
Section 3(8), which requires the showing of either “a special
interest in the proceeding which is not otherwise adequately
represented,” or a showing that intervention “is likely to
present issues or to develop facts that assist the commission in
fully considering the matter without unduly complicating or
disrupting the proceedings.”
-9-
The PSC properly found that since “EnviroPower had
no role in either the development of EKPC’s bidding procedures
or the evaluation of the bids received,” and its intervention
was not likely to present issues or develop facts to assist the
PSC in fully considering the CON Case.
Moreover, the PSC noted
the intervention of Gallatin Steel, EKPC’s largest retail
customer, and the Attorney General was adequate to protect
EnviroPower’s interest.
In conclusion, the Court finds the
denial of intervention to EnvrioPower was neither unlawful nor
unreasonable.
II.
Allegations of Fraud
EnvrioPower has aggressively asserted that EKPC
engaged in a fraudulent RFP by skewing its evaluation to support
its own self-bid proposal.
However, the cases cited, Pendleton
Bros. Vending, Inc. v. Comm. of Ky. Finance and Administration
Cabinet, 758 S.W.2d 24 (Ky. 1988) and HealthAmerica Corp. of
Kentucky v. Humana Health Plan, Inc., 697 S.W.2d. 946 (Ky. 1985)
do not apply because in those cases the issue involved a claim
of fraud against a public agency as opposed to a claim of fraud
against a private entity such as EKPC.
EnviroPower then argues that under Kentucky common
law its allegations of fraud give it standing as a competitor
“to challenge the granting of a license or permit to another
-10-
competitor by an administrative agency,” citing PIE Mutual
Insurance Co. v. Kentucky Medical Insurance Co., 782 S.W.2d 51,
54 (Ky. App. 1990).
But even this authority is unavailing here
since the common law has been superseded by statutes expressly
limiting the PSC’s jurisdiction to “the regulation of rates and
service of utilities,” KRS 278.040(2), and further limiting the
participation in a CON Case to “interested parties,” KRS
278.020(1).
III.
Constitutional Claims
EnviroPower also contends the PSC’s denial of
intervention deprived it of its right to procedural due process
and equal protection of the law.
First, EnviroPower claims that it had a
constitutionally protected property interest in its
environmental permits, and by denying intervention, the PSC
impermissibly deprived EnviroPower of the value of the permits.
EKPC argues that EnviroPower’s interest created a mere
expectancy that it might develop a power plant project at a
future date.
Further, EKPC points out that EnviroPower never
had any contract with EKPC to develop power, and nothing
prevented EnviroPower from using its permits to establish other
projects.
The PSC argues that, as an agency, it had no
-11-
jurisdiction over the environmental permits issued to
EnviroPower.
“It is well established that in order to succeed in
either a procedural or substantive due process claim, such
claimant must demonstrate a legitimate entitlement to a vested
property interest.”
Kentucky Industrial Utility Customers, Inc.
v. Kentucky Utilities Co., 983 S.W.2d 493, 497 (Ky. 1998) citing
Board of Regents of State Colleges v. Roth, 408 U.S. 564, 577,
92 S.Ct. 2701, 2709, 33 L.Ed.2d 548 (1972).
Furthermore, a
“mere subjective expectancy” of a property interest is not
protected by procedural due process.
Perry v. Sindermann, 408
U.S. 593, 603, 92 S.Ct. 2694, 2700, 33 L.Ed.2d 570 (1972).
EnviroPower insists that it has a substantial and
concrete interest in the CON proceeding.
EnviroPower obtained
many of the critical permits requested to begin construction of
the new power plant.
The permits included a Construction
Certificate and an Air Quality Permit.
Both permits were
required before construction could begin.
EnviroPower also
argues its reputation will be tarnished if it cannot participate
in the CON proceedings.
These arguments are novel, but totally unpersuasive
in establishing a right to intervene in a CON proceeding.
EnviroPower could best be described as an unsuccessful bidder in
-12-
the RFP.
There were thirty-eight (38) other successful
bidders.
As a bidder, EnviroPower knew, or should have known,
that EKPC had made a self-build proposal.
PSC argues
EnviroPower had a mere expectancy and no fundamental property
right.
The Court agrees with EKPC’s analysis of this issue.
In the case at bar, it appears to the Court that
EnviroPower had indeed, nothing more than an expectancy interest
in the environmental permits.
When the PSC denied EnviroPower's
intervention in the CON proceeding, it did not render the
environmental permits worthless.
Furthermore, EnviroPower was
free to use its permits in seeking out another power plant
project.
Accordingly, we find that the Commission did not
deprive EnviroPower of any right to procedural due process.
Finally, EnviroPower contends that the PSC violated
its constitutional right to equal protection by allowing
Gallatin Steel to intervene in the CON proceeding, but denying
EnviroPower’s petition to intervene.
EKPC argues that the PSC’s
action is rationally related to the legitimate state interest of
regulating utility rates.
Appellees also point out that
EnviroPower has no actual legal interest in the PSC proceeding,
while Gallatin Steel is an interested ratepayer of EKPC.
agree with Appellee’s position.
We
EnviroPower, as a potential
merchant energy supplier, has far different interests that that
-13-
of Gallatin Steel, an energy consumer.
Gallatin’s interests
relate directly to the rates and services of EKPC, while
EnviroPower’s pecuniary interests relate solely to the marketing
of its wholesale power produced.
Consequently, no
constitutional violation occurred.
For these reasons, we respectfully affirm the
decision of the Franklin Circuit Court.
ALL CONCUR.
-14-
BRIEF FOR APPELLANT:
Stephen M. Soble
Washington, DC
Frederic J. Cowan
Louisville, KY
BRIEF AND ORAL ARGUMENT FOR
APPELLEE, PUBLIC SERVICE
COMMISSION OF KENTUCKY:
David S. Samford
Richard G. Raff
Frankfort, KY
BRIEF AND ORAL ARGUMENT FOR
APPELLEE, EAST KENTUCKY POWER
COOPERATIVE, INC.:
Charles Lile
Dale Henley
East Kentucky Power
Cooperative, Inc.
Winchester, KY
BRIEF AND ORAL ARGUMENT FOR
APPELLEE, GREGORY D. STUMBO,
ATTORNEY GENERAL OF KENTUCKY:
Dennis Howard
Elizabeth Blackford
Office of the Attorney General
Frankfort, KY
BRIEF AND ORAL ARGUMENT FOR
APPELLEE, GALLATIN STEEL COMPANY
Michael L. Kurtz
Cincinnati, OH
-15-
Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.