RELIABLE MECHANICAL, INC. v. NAYLOR INDUSTRIAL SERVICES, INC.; FIRST STAINLESS, INC.; AND STAINLESS STEEL INVEST, INC. FIRST STAINLESS, INC. AND STAINLESS STEEL INVEST, INC. v. NAYLOR INDUSTRIAL SERVICES, INC. AND RELIABLE MECHANICAL, INC. NAYLOR INDUSTRIAL SERVICES, INC. v. RELIABLE MECHANICAL, INC.; FIRST STAINLESS, INC.; STAINLESS STEEL INVEST, INC.
Annotate this Case
Download PDF
RENDERED:
SEPTEMBER 14, 2001; 10:00 a.m.
NOT TO BE PUBLISHED
C ommonwealth O f K entucky
C ourt O f A ppeals
NO.
2000-CA-001064-MR
RELIABLE MECHANICAL, INC.
v.
APPELLANT
APPEAL FROM CARROLL CIRCUIT COURT
HONORABLE STEPHEN L. BATES, JUDGE
ACTION NO. 92-CI-00158
NAYLOR INDUSTRIAL SERVICES, INC.;
FIRST STAINLESS, INC.; AND
STAINLESS STEEL INVEST, INC.
AND
NO.
2000-CA-001242-MR
FIRST STAINLESS, INC. AND
STAINLESS STEEL INVEST, INC.
v.
NO.
CROSS-APPELLEES
2000-CA-001250-MR
NAYLOR INDUSTRIAL SERVICES, INC.
v.
CROSS-APPELLANTS
CROSS-APPEAL FROM CARROLL CIRCUIT COURT
HONORABLE STEPHEN L. BATES, JUDGE
ACTION NO. 92-CI-00158
NAYLOR INDUSTRIAL SERVICES, INC. AND
RELIABLE MECHANICAL, INC.
AND
APPELLEES
CROSS-APPELLANT
CROSS-APPEAL FROM CARROLL CIRCUIT COURT
HONORABLE STEPHEN L. BATES, JUDGE
ACTION NO. 92-CI-00158
RELIABLE MECHANICAL, INC.;
FIRST STAINLESS, INC.;
STAINLESS STEEL INVEST, INC.;
AND NORTH AMERICAN STAINLESS, L.P.
CROSS-APPELLEES
OPINION
AFFIRMING
** ** ** ** **
BEFORE:
GUDGEL, CHIEF JUDGE; EMBERTON AND SCHRODER, JUDGES.
SCHRODER, JUDGE:
This case concerns a construction contract
between First Stainless, Inc. and Stainless Steel Invest, Inc.
(NAS)1 and Reliable Mechanical, Inc. (Reliable) for work
performed on a stainless steel processing facility in Carroll
County, Kentucky.
Further at issue is a subcontract between
Reliable and Naylor Industrial Services, Inc. for the pickling
and flushing of hydraulic and lubricating pipe systems in a
sector of the facility.
All parties asserted claims for breach
of contract and/or unjust enrichment against each other.
The
trial court entered its order finding in favor of Naylor on its
claims and against NAS and Reliable.
Having reviewed the record
and applicable law, it is our opinion that the trial court
correctly concluded the issues before it; hence, we affirm.
The principal controversy between the parties centers
on the contract between NAS and Reliable calling for Reliable to
perform construction services on the Sendzimir stainless steel
rolling mill (Z-Mill).2
Reliable was to supply and install
hydraulic and lubricating oil pipe systems for the Z-Mill as well
1
First Stainless, Inc. and Stainless Steel Invest, Inc.
formed the partnership North American Stainless.
2
Reliable entered into five (5) separate contracts with NAS
for performance of various jobs on the stainless steel processing
facility of which the Z-Mill contract was one.
-2-
as perform pre-operational chemical cleaning and of pipe systems
they installed.
The cleaning process consisted of pickling and
flushing the systems.
Simply stated, this process involved the
introduction of a chemical solution in the pipe systems to remove
rust, scale or other contaminants (pickling) followed by the high
speed circulation of an oil based solution to remove debris
(flushing).
Since Reliable had no experience with the pickling
and flushing operations, it subcontracted those duties out to
Naylor, a Texas corporation.
Naylor proceeded with cleaning and flushing the pipes
in late December 1991, completing the job in early January 1992.
As required by the subcontract, a NAS representative inspected
and approved Naylor’s performance at the conclusion of each phase
of the work, granting acceptance and signing off on the entire
project upon completion.
Approximately one week following
Naylor’s performance, NAS supervisory employees returned from
their Christmas holiday in Spain.
Upon visual inspection, these
officials found debris particles in the pipes and “rust blooms”
on the top of some of the pipes.
Based on the inspection, NAS
determined that the hydraulic system had been correctly pickled
but not properly flushed and the lube oil system had not been
either correctly pickled or flushed.
NAS then demanded that
Reliable re-pickle and re-flush the lube oil system and re-flush
the hydraulic system.
Consequently, Reliable threatened to
withhold payment from Naylor on the subcontract if it did not
return to re-clean the system as originally contracted.
Naylor
did so only after Reliable agreed to pay $50,000 toward the
-3-
original contract price with the balance of $53,750 due if it was
determined that the first cleaning had satisfied the objective
cleanliness criteria.
Following completion of the project, NAS refused to pay
Reliable’s contract balances asserting, inter alia, that the
necessity of conducting the second cleaning and flushing caused a
delay in operation of the Z-Mill resulting in lost profits.
Therefore, on November 11, 1992, Reliable filed its complaint
against NAS alleging breach on numerous contracts between those
parties.
In turn, NAS filed a counterclaim seeking recovery of
more than $11 million dollars claimed lost due to the delays in
completing the pipe cleaning.
Reliable then filed a third-party
complaint against Naylor seeking indemnification for any sums
awarded to NAS.
As a result, Naylor filed a counterclaim against
Reliable and cross-claim against NAS seeking to recover its
additional costs associated with the second pickling and flushing
job, and alleging that NAS was unjustly enriched by the
performance of those services.
NAS filed a cross-claim against
Naylor for whatever costs it incurred as a result of the second
cleaning operation.
Likewise, included in Reliable’s complaint
against NAS and third-party claim against Naylor was a claim for
costs incurred in the performance of the second cleaning.
By agreement of the parties, the entire matter was
submitted to the trial court for a decision based upon the
extensive record developed through discovery.
On March 8, 2000,
the court rendered its findings of fact, conclusions of law and
order wherein it awarded Naylor its outstanding sum due on the
-4-
original subcontract with Reliable ($53,750) plus pre- and postjudgment interest.
Likewise, the court concluded that Naylor was
entitled to recover $103,750 for the second cleaning job;
however, the court denied any pre-judgment interest on that sum.
The claims of Reliable and NAS were dismissed.
From that
judgment, these appeals ensued.
Before this Court, NAS argues: (1) Naylor is not
entitled to recover from NAS on the basis of quantum meruit; (2)
the trial court erred in permitting Naylor to pursue its
counterclaim since Naylor never obtained a certificate of
authority to transact business in Kentucky; and (3) the court
erred in dismissing NAS’s claim for damages against Reliable.
Reliable contends: (1) the trial court erred in refusing to
indemnify it from NAS for the monetary award to Naylor; and (2)
Reliable was entitled to its costs associated with the second
pipe system cleaning.
Naylor counters that the trial court erred
in calculating the amount owed as a result of the second cleaning
procedure and by failing to award pre-judgment interest on that
sum.
We first address the issue of whether Naylor was
required to obtain a certificate of authority to transact
business in Kentucky.
KRS 271B.15-020(1) provides that “[a]
foreign corporation transacting business in this state without a
certificate of authority shall not maintain a proceeding in any
court in this state until it obtains a certificate of authority.”
However, KRS 271B.15-010 contains a list of exceptions, albeit
not exhaustive, of what activities do not constitute “transacting
-5-
business.”
Specifically, “conducting an isolated transaction
that is completed within thirty (30) days and that is not one (1)
in the course of repeated transactions of a like nature” does not
trigger the requirement for a certificate of authority.
KRS
271B.15-010(j).
While technically on the job site for 32 days, Naylor
actually performed its duties under the subcontract in 17 days
(December 16, 1991 - January 3, 1992).
The remaining 15 days
were occupied by one or two of Naylor’s employees loading or
unloading equipment for purposes of transportation.
Likewise,
Naylor does not maintain an office, telephone listing, employees,
agents or inventory in the state of Kentucky.
Similarly, it does
not own any property or transact continuous or ordinary business
within the state.
Naylor does not advertise, pay taxes or
maintain a bank account within Kentucky’s borders.
Rather,
Naylor’s presence in this state was for the limited purpose of
conducting the isolated transaction at the NAS plant.
As such,
it was not obligated to obtain a certificate of authority to
conduct business as contemplated by KRS 271B.15-020.
See
Commonwealth ex rel. Stephens v. Nat’l Steeplechase & Hunt
Assoc., Inc., Ky. App., 612 S.W.2d 347 (1981).
Moreover, Naylor has not voluntarily availed itself of
the rights and privileges of this jurisdiction by maintaining a
legal proceeding.
Conversely, Naylor was hauled into the
Kentucky court vis à vis Reliable filing a third-party complaint
against it.
The statutory prohibition of a non-certified
corporation bringing suit in this state does not address the
-6-
assertion of a compulsory counterclaim or cross-claim such as
those filed by Naylor.
It is unlikely that the legislature
intended to permanently preclude a foreign corporation the right
to ever assert those claims under circumstances such as those in
the matter sub judice.
Although never addressed under the
Kentucky statute, see Clayton Carpet Mills, Inc. v. Martin
Processing, Inc., 563 F.Supp. 288 (N.D. Ga. 1983), wherein the
Court held that a foreign corporation that did not possess a
certificate of authority when the action was commenced could,
nonetheless, file a compulsory counterclaim since it would
otherwise be permanently deprived of the right to assert its
claim.
The statute in issue before the Georgia Court was
sufficiently similar to KRS 271B.15-020(1) to permit the drawing
of an analogy thereto.3
It is our opinion, therefore, that Naylor was not
required to obtain a certificate of authority to transact
business in the state of Kentucky as it qualified for the
isolated transaction exemption from that requirement.
271B.15-010.
KRS
Further, even if Naylor were subject to the
certificate of authority requirement contained in KRS 271B.15-
3
The statute in issue was O.C.G.A. § 14-2-331(b) which
provided:
No foreign corporation that under this
chapter is required to obtain a certificate
of authority shall be permitted to maintain
any action, suit, or proceeding in any court
of this state unless before commencement of
the action it shall have obtained such a
certificate.
-7-
020, it is not precluded from asserting a compulsory counterclaim
or cross-claim under the terms of that statute.
We next address NAS’s allegation that Naylor was not
entitled to recover from it on the basis of quantum meruit.
The
trial court held NAS and Reliable jointly and severally liable to
Naylor in the amount of $103,750 as costs for the second
cleaning.
NAS contends that there is no privity of contract
between Naylor and itself and recovery under the theory of
quantum meruit is inappropriate since Naylor should look to its
subcontractor, Reliable, for payment of its costs.
We disagree.
A contract implied by law permits recovery in quantum
meruit where one party has been unjustly enriched by another
party’s performance.
The theory is not premised on an actual
contract but is a legal fiction created to permit recovery where
justice and equity so require, as if promises had been made.
The
courts invent the fiction as though the promises had, in fact,
been made in order to permit reclamation from those unjustly
enriched.
“Furthermore, recovery quantum meruit may be had
irrespective of the intentions of the parties, and sometimes even
in violation of them.”
Perkins v. Daugherty, Ky. App., 722
S.W.2d 907, 909 (1987).
We believe that the evidence contains sufficient
support for the trial court’s determination that Naylor should
recover from NAS in quantum meruit.
The record reflects that the
subcontract between Reliable and Naylor provided that Naylor
would perform to the satisfaction of NAS.
Specifically, the
subcontract stated that “it is agreed that [Naylor] will meet the
-8-
owner’s level of satisfaction, not to exceed the requirement of
the contractor’s written specifications before considering the
job complete.”
The “written specification” referred to the
objective cleanliness criteria set forth in Naylor’s original
proposal.
Thus, while the subcontract obligated Naylor to
perform to NAS’s satisfaction, it further provided that NAS could
not withhold conferring acceptance after the objective
cleanliness criteria were met.
Further, Naylor’s proposal which
was incorporated into the subcontract specifically stated that
Naylor’s bid was for one mobilization and that upon acceptance by
NAS, Naylor would not return its personnel and equipment to the
plant.
Due to Naylor having to perform subject to the
acceptance of NAS, Michael Brate, an NAS engineer, was designated
as the representative to approve Naylor’s work.
Although NAS
contends that Brate was not authorized to accept the work, the
written record clearly refutes any such contention.
Rather,
unquestionably, Brate was the NAS-designated representative
cloaked with apparent, if not actual, authority to scrutinize the
processes being performed by Naylor.
As the designated
representative, Brate signed Naylor’s log book upon completion of
every phase of the project.
On January 3, 1992, Brate signed a
statement acknowledging that “North American Stainless (Michael
Brate) . . . accepts systems and states that Naylor’s contractual
commitments have been satisfied.”
Relying on this final
approval, Naylor demobilized its equipment and personnel.
Thereafter, the pipes remained empty for several days, making
-9-
them susceptible to contamination from atmospheric conditions at
the plant.
As discussed, supra, NAS subsequently revoked its
acceptance, insisting that the pickling and flushing processes
were flawed.
However, the totality of the evidence reveals that
the contamination in the lubrication system was the result of
either NAS’s or Reliable’s failure4 to fill the pipe with oil
immediately upon completion of the cleaning.
With regard to the
hydraulic system, Naylor agreed to re-flush a portion of same
only after NAS agreed that it would assume financial
responsibility for Naylor’s costs should Naylor prove that the
system satisfied the original specification.
After the hydraulic
system was flushed, oil samples were taken and a microscopic
examination of the samples indicated that the system satisfied
the original specification.
results.
NAS’s own test produced the same
Nonetheless, NAS insisted that substitute testing be
performed and an additional test be conducted following the
system’s attachment to another pipeline.
Naylor rejected this
proposal due to concern that the entire system would be
contaminated by hooking it up to the other pipeline, which Naylor
perceived to be dirty.
As such, Reliable and NAS completed the
subsequent work on the hydraulic system while Naylor moved on to
re-pickling and re-flushing the lubrication system.
4
Reliable contends that it was unable to attach the system
to another piping system due to NAS’s failure to have that
portion of the plant completed. NAS rebuts that it was
Reliable’s duty to assure that the pipes were properly maintained
until attachment was available, specifically by introducing
nitrogen into the system.
-10-
In sum, NAS’s agent, Michael Brate, approved and signed
off on Naylor’s performance under the subcontract, that is, that
the cleaning and flushing of the piping systems conformed to
NAS’s specifications for approval.
As observed by the trial
court, a principal is bound by and liable for the acts of its
agent performed within the scope of the agent’s employment.
City
of Covington v. Reynolds, 240 Ky. 86, 41 S.W.2d 664 (1931).
The
court concluded, and we agree, that the systems were cleaned in
compliance with the subcontract the first time.
However, even if
the pipe systems were not within the objective cleanliness
criteria following the first cleaning, Naylor is entitled to
payment for its performance by virtue of Brate’s acceptance of
that work.
The preponderance of proof contained in the record
firmly establishes that all parties involved considered Brate to
have had at least apparent authority to act on NAS’s behalf.
As
such, Naylor is entitled to payment for its second cleaning
procedure in quantum meruit.
The services rendered during this
performance enured to NAS’s benefit without any remuneration to
Naylor.
Naylor re-mobilized its equipment and personnel to the
NAS plant and re-serviced the pipe systems, the contamination of
which had occurred by no fault of Naylor’s.
NAS recognized the
benefit of this service through the enhancement of its production
plant as a whole.
Equity and justice, therefore, require that
NAS compensate Naylor for this accrued benefit.
We next address Naylor’s contention that the court
wrongfully calculated the amount it was to recover for the second
cleaning job and that the court failed to award pre-judgment
-11-
interest on that sum.
Specifically, Naylor claims that it was
entitled to recover $204,875 for the second cleaning.
It
computed this amount based upon the rates and fees set forth in
its proposal, multiplied by the number of man hours and equipment
information documented in Naylor’s logs.
The court, however,
found that Naylor was entitled to $103,750 in damages for its
repeat performance, stating:
The Court finds no convincing proof was
provided by Naylor as to why the second job
would be double the cost of the first. This
is particularly true since it did not redo,
for good reason, the hydraulic system the
second time. Having found for Naylor on its
claims against both Reliable and NAS, their
claims against Naylor must fail.
The trial court, sitting as the trier of fact, is
vested with the discretion to ascertain the reasonableness of the
amount of damages claimed.
Where the court acts as fact finder,
its findings will not be disturbed unless clearly erroneous.
Faulkner Drilling Co. v. Gross, Ky. App., 943 S.W.2d 634 (1997).
If supported by substantial evidence the trial court’s findings
will not be deemed erroneous.
Id.
In our opinion, the trial
court’s determination that Naylor could not justify expenses
exceeding twice the amount of its original contract price, where
one-half the amount of work was required, is supported by the
record.
Therefore, we adjudge no abuse of this discretion and
the trial court’s decision will not be disturbed. CR 52.01.
Likewise, the damages claimed by Naylor as a result of
its second performance were an unliquidated sum.
In such cases,
the award of pre-judgment interest is left to judicial
discretion.
The court is not required to grant pre-judgment
-12-
interest but may do so if, in its discretion, it believes under
the facts and circumstances of the case that equity and justice
require such an award.
Nucor Corp. v. General Elec. Co., Ky.,
812 S.W.2d 136 (1991).
We believe the trial court acted within
its discretion and its judgment will not be altered on this
issue.
Finally, we discuss the various claims asserted by both
NAS and Reliable.
Collectively, our review of the record accords
that these remaining arguments were properly disposed of by the
trial court and we adopt its well reasoned opinion, to wit:
14.
Concerning the claims by Reliable
and by NAS for damages against each other as
well as the establishment of which of those
parties is responsible for the damages of
Naylor, the Court finds the parties are
jointly and severally responsible.
NAS accepted the performance of
Naylor through its agent Michael Brate and
thereafter required Reliable to have Naylor
return to the site for the second time. The
Court finds that the changing of
specifications relative to the hydraulic
system upon the second inspection when Naylor
returned was unreasonable under the
circumstances. Furthermore, after accepting
the lubrication system through its
representative Brate, NAS had no right to
require Reliable to have Naylor return
regarding that system. For that reason NAS
injected itself into the agreement between
Naylor and Reliable and should be held
accountable for damages resulting therefrom,
being Naylor’s expenses. As previously
stated, a quantum mer[u]it recovery is
warranted against NAS by Naylor under the
facts herein.
Reliable is also responsible for
Naylor’s damages, despite the previously
referenced liability of NAS, for requiring
Naylor to return to the site for not properly
preserving the system. Reliable is
ultimately accountable to NAS for all parts
-13-
of the contracts it undertook regardless of
whether Reliable did the work or subbed it
out as here. It was Reliable’s
responsibility to have a properly maintained
system ready to connect to the rest of the
mill when the time came. It is very
doubtful, under the facts in this case, if
Reliable was prepared to introduce the oil or
nitrogen to preserve the system even if it
had been available. In other words, some of
the problems that occurred with regard to
Naylor being required to return to the site
resulted from the overlooked areas that often
occur in construction contract situations.
Since Reliable had the primary contract with
NAS, it was its responsibility to stay on top
[of] any of those gaps and responsibilities,
and make sure the system was either put in
operation once Naylor left the site or to
preserve the system in an appropriate
fashion. It was further the responsibility
of Reliable to clean out all the traps and
other areas that might have resulted in
contamination to the system, and which the
Court finds was a factor that resulted in the
problems with the lube system. For that
reason, the Court finds that any damages that
either NAS or Reliable may have suffered, and
those damages are clearly suspect based on
this Court’s review, to be off-set and will
award neither damages against the other.
15.
There is insufficient evidence to
support NAS’s claim that Reliable lost or
damaged materials. Their argument that
Reliable should be held responsible because
it did not come forward to challenge NAS’s
assertion that it had lost or damaged
materials require Reliable to prove a
negative. Kentucky law does not place such a
burden on a party defending a claim. Ash v.
Marsh, Ky., 412 S.W.2d 853 (1997); Jones v[.]
Vitumuous Casualty Corp., Ky., 821 S.W.2[d]
798 (1992). Therefore NAS’s claim against
Reliable for the lost or damage [sic]
materials has not been proven.
16.
NAS has also failed to establish
any legal or contractual basis for its claim
that it is entitled to funds for steel not
used by Reliable in construction of the
structural supports. The contract clearly
calls for a lump sum to be paid to Reliable
for performing specified work and did not set
-14-
unit prices for the amount of steel saved or
used. Furthermore, even if a contractual or
legal basis existed, NAS has waived or is
estopped to recover any “saving” from
Reliable. Finally NAS has failed to
establish that Reliable has saved any money
by the installation of the pipe supports in a
different manner than originally shown in the
drawing. Therefore, NAS has failed to prove
its claim in regard to this issue.
For the foregoing reasons the judgment of the Carroll
Circuit Court is affirmed.
EMBERTON, JUDGE, CONCURS.
GUDGEL, CHIEF JUDGE, CONCURS IN RESULT ONLY.
BRIEF FOR APPELLANT/CROSSAPPELLEE, RELIABLE MECHANICAL,
INC.:
BRIEF FOR APPELLEE/CROSSAPPELLEE/CROSS-APPELLANT,
NAYLOR INDUSTRIAL SERVICES,
INC.
Thomas E. Roma, Jr.
Louisville, Kentucky
Cornelius E. Coryell, II
Louisville, Kentucky
BRIEF FOR APPELLEES/CROSSAPPELLANTS/CROSS-APPELLEES,
FIRST STAINLESS, INC.;
STAINLESS STEEL INVEST, INC.
AND NORTH AMERICAN STAINLESS
L.P.:
Carl D. Edwards, Jr.
William H. Jones, Jr.
Christopher A. Dawson
Ashland, Kentucky
-15-
Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.