JERRY RUMMAGE, D/B/A JERRY RUMMAGE & SONS v. FRANKIE DUVALL AND ELMO GREER & SONS, INC.
Annotate this Case
Download PDF
RENDERED: OCTOBER 22, 1999; 10:00 a.m.
NOT TO BE PUBLISHED
C ommonwealth O f K entucky
C ourt O f A ppeals
NO.
1998-CA-001399-MR
JERRY RUMMAGE, D/B/A JERRY
RUMMAGE & SONS
APPELLANT
APPEAL FROM SPENCER CIRCUIT COURT
HONORABLE WILLIAM F. STEWART, JUDGE
ACTION NO. 1995-CI-0008
v.
FRANKIE DUVALL AND
ELMO GREER & SONS, INC.
APPELLEES
OPINION
AFFIRMING IN PART, REVERSING IN PART, AND REMANDING
** ** ** ** **
BEFORE:
GUDGEL, CHIEF JUDGE; HUDDLESTON, AND KNOPF, JUDGES.
KNOPF, JUDGE:
Jerry Rummage, in his capacity as proprietor of
Jerry Rummage & Sons, a hauling business, appeals from a March
31, 1998, summary judgment of Spencer Circuit Court ordering him
to pay damages and pre-judgment interest to plaintiff/appellee
Frankie Duvall.
Rummage maintains that the trial court
improperly entered summary judgment in the face of material
factual disputes.
He further maintains that the trial court
erred in its manner of enforcing a settlement between Rummage,
Duvall, and third-party defendant/appellee, Elmo Greer & Sons,
Inc. (Greer).
Although we agree with the trial court that
Rummage may summarily be found liable under the parties’
settlement, we nevertheless agree with Rummage that the
settlement precludes the relief awarded Duvall.
Accordingly, we
affirm the judgment in part, reverse in part, and remand for
additional proceedings.
Because Rummage is appealing from a summary judgment,
this Court reviews the record “in a light most favorable” to the
party against whom judgment was rendered.
Summary judgment is
improper unless “it appears impossible for the nonmoving party to
produce evidence at trial warranting a judgment in his favor . .
. .”
Steelvest, Inc. v. Scansteel Service Center, Inc., Ky., 807
S.W.2d 476, 482 (1991).
Viewed thus in a manner favorable to Rummage, the
record discloses an interesting if somewhat convoluted case
stemming from a contract between Greer and the Transportation
Cabinet to resurface a portion of Kentucky Highway 44 in Spencer
County.
Greer subcontracted with Rummage for hauling services,
and Rummage, in turn, contracted with Duvall, an independent
hauler, to supplement Rummage’s capacity and ensure that he could
meet Greer’s needs.
The agreement between Rummage and Duvall
included some version of the standard “pay when [or, perhaps, if]
paid” clause.
A dispute arose among Rummage, Greer, and the
Cabinet concerning the amount Rummage was to pay his employees.
Apparently, at some point during the dispute, payments to Duvall
were suspended.
Duvall eventually sued Rummage for the amount
allegedly due under their contract ($2,362.50) plus interest.
-2-
Rummage responded by denying that his duty to pay Duvall had
arisen because he had not yet been payed by Greer.
He also
brought a third-party action against Greer for indemnity and
additional damages.
In June 1997, while the complaint and third-party
complaint were pending, the parties entered a settlement
according to which Greer agreed to pay Rummage the full amount of
Duvall’s underlying claim.
Rummage agreed to pass that money
along to Duvall within two weeks, and Duvall agreed to forego his
claim for interest.
Greer and Rummage also agreed to settle
Rummage’s other claims for a fixed amount subject to a credit in
the amount paid to Duvall if an audit revealed that (as Greer
claimed) Greer had already paid Rummage for Duvall’s services.
Promptly following entry of this agreement, Greer tendered to
Rummage one check in the amount claimed by Duvall and another
check in the amount claimed by Rummage less the amount paid to
Duvall.
Unwilling to accept this reduction in his claim prior to
the audit, Rummage refused the check to himself and refused as
well to transfer the other check to Duvall.
The audit eventually
revealed not only that Greer had failed to pay for Duvall’s
services, but also that Rummage had underestimated the amount of
Greer’s indebtedness to him.
In the meantime, when he did not receive his money
within two weeks, Duvall moved for summary judgment on his
underlying suit for damages and interest.
The trial court ruled
that Rummage had breached the settlement by failing to pass-on
Duvall’s check and that the settlement between Duvall and Rummage
-3-
could be deemed rescinded.
Duvall’s action against Rummage was
thus reinstated, and on the merits of that claim, including the
claim for pre-judgment interest, the trial court ruled that
Duvall was entitled to summary judgment.
On the other hand, the
court further ruled that Rummage had settled its third-party
complaint against Greer, and that part of the settlement remained
in force.
Accordingly, Rummage’s claim for indemnity against
Greer (as well as his new claim for the additional arrearage
discovered during the audit) was denied.
from which Rummage appeals.
This is the judgment
He maintains that Duvall’s
entitlement to damages and interest is still subject to factual
dispute.
He also maintains that, in light of the audit and
Duvall’s withdrawal from the settlement, his settlement with
Greer should not have been enforced.
Our analysis is slightly
different from Rummage’s, but we agree that the trial court did
not give proper effect to the settlement.
It is a familiar rule of long standing in Kentucky that
the voluntary settlement of law suits is to be encouraged.
Murphy v. Henry, 311 Ky. 799, 225 S.W.2d 662 (1949); Childs v.
Hamilton, 308 Ky. 203, 214 S.W.2d 106 (1948).
It is equally
fundamental that such agreements are contracts and so receive the
full benefit and protection of the law pertaining thereto.
Motorists Mutual Insurance Company v. Glass, Ky., 996 S.W.2d 437
(1999); Annotation, Remedies for breach of valid accord or
compromise agreement involving disputed or unliquidated claim, 94
A.L.R. 2d 504 (1964).
Readily avoidable mistakes concerning the
value of one’s bargain, for example, do not provide a basis for
-4-
relief from an ordinary contract, and likewise do not provide
Rummage here with a basis for relief from his settlement with
Greer.
Creason v. Carmody, 310 Ky. 861, 222 S.W.2d 935 (1949);
Kane v. Hopkins, 309 Ky. 488, 218 S.W.2d 37 (1949).
By the same token, although rescission is frequently
the remedy for the breach of a settlement, 94 A.L.R.2d 504,
supra, rescission is generally not appropriate where, as here,
the parties can not be returned to the status quo ante.
Lappas
v. Barker, Ky., 375 S.W.2d 248 (1963); Meyer’s Executor v. Huber,
Ky., 280 S.W.2d 157 (1955).
Accordingly, although we agree with
the trial court that Rummage breached the settlement by failing
to pass along Duvall’s money in a timely manner, we do not agree
that rescission was the proper remedy in this case.
Rummage’s
concurrent settlement with Greer prevented a return to the status
quo ante, with the result that rescission became patently unfair:
Rummage was to be held to his part of the settlement, while
Duvall was to be freed from his.
Instead, Duvall should be
limited to a claim for damages arising from Rummage’s breach of
the settlement.
He will be entitled to interest, for example,
from the date payment was due under the settlement, and he may
have suffered other consequential losses as well.
Such a claim
adequately protects Duvall’s bargain, and at the same time
prevents any injustice to Rummage, a result consistent, we
believe, with our duty both to encourage and to enforce
settlements.
This disposition makes further discussion of Rummage’s
assertions of error unnecessary.
-5-
It remains only to mention two
procedural issues raised by Greer.
First, Greer asserts that
Rummage’s notice of appeal was fatally defective in that it
referred not to the March 31, 1998, summary judgment, but to the
subsequent order denying Rummage’s CR 59.05 motion to alter,
vacate, or amend that judgment.
The rule of strict compliance
upon which Greer relies, however, was modified by the now very
familiar 1985 amendment to CR 73.02.
Rummage’s notice of appeal
was proper under the current rules of procedure.
Jamison, Ky., 705 S.W.2d 479 (1986).
Ready v.
Greer also asserts that
Rummage’s appeal is untimely to the extent that it takes issue
with the trial court’s order of January 8, 1998, as opposed to
the March 31, 1998, summary judgment.
The January order,
however, dealt with only a portion of a multiple claim and was
not expressly made final and appealable.
It is therefore deemed
to have been readjudicated as part of the summary judgment, and
so was properly included in Rummage’s appeal.
CR 54.02.
In sum, this is a controversy over a few thousand
dollars that has continued now for several years.
Even the
parties’ settlement has failed to bring the matter to a close.
The trial court correctly ruled that, under the settlement,
Rummage has fixed his claim against Greer and thus has waived the
additional, post-audit claim he now pursues.
The trial court
also correctly determined that Rummage breached the settlement by
failing promptly to give Duvall his money.
We are persuaded,
however, that permitting Duvall to rescind the settlement and
proceed against Rummage on his underlying claim was an
-6-
inappropriate remedy in this case, because Rummage can not
similarly be returned to his pre-settlement position.
Accordingly, we affirm the March 31, 1998, judgment of
Spencer Circuit Court in all respects except its provision of a
remedy for Duvall.
We reverse that portion of the judgment and
remand for additional proceedings during which Duvall is to be
afforded an opportunity to prove the extent of his damages.
ALL CONCUR.
BRIEF FOR APPELLANT:
BRIEF FOR APPELLEE ELMO GREER
& SONS, INC.:
John S. Kelley, Jr.
Bardstown, Kentucky
Robert L. Ackerson
Anne B. Courtney
Ackerson, Mosley & Yann,
P.S.C.
Louisville, Kentucky
BRIEF FOR APPELLEE FRANKIE
DUVALL:
David M. Cross
Albany, Kentucky
-7-
Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.