CUMBERLAND SURETY INSURANCE COMPANY, INC. v. LANDRUM & SHOUSE
Annotate this Case
Download PDF
RENDERED: May 25, 2001; 10:00 a.m.
NOT TO BE PUBLISHED
C ommonwealth O f K entucky
C ourt O f A ppeals
NO.
1999-CA-001660-MR
CUMBERLAND SURETY INSURANCE
COMPANY, INC.
APPELLANT
APPEAL FROM JEFFERSON CIRCUIT COURT
HONORABLE THOMAS KNOPF, JUDGE
ACTION NO. 97-CI-002404
v.
LANDRUM & SHOUSE
APPELLEE
OPINION
AFFIRMING
** ** ** ** **
BEFORE:
JUDGE1.
BARBER, JUDGE; SCHRODER, JUDGE; AND MARY COREY, SPECIAL
BARBER, JUDGE: This case involves application of the statute of
limitations to a claim of legal negligence.
In 1992, David
Engineering & Construction was awarded a contract to renovate the
Beecher Terrace Housing Project in Louisville, Kentucky.
David
Engineering & Contracting hired a subcontractor, Master
Mechanical & Construction, Inc., to replace the plumbing fixtures
for the project.
1
Master Mechanical posted a $50,000 “labor only”
Senior Status Judge Mary Corey sitting as Special Judge by
assignment of Chief Justice pursuant to Section 110(5)(b) of the
Kentucky Constitution.
bond, which was underwritten by Appellant, Cumberland Surety
Insurance Company(“Cumberland Insurance”).
When the need for
additional plumbing work was discovered, David Engineering &
Construction was required to competitively bid the extra work.
Master Mechanical submitted the lowest bid.
David Engineering & Construction believed that Master
Mechanical was in default under the earlier subcontract.
David
Engineering obtained a legal opinion letter from Appellee,
Landrum & Shouse (“Landrum & Shouse”), to that effect.
The law
firm counseled David Engineering to accept Master Mechanical’s
low bid, arguing that litigation might result if the bid was not
accepted.
Landrum & Shouse conferred with Master Mechanical’s
attorney, asking that earlier defects be cured.
David Engineering required Master Mechanical to obtain
a $1,145,000.00 bond as a condition for accepting the second bid.
Master Mechanical promptly posted the requested performance bond.
David Engineering also required Master Mechanical to enter into a
Memorandum Agreement in which Master Mechanical admitted the
earlier defects, and agreed that the new contract could be
terminated if Master Mechanical defaulted in any way.
The
Memorandum Agreement also contained a provision permitting David
Engineering to proceed against the surety in case of a default.
Landrum & Shouse argues that the Memorandum Agreement was
intended as a “red flag”, to alert any responsible bonding
company to the fact that Master Mechanical was already in
default.
-2-
The deposition testimony of David Engineering’s
president, David Holobaugh, states that he wanted to call
Cumberland Insurance to “warn them” that he believed Master
Mechanical would default on the Agreement.
Cumberland Insurance
asserts that Landrum & Shouse knew that Cumberland Insurance
would be sued due to Master Mechanical’s inability to comply with
the terms of the Agreement, but failed to warn Cumberland
Insurance of this, and in fact advised Holobaugh not to call
Cumberland Insurance.
In April 1994, David Engineering sent notice of default
to Master Mechanical.
David Engineering then terminated Master
Mechanical’s subcontract in June 1994.
David Engineering then
gave Cumberland Insurance three days to perform as surety on the
bond.
Cumberland Insurance consented to permit Landrum & Shouse
to act as counsel for both David Engineering and Cumberland
Insurance, after being advised of a “potential conflict” between
the parties.
Cumberland made a partial payment under the bonds,
but refused to make full payment.
Cumberland Insurance asserts that advising a client as
to a “potential conflict” is not sufficient to put Cumberland
Insurance on notice that there had been legal negligence.
Cumberland Insurance argues that its consent to joint
representation cannot be considered true consent or a waiver, as
it was not told that there was an actual and ongoing conflict
between its interests and those of David Engineering.
SCR 1.7(b)
forbids an attorney from representing one client if doing so will
materially limit the lawyer’s responsibilities to another client.
-3-
Cumberland Insurance argues that Landrum & Shouse failed to
comply with this rule of professional conduct.
Cumberland
Insurance also asserts that Landrum & Shouse failed to comply
with SCR 1.7(b)(2), mandating an explanation to the client of the
implications of joint representation, and the advantages and
risks involved in such representation.
Landrum & Shouse withdrew from the joint representation
once it became clear that David Engineering and Cumberland
Insurance would not resolve their differences without litigation.
David Engineering retained other counsel to conduct litigation.
In this separate action, David Engineering sued Cumberland
Insurance over the bond.
This separate action was eventually
ended by a financial settlement between the parties.
Cumberland Insurance argues that, during the discovery
process in that separate litigation, they discovered that Landrum
& Shouse had drawn up the Memorandum Agreement between David
Engineering and Master Mechanical.
Cumberland Insurance
characterized this as a “win-win” strategy for David Engineering.
Cumberland Insurance asserts that Landrum & Shouse “sabotaged”
them to aid David Engineering.
The record reflects that in May 1994 Cumberland
Insurance was made aware of Landrum & Shouse’s representation of
David Engineering, and waived any objection to the joint
representation.
In June 1994, communications between Cumberland
Insurance and Landrum & Shouse revealed the existence of the
Memorandum Agreement drawn up by Landrum & Shouse, and referring
to Master Mechanical’s past defaults.
-4-
Based on these facts, the
trial court found that Cumberland Insurance had knowledge of the
injury by June 23, 1994.
The trial court stated Cumberland
Insurance’s actions following that date show that Cumberland
Insurance knew or should have known of the alleged legal
negligence.
The trial court found that on October 21, 1994, when
Cumberland Insurance made a partial payment on its obligation as
surety for Master Mechanical damages were not merely probable or
speculative, but were actual and known.
For this reason, the
trial court ruled that this date was the date on which the
limitations period began to run.
Cumberland Insurance denied
this knowledge, and claims that it did not discover the
Memorandum Agreement until April 17, 1995.
Cumberland Insurance
also argues that the damages were not certain until final
settlement of the action, on March 28, 1997.
Landrum & Shouse entered into a tolling agreement with
Cumberland Insurance on October 25, 1995.
This agreement tolled
the limitations period until March 28, 1997.
The tolling
agreement provided that Landrum & Shouse expressly reserved any
statute of limitations defense that they had at the time of its
signing.
On May 5, 1997, following settlement of David
Engineering’s litigation against Cumberland Insurance, Cumberland
Insurance filed the underlying legal negligence action against
Landrum & Shouse.
Landrum & Shouse moved for summary judgment claiming
that the applicable statute of limitations barred Cumberland
Insurance’s suit.
The trial court entered summary judgment in
favor of Landrum & Shouse, stating Cumberland Insurance should
-5-
have discovered that it was wronged no later than October 1994,
the date on which the partial payment was made under the
performance bond.
Cumberland Insurance argued that entry of summary
judgment was improper, as Landrum & Shouse failed to show that
Cumberland Insurance could not prevail at trial under any
circumstances.
Cumberland Insurance asserts that the applicable
statute of limitations in the underlying action did not begin to
run until Cumberland Insurance’s claims were fixed and certain.
Cumberland Insurance claims that the trial court fixed an
incorrect date as to when the statute of limitations began to
run.
The trial court found when Landrum & Shouse wrote to
Cumberland on behalf of David Engineering, on June 23, 1994,
Cumberland was then put on notice as to the existence of the
Memorandum Agreement, and the fact that Landrum & Shouse
represented both Cumberland and David Engineering.
The trial
court stated that the statute of limitations began to run the
date that Cumberland Insurance tendered partial payment on the
bonds, which was October 21, 1994.
The trial court stated that
on that date the damages were “not merely probably, but had
become a fact and thus, commenced the limitations period to run.”
Therefore, the trial court held that on the date on which the
parties entered into a tolling agreement, October 26, 1995, the
statute of limitations had already run.
Cumberland Insurance asserts that the trial court erred
in applying the discovery rule to determine when the applicable
-6-
limitations began to run.
Cumberland Insurance states that the
“occurrence rule” should have been applied in its stead.
Cumberland Insurance claims that because there was no
“occurrence” as of October 21, 1994, and that on that date
damages were not fixed and certain, the limitations period could
not begin to run.
Cumberland Insurance cites Alagia, Day,
Trautwein & Smith v. Broadbent, Ky., S.W.2d 121 (1994), holding
that until a legal harm becomes fixed and non-speculative, the
statute of limitations does not begin to run.
A final settlement was made between Cumberland
Insurance and David Engineering on March 28, 1997.
Cumberland
Insurance claims that it was on that date that the statute of
limitations began to run.
Cumberland Insurance argues that the
discovery rule applied only if the discovery comes after the
occurrence.
Cumberland Insurance states that an occurrence
cannot be found until the damages are fixed and certain.
Cumberland claims that on October 21, 1994, when it
made the payment of $84,392.00 to David Engineering it was acting
under the reservation of rights, and at the time disputed that it
was obligated to pay at all.
Cumberland Insurance’s letter to
David Engineering does not contain a reservation of rights
sufficient to support the allegation that Cumberland Insurance
did not know of its injury at that time, or was disputing its
duty to pay any damages at all.
This reservation of rights
stated “we reserve the right to make deductions on future
payments . . . should we determine after an audit and
investigation that any of the charges are not appropriate.”
-7-
This
sentence shows that Cumberland Insurance was reserving the right
to question the sum of payments owed, not the fact that payment
was owed.
In the same letter, Cumberland Insurance also admitted
liability stating, “we will acknowledge our obligation to pay for
certain of that work . . . .”
The terms of the transmittal
letter do not constitute an unequivocal reservation of rights
sufficient to deny knowledge of an occurrence triggering the
limitations period.
No further payments were made by Cumberland
until final settlement of the action.
In the alternative, Cumberland Insurance argues that if the
discovery rule is applied, the applicable date on which the
limitations period began to run was April 17, 1995, the date on
which Cumberland Insurance obtained sufficient information as to
be on notice that Landrum & Shouse had elevated David
Engineering’s interests above those of Cumberland Insurance.
Cumberland Insurance cites Gill v. Warren, Ky., 474 S.W.2d 377
(1971), arguing that the date on which one discovers a wrong is a
question of fact, and thus inappropriate for resolution on
summary judgment.
Cumberland Insurance also argues that the
discovery rule should be tolled when the parties are in a
confidential relationship and “do not have the reasons or
occasions to check on each other that would exist if they were
dealing at arms’ length.”
S.W.2d 414, 415 (1988).
Shelton v. Clifton, Ky. App., 746
Cumberland Insurance asserts that, had
it known of the Memorandum Agreement and been informed of Master
Mechanical’s prior default, it would not have issued the
$1,145,000.00 bond.
Regardless of whether Cumberland Insurance
-8-
would have issued the bond had it been fully informed of Master
Mechanical’s earlier performance, this fact does not operate to
alter the date on which the limitations period began to run.
KRS 413.245 reads, in pertinent part:
[A] civil action brought in tort or contract,
arising out of any act or omission in
rendering, or failing to render, professional
services for others shall be brought within
one(1) year from the date of the occurrence
or from the date when the cause of action
was, or reasonably should have been
discovered by the party injured.
Id.
A statute of limitations begins to run when the party
injured has the right and capacity to sue.
Lexington-Fayette
Urban County Government v. Abney, Ky. App., 748 S.W.2d 376
(1988).
A triggering effect cannot take place until a
cognizable, non-speculative loss has been suffered.
Tomlinson v.
Siehl, Ky., 459 S.W.2d 166 (1970).
Two separate rules are used to toll limitations
periods.
The “discovery rule” tolls a statute of limitations
period until such time as the injured party “knows or in the
exercise of reasonable care, should know, that the injury has
occurred.”
Gray v. Commonwealth Transp. Cabinet, Department of
Hwys., Ky. App., 973 S.W.2d 61, 62 (1997).
Under this rule,
Cumberland knew or should have known of the injury as of the date
it was provided with reference to the Memorandum Agreement, that
being June 1994.
At the very latest, it should be held to have
discovered the injury on the date in which it was required to
make partial payment under the bond, that being October 23, 1994.
The limitations period triggered on that date expired prior to
-9-
the parties’ entering into the tolling agreement.
Under the
discovery rule, the action is clearly time barred, and the trial
court’s dismissal was correct.
Under the “occurrence rule”, claimed by Cumberland
Insurance to have tolled the limitations period in this action,
the limitations period begins to run as of the date on which the
injured party could “justifiably claim that the entire damage was
caused by counsel’s failure, for which he might seek a remedy.”
Michels v. Sklavos, Ky., 869 S.W.2d 728, 732 (1994).
Citing this
case, Cumberland argues that it was the date on which final
settlement was made in the action between David Engineering and
Cumberland Insurance that triggered the running of the
limitations period.
In Michels, supra, unlike the present case,
the cause of action was for “litigation” negligence, where the
attorney’s negligence in preparation and presentation of a
litigated claim resulted in the failure of an otherwise valid
claim.
Necessarily, in such an action, the occurrence and known
harm does not take place until the jury’s verdict is rendered.
Id. at 730.
The Michels case differs greatly from the present
one, where negligence was known and the negligent occurrence took
place prior to the institution of any litigation.
Cumberland Insurance’s argument that the underlying
litigation had to be complete prior to commencement of the
limitations period must also fail because the date of the
occurrence, when Cumberland Insurance could justifiably claim
that the entire damage was caused by the alleged legal negligence
of Landrum & Shouse, was the date on which Cumberland realized
-10-
that it owed money under a suspect bond issuance.
“[T]he use of
the term ‘occurrence’ in KRS 413.245 indicates a legislative
policy that there should be some definable, readily ascertainable
event which triggers the statute.”
Northwestern Nat. Ins. Co. v.
Osborne, 610 F. Supp. 126, 128 (D.C. Ky. 1985).
When Cumberland
made partial payment the triggering occurrence took place, even
though Cumberland asserts that it would not have issued the bond
had Landrum & Shouse informed it of the prior defaults by Master
Mechanical.
As this court stated in Barker v. Miller, Ky. App., 918
S.W.2d 749, 751 (1996), the damages are fixed under the
occurrence rule when the party knows the possible extent of the
harm caused by the legal negligence, not when the underlying
litigation is completed.
In that case, the Court of Appeals
found that the occurrence date was when the plaintiff’s motion
for discretionary review was denied by the Kentucky Supreme
Court, and not the date on which the plaintiff’s time to file a
motion with the United States Supreme Court expired.
In cases where the party claiming injury has incurred a
financial loss, the occurrence rule holds that the limitations
period begins to run on the date the injured party knew of the
financial loss.
235 (1995).
Meade Co. Bank v. Wheatley, Ky., 910 S.W.2d 233,
When Cumberland Insurance knew that it would suffer
a loss under the bond, and made partial payment in excess of
$84,000.00, the limitations period for the legal negligence claim
began to run.
Cumberland Insurance had personal knowledge of the
date on which that occurrence took place, and should have been
-11-
aware that the occurrence triggered any applicable limitations
period.
Real Estate Marketing, Inc., v. Franz, Ky., 885 S.W.2d
921 (1994).
Limitations periods:
[A]re creatures of statute which are intended
by the legislature to bring finality to the
legal process. Hazel v. General Motors
Corp., 863 F. Supp. 435, 438(W. D. Ky. 1994).
‘Thus, limitations act arbitrarily, sometimes
extinguishing otherwise viable claims and at
other times extinguishing speculative
claims.’
Barker v. Miller, Ky. App., 918 S.W.2d 749, 751 (1996),
additional citation to authority deleted.
In the present case,
the limitations period expired prior to the execution of the
tolling agreement.
For this reason, any action by Cumberland
Insurance against its legal counsel with regard to the issuance
of the bond and the joint representation is time-barred.
We
affirm the trial court’s dismissal of the action.
Cumberland Insurance’s attempt to argue that the date
on which a limitations period begins to run is a question of fact
to be determined by the jury is in error.
is a question of law.
A limitations period
Perkins v. Northwestern Log Homes, Ky.,
808 S.W.2d 809 (1991).
Offers, negotiations, partial settlement,
or other actions taking place after expiration of the limitations
period do not estop a party from claiming statute of limitations
as a defense to a legal action.
S.W.2d 597, 606 (1999).
Gailor v. Alsabi, Ky., 990
The trial court’s dismissal of the
action must be affirmed.
As a separate issue, Landrum & Shouse argued that this
appeal should be dismissed for failure to name the individual
-12-
partners of Landrum & Shouse as appellees.
The record contains a
May 2, 1997 Agreement, which stated that “naming of the firm
[Landrum & Shouse] only . . .
with Kentucky law.”
will be considered full compliance
This Agreement was entered into due to the
reluctance of counsel for Cumberland Insurance to name the
individual attorney defendants.
This Agreement also permits the
naming of Landrum & Shouse to be, in effect, a naming of the
former firm members directly involved in the complained of
incident.
Although such an Agreement is unusual, the fact that
it was agreed to by both parties should be sufficient to permit
the term “Landrum & Shouse” to be considered a naming of each
individual defendant.
ALL CONCUR.
BRIEFS FOR APPELLANT:
BRIEF FOR APPELLEE:
Penny R. Warren
Debra H. Dawahare
Wyatt, Tarrant & Combs
Lexington, Kentucky
Carl D. Frederick
Paul J. Hershberg
Frederick Banks & Kinberger
Louisville, Kentucky
Bill V. Seiller
Seiller and Handmaker
Louisville, Kentucky
ORAL ARGUMENT FOR APPELLEE:
Carl D. Frederick
Louisville, Kentucky
ORAL ARGUMENT FOR APPELLANT:
Penny R. Warren
Lexington, Kentucky
-13-
Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.