Oracle America Inc. v. United States, No. 19-2326 (Fed. Cir. 2020)
Annotate this Case
The Joint Enterprise Defense Infrastructure Cloud procurement is directed to the long-term provision of enterprise-wide cloud computing services to the Defense Department. Its solicitation contemplated a 10-year indefinite-delivery, indefinite-quantity contract with a single provider. The JEDI solicitation included “gate” provisions that prospective bidders would be required to satisfy, including that the contractor must have at least three existing physical commercial cloud offering data centers within the U.S., separated by at least 150 miles, providing certain offerings that were “FedRAMP Moderate Authorized” at the time of proposal (a reference to a security level). Oracle did not satisfy the FedRAMP Moderate Authorized requirement and filed a pre-bid protest.
The Government Accountability Office, Claims Court, and Federal Circuit rejected the protest. Even if Defense violated 10 U.S.C. 2304a by structuring the procurement on a single-award basis, the FedRAMP requirement would have been included in a multiple-award solicitation, so Oracle was not prejudiced by the single-award decision. The FedRAMP requirement “constituted a specification,” not a qualification requirement; the agency structured the procurement as a full and open competition. Satisfying the gate criteria was merely the first step in ensuring that the Department’s time was not wasted on offerors who could not meet its minimum needs. The contracting officer properly exercised her discretion in finding that the individual and organizational conflicts complained of by Oracle did not affect the integrity of the procurement.
Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.