CORBIN GLASS COMPANY v. DENHAM-BLYTHE, INC.
Annotate this Case
Download PDF
RENDERED: January 15, 1999; 10:00 a.m.
NOT TO BE PUBLISHED
C ommonwealth O f K entucky
C ourt O f A ppeals
NO.
NO.
1997-CA-001140-MR
1997-CA-001198-MR
CORBIN GLASS COMPANY
v.
APPELLANT/
CROSS-APPELLEE
APPEAL AND CROSS-APPEAL FROM LAUREL CIRCUIT COURT
HONORABLE RODERICK MESSER, JUDGE
ACTION NO. 96-CI-286
DENHAM-BLYTHE, INC.
APPELLEE/
CROSS-APPELLANT
OPINION
AFFIRMING
** ** ** ** **
BEFORE:
BUCKINGHAM, DYCHE AND GARDNER, JUDGES.
GARDNER, JUDGE: Corbin Glass Company (Corbin) has appealed from a
judgment of the Laurel Circuit Court in this contractor/
subcontractor dispute stemming from a construction project.
Denham-Blythe, Incorporated (Denham) has cross-appealed.
After
reviewing the issues raised by both parties, this Court affirms
the circuit court’s judgment.
This action arises from a project to build a
psychiatric addition to the Appalachian Regional Hospital
(Appalachian) in Hazard, Kentucky.
Denham was the general
contractor for the project, and it entered into a contract with
Corbin by which Corbin agreed to furnish and install certain
glass and glazing for the project.
work at a cost of $375,080.
Corbin agreed to perform the
Corbin subcontracted with Atlas
Metals (Atlas) to provide screens for the project.
Appalachian,
a non-profit entity, reserved the right to pay any material
suppliers directly, thus enabling it to save the applicable
Kentucky sales tax.
During the course of the project, a problem arose
regarding the screens that Atlas furnished for the project.
The
screens had the wrong finish and also were sized incorrectly and
thus, would not fit.1
Appalachian and Denham discussed the
matter with Atlas and determined that the best course was for
Atlas to correct the size of the screens at an additional cost of
$14,126.
Corbin has maintained that it was not consulted
regarding this matter and that it should not be forced to bear
the additional cost.
The screens were corrected and eventually
installed on the new addition.
Over the course of the project, Corbin invoiced Denham
$156,605 which Denham paid.
Following completion of the project,
Denham requested Corbin to sign a release whereby Corbin
acknowledged receipt of all sums due to it and released any claim
it might have had to a lien on the project.
release.
Corbin signed this
Sometime after this release was signed, Denham
1
A dispute apparently exists regarding who provided the
incorrect measurements for the screens. Denham maintains that
Corbin provided incorrect specifications while Corbin contends it
was not given a timely opportunity to provide Atlas with the
correct dimensions prior to the delivery of the screens.
-2-
contended that it overpaid Corbin $22,995.56, and demanded Corbin
refund that amount.
Corbin declined to refund any money to
Denham.
In April 1996, Denham filed a complaint in circuit
court seeking to recover $22,995.56 plus interest from Corbin.
The court conducted a bench trial, and in March 1997 issued its
findings of fact, conclusions of law and judgment.
The court
found that Denham overpaid $14,126 for the cost of resizing the
screens and that payments to Corbin included an overpayment of
$492.36 in sales tax.
It found that another $2,080.00 paid to
Corbin by Denham regarding materials provided by Kawneer, another
subcontractor under Corbin, did not constitute an overpayment.
The court concluded as a matter of law that the release signed by
Corbin barred its counterclaim.
The court awarded Denham
$14,618.36 which constituted overpayments it made to Corbin.
Corbin subsequently moved the court to alter, amend or
vacate its previous judgment.
Corbin specifically asked the
court to reconsider its award of $492.36 in overpayment of taxes.
It also moved the court to make additional findings of fact
regarding whether the additional $14,126 paid to Atlas by Denham
was with or without the consent of Corbin and if made without
Corbin’s consent, Corbin asked the court to make a finding
regarding whether Denham knew Corbin did not consent to the
overpayment.
It also asked that if the court found that the
overpayment was made without Corbin’s consent, that the court
state what provision of the contract between Denham and Corbin or
what legal authority permitted Denham to recover the overpayment
-3-
from Corbin.
The court in an April 1997 order, granted the
motion to alter, amend or vacate and reduced the judgment by
$492.36.
fact.
It denied the motion to make additional findings of
Corbin subsequently brought this appeal, and Denham cross-
appealed.
Corbin argues that the trial court erred by allowing
Denham to recover for an overpayment to Atlas.
Corbin maintains
that it was left out of the negotiating between Appalachian,
Denham and Atlas regarding how to correct the problem of the
nonconforming screens.
It thus contends that it was not allowed
to correct or minimize damages with Atlas, a company with which
it had subcontracted.
It also argues that the trial court erred
by holding that the release signed by it barred its counterclaim
and that Denham should have told Corbin at the time Corbin signed
the release that Denham planned to recover additional amounts.
After reviewing the agreement signed between Denham and Corbin
and the trial court’s findings in this case, this Court affirms
the trial court on this issue.
Two provisions of the agreement signed by Denham and
Corbin are particularly relevant to the dispute in the instant
case.
The agreement on page one states,
THE INSTALLATION OF THE MATERIALS OR THE WORK
TO BE PERFORMED SHALL BE DONE WHEN AND AS
REQUIRED TO MEET JOB PROGRESS REQUIREMENTS,
OR AS DIRECTED BY THE CONTRACTOR. IF THE
MATERIALS HEREIN CALLED FOR ARE NOT DELIVERED
PROMPTLY, THEREBY CAUSING OR THREATENING TO
CAUSE DELAY IN THE GENERAL PROGRESS OF THE
WORK, THE CONTRACTOR SHALL HAVE THE RIGHT TO
INVESTIGATE THE CAUSE OF SAID DELAY AND
EXPEDITE DELIVERIES, AND ALL EXPENSES THUS
INCURRED BY THE CONTRACTOR SHALL BE CHARGED
TO AND PAID BY THE SAID SUBCONTRACTOR.
-4-
On page two it states,
SUBCONTRACTOR SHALL INDEMNIFY AND HOLD
HARMLESS THE CONTRACTOR FROM AND AGAINST ANY
AND ALL PAYMENTS AND LIABILITIES FOR PAYMENT
OF COMPENSATION OR DAMAGES WHICH THE
CONTRACTOR MAY BE REQUIRED OR OBLIGATED TO
MAKE TO OR ON ACCOUNT OF SUBCONTRACTOR’S OWN
EMPLOYEES, AND ALSO INDEMNIFY AND HOLD
HARMLESS THE CONTRACTOR FROM AND AGAINST ANY
AND ALL LOSSES, LIABILITIES, SUITS OR
OBLIGATIONS OF ANY KIND, PAID OR INCURRED BY
THE CONTRACTOR ON ACCOUNT OF THE ACT, NEGLECT
OR DEFAULT OF THE SUBCONTRACTOR, ITS AGENTS,
SERVANTS, EMPLOYEES OR SUBCONTRACTORS
NOTWITHSTANDING THAT ANY ACT, NEGLECT OR
DEFAULT OF CONTRACTOR MAY HAVE CONTRIBUTED
THERETO.
The language of this agreement is clear and unambiguous.
Under
these provisions, Corbin bears the burden of absorbing the extra
cost of damage done by its subcontractor, even if Denham, the
general contractor,
may have contributed to the problem through
its own fault.
The key problem that arose in this case is that once
Atlas delivered the nonconforming screens, Corbin was basically
left out of the negotiations with Atlas to correct the problem.
Appalachian and Denham apparently decided that the quickest and
least expensive way to remedy the problem was for Atlas to
correct the screens at an extra cost of $14,126.
This fact does
render the matter of who supplied the wrong specifications to
Atlas more relevant, and the evidence was apparently disputed on
this issue.
The trial court made no definite finding on this
issue but in deciding for Denham, it apparently concluded that
Corbin was at fault and must bear the burden.
Corbin requested
no specific findings of fact on this issue so it has essentially
waived any contention on this matter.
-5-
See Eaton Axle Corp. v.
Nally, Ky., 688 S.W.2d 334, 338 (1985); Cherry v. Cherry, Ky.,
634 S.W.2d 423, 426 (1982); Kentucky Rules of Civil Procedure
(CR) 52.02, 52.04.
Further, Corbin has cited nothing in the
record which renders the trial court’s findings of fact clearly
erroneous, and we decline to disturb the trial court’s findings
of fact in this matter.
See Reichle v. Reichle, Ky., 719 S.W.2d
442 (1986); Cherry v. Cherry, 634 S.W.2d at 425; Wells v. Wells,
Ky., 412 S.W.2d 568 (1967); Byerly Motors, Inc. v. Phillips
Petroleum Co., Ky., 346 S.W.2d 762 (1961); CR 52.01.
Based upon
the original agreement between Denham and Corbin and the trial
court’s findings of fact, this Court declines to disturb the
trial court’s conclusion that Corbin must repay Denham the
$14,126 for resizing the screens.2
The cases cited by Corbin
regarding mistake are fundamentally distinguishable and do not
apply to this case.
Corbin also seems to dispute the trial court’s findings
regarding $2,080 to which it claimed it was entitled based upon
its subcontract with Kawneer and $492.36 in sales tax which it
claims was erroneously awarded to Denham.
The record shows that
the trial court ruled in favor of Corbin in both instances.
The
court concluded that the $2,080 was the result of Corbin’s
agreement to do certain work at its shop so it did not appear
2
We do not believe that the release signed by Corbin at
Denham’s insistence has any bearing on this particular issue
since Corbin had already been paid this amount at the time that
it signed the release. We also note that Corbin may have some
remedy against Atlas, but for some reason neither party brought
any claim against Atlas in the proceedings below.
-6-
Corbin was overpaid.3
Further, while the trial court initially
ruled that the payments to Corbin included an overpayment in
sales tax of $492.36, in its subsequent order of April 21, 1997,
it granted Corbin’s motion to alter, amend or vacate to the
extent that the judgment was reduced by $492.36.
In its cross-appeal, Denham argues that the trial court
erred in not awarding the total overpayment to Corbin of $22,995.
Thus, it argues it should have been awarded an additional $8,869.
We have uncovered no error by the trial court on this issue.
The record reveals that a dispute existed regarding
whether certain glazing, glass installation, and other work to be
done to a connector building at the project was included in the
original bid packages three or four, or included later in change
order A.
Corbin’s witnesses testified that extra work had to be
done for additional material and labor costs which were
apparently part of change order A.
Denham’s witness however
stated that bid package four was included in change order A and
that no extra costs were incurred.
The record contains ample
evidence to support the trial court’s conclusion that Denham was
not entitled to any extra amount and we decline to disturb its
findings.
See Reichle v. Reichle, 719 S.W.2d at 444.
For the foregoing reasons, this Court affirms the
judgment of the Laurel Circuit Court.
ALL CONCUR.
3
It also appears that any claims for Corbin for additional
amounts from Denham after it was initially paid would be barred
by the release it signed.
-7-
BRIEF FOR APPELLANT/CROSSAPPELLEE:
BRIEF FOR APPELLEE/CROSSAPPELLANT:
Larry E. Conley
Corbin, Kentucky
Richard E. Vimont
Lexington, Kentucky
-8-
Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.