TILFORD CONTRACTORS, INC. v. STEWART SERVICES, INC.

Annotate this Case
Download PDF
RENDERED: March 26, 1999; 10:00 a.m. NOT TO BE PUBLISHED C ommonwealth O f K entucky C ourt O f A ppeals NO. 1997-CA-003059-MR TILFORD CONTRACTORS, INC. APPELLANT APPEAL FROM JEFFERSON CIRCUIT COURT HONORABLE ELLEN EWING, JUDGE ACTION NO. 97-CI-04170 v. STEWART SERVICES, INC. APPELLEE OPINION VACATING AND REMANDING ** ** ** ** ** BEFORE: COMBS, DYCHE, and SCHRODER, Judges. COMBS, JUDGE: The appellant, Tilford Contractors, Inc. (Tilford), appeals from the order of the Jefferson Circuit Court granting the motion by the appellees, Stewart Services, Inc. (Stewart) to stay arbitration proceedings between the parties. After reviewing the record, we vacate and remand. This action arises from a dispute as to the scope of an arbitration clause contained in a subcontract into which Tilford had entered with Stewart. Western Baptist Hospital undertook an expansion project of its hospital facilities in McCracken County, Kentucky, and hired Centex-Rodgers Construction Company (CentexRodgers) as the general contractor for the project. Centex- Rodgers contracted a portion of this project to Stewart. Stewart then entered into a subcontract with Tilford for the installation of the plumbing and mechanical systems for its portion of the expansion project. Tilford alleged that during the course of construction, it was required to make approximately 1500 additions and deletions to the work that it had performed under the parties’ subcontract. Stewart disputed Tilford’s claim for the costs of this additional work. On April 21, 1997, Tilford filed a claim for arbitration with the American Arbitration Association in Louisville, Kentucky, to resolve the dispute with Stewart over the costs of the extra work that it had performed. Subsequently, on July 25, 1997, Stewart filed a motion with the Jefferson Circuit Court to stay the arbitration proceedings, arguing that it had not agreed to the arbitrate the issue presented by Tilford in its demand for arbitration. Stewart asserted that pursuant to the parties’ subcontract, it had agreed to arbitrate only those disputes arising from the costs associated with “change orders" and that Tilford was inappropriately attempting to force it to arbitrate a “delay/impact claim.” Conversely, Tilford claimed that Article 12.1.7 of the parties’ agreement provided that any disputes over the costs of any additional work were to be resolved by arbitration. On September 25, 1997, the court entered an order denying Stewart’s motion to stay arbitration. Stewart subsequently filed a motion to amend, alter, or vacate the court’s order. After conducting a hearing, the court entered an -2- order vacating its previous order of September 25, 1997, and staying arbitration. The court held that the Article 12.1.7 of the parties’ subcontract applied only to disputes over the pricing of change orders issued by Stewart and that the claim presented by Tilford for arbitration did not fall within the scope of Article 12.1.7. This appeal followed. The parties addressed the issue of additional work and changes in the nature and extent of the work that might arise during the course of performance of the contract by Tilford. They focused on Articles 9 and 12 of their agreement. provides in pertinent part as follows: Article 9 Article 9 Subcontractor Rights and Responsibilities 9.8 Changes in Work 9.8.1 Requests for adjustment to the Subcontract amount for changes in work shall be recognized only if recognized and paid for by the Owner. 9.8.2 The Subcontractor may be ordered in writing by the Contractor, without invalidating this Subcontract, to make changes in the Work within the general scope of this Subcontract consisting of additions, deletions or other revisions, the Contract Sum and the Contract Tine being adjusted accordingly. The Subcontractor, prior to the commencement of such changed or revised Work, shall submit promptly to the Contractor written copies or any claim for adjustment to the Contract Sum and Contract Time for such revised Work in a manner Consistent with the Contract Documents. No extra work or changes will be recognized or paid for unless agreed to in writing prior to performance. 9.8.3 In the event that the Owner, Architect or Engineer authorizes additional work on this project, the Subcontractor mentioned above is obligated to perform that part of the work and shall receive as payment -3- therefore, a sum not to exceed 85% of that amount received by Contractor from the Owner, due and payable upon receipt of the payment from the Owner or Architect. Subcontractor has the obligation to provide such information that validates his cost on the extra work order in a timely fashion or within seven days after work was performed. If Contractor requests quotation on work before it is performed, quotation shall be given within 48 hours after request. Should the Subcontractor be directed by the Contractor to provide additional work, the mark-up on the additional work shall not exceed 15%. The 15% shall include all office overhead and job supervision, and cost shall be considered only direct cost applicable to the work authorized. Additionally, Article 12 of the subcontract states in pertinent part: Article 12 12.1 Changes in Work Change Orders 12.1.1 The Contractor may, without affecting any other Contract Document or terms or conditions thereof, issued [sic] a Change Order for extra work or other changes in the work by altering adding to or deducting the existing work or conditions. 12.1.2 The amount to be paid to or deducted from the Subcontractor shall be determined as hereinafter set forth; provided, however, that upon receipt of a written order describing the work the Subcontractor shall promptly proceed with the revised work as described, even though the amount of any resultant increase or decrease in the Contract sum has not yet been determined. All changes in the Work shall be performed in accordance with Contract Documents. * * * 12.1.7 If the parties are unable to finally agree to a fair dollar amount for additions or deletions to the scope of work, said disputes shall be brought before the American Arbitration Society for review and settlement. Payment for said services shall -4- be borne equally by both parties. Such arbitration proceedings shall occur at a place to be decided on in Louisville, Kentucky. Said disputes, however, shall not be justification by the Subcontractor to refuse to proceed with the work any changes (“Change Orders”) in the work of said Contract. Subcontractor agrees to proceed with all work, change orders included, in a timely manner and to resolve any questions or problems as herein before established. While the parties agree that Article 12.1.7 provides for the resolution of certain disputes through arbitration, they disagree as to its scope. Stewart argues that Article 12.1.7 applied only to “change orders,” a term of art which should be given its technical meaning; i.e., a formal, written order issued by the contractor or architect authorizing a change in the work or in the scope of the work. Construction.1 Dictionary of Architecture & Stewart reasons that Tilford’s demand for arbitration was based upon a claim for additional costs and extensions of time — items not falling within the scope of 12.1.7. Stewart thus contends that since the dispute between the parties was not related to formal "change orders" issued to Tilford, the court properly stayed the arbitration proceedings. Tilford, however, argues that the Article 12.1.7 requires the parties to arbitrate any dispute over costs for additions or deletions to the scope of work and that arbitration is not limited only to disputes arising from formal change orders. We are compelled to agree with Tilford’s reading of Article 12.1.7. “Any contract or agreement must be construed as a whole, giving effect to all parts and every word in it if 1 See Brief for Appellee, Stewart Services, Inc. -5- possible.” (1986). City of Louisa v. Newland, Ky., 705 S.W.2d 916 However, when words are used as technical terms in a transaction between parties knowledgeable in a technical field, such words are to be given their technical meanings. Cook United, Inc. v. Waits, Ky., 512 S.W.2d 493 (1974). While we agree that “change order” as used in Article 12 is a term of art which should be ascribed its technical meaning, we do not agree that the arbitration clause contained in the subcontract applies only to “change orders.” The unambiguous language of Article 12.1.7 requires the parties to submit to arbitration when they are “unable to agree to a fair dollar amount for additions or deletions to the scope of work.” (Emphasis added). The clear wording of this clause is not restricted only to disputes over formally drafted change orders. In light of the subcontract as a whole, it is clear that the parties fully anticipated and made provisions for any changes in the scope of the work that Stewart had subcontracted to Tilford — including change orders or other “additions, deletions or other revisions.” Article 9.8.2. The arbitration clause is physically positioned at the very end of the subcontract, impliedly encompassing disputes arising not only as to "additions or deletions to the scope of the work" immediately preceding it at Article 12.1.7 but also as to the "additions, deletions or other revisions" alluded to at Article 9.8.2. The term "change orders" also appears at Article 12.1.7, and there is no specific restriction or limitation, or -6- clarification that the arbitration clause is to pertain to "change orders" as distinguished from "additions or deletions." Articles 9 and 12 reflected and assured the parties’ intent that work on the expansion project might proceed uninterrupted by disputes over extra costs. Both articles contain language that Tilford was to proceed with all work (including additions and change orders) and that they were to resolve any disputes over costs through arbitration — not by cessation of work. We hold that the court erred in ordering a stay of arbitration proceedings between the parties as we construe the arbitration clause as governing the resolution of the dispute at issue in this case. For the foregoing reasons, we vacate the order of the circuit court staying arbitration and remand for further proceedings consistent with this opinion. ALL CONCUR. BRIEFS AND ORAL ARGUMENT FOR APPELLANT: BRIEF AND ORAL ARGUMENT FOR APPELLEE: Robert C. Fields Frankfort, KY Thomas E. Roma, Jr. Louisville, KY -7-

Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.