VT Yankee Nuclear Power Corp. v. United States
Justia.com Opinion Summary: In 1983, the Nuclear Waste Policy Act, 42 U.S.C. 10101-10270, authorized the Department of Energy to contract with nuclear facilities for disposal of spent nuclear fuel and high level radioactive waste. The Standard Contract provided that rights and duties may be assignable with transfer of SNF title. Plaintiff entered into the Standard Contract in 1983 and sold its operation and SNF to ENVY in 2002, including assignment of the Standard Contract, except one payment obligation. Plaintiff transferred claims related to DOE defaults. As a result of DOE’s breach, ENVY built on-site dry-storage facilities. The Claims Court consolidated ENVY’s suit with plaintiff’s suit. The government admitted breach; the Claims Court awarded ENVY $34,895,467 (undisputed damages) and certain disputed damages. The Federal Circuit affirmed in part. Plaintiff validly assigned pre-existing claims; while partial assignment of rights and duties under the contract was not valid, the government waived objection. The assignment encompassed claims against the government. Legal and lobbying fees to secure Vermont approval for mitigation were foreseeable, but other expenses were not recoverable. ENVY failed to prove costs of disposing of contaminated material discovered due to the breach and its characterization of spent fuel moved to dry storage. ENVY is not entitled to recover cost of capital for funding mitigation, or Resource Code 19 payroll loader overhead costs, but may recover capital suspense loader overhead costs,.
Receive FREE Daily Opinion Summaries by Email
Receive FREE Daily Opinion Summaries by Email
Loading PDF...
United States Court of Appeals
for the Federal Circuit
__________________________
VERMONT YANKEE NUCLEAR POWER
CORPORATION,
Plaintiff-Cross Appellant,
v.
ENTERGY NUCLEAR VERMONT YANKEE, LLC,
AND ENTERGY NUCLEAR OPERATIONS, INC.,
Plaintiffs-Cross Appellants,
v.
UNITED STATES,
Defendant-Appellant.
__________________________
2011-5033, -5034, -5042
__________________________
Appeals from the United States Court of Federal
Claims in consolidated case nos. 02-CV-898 and 03-CV2663, Judge Thomas C. Wheeler.
__________________________
Decided: June 13, 2012
___________________________
RICHARD J. CONWAY, Dickstein Shapiro LLP, of Washington, DC, argued for plaintiff-cross appellant, Vermont
Yankee Nuclear Power Corporation, of Washington, DC.
VERMONT YANKEE NUCLEAR POWER
v. US
2
BRAD FAGG, Morgan, Lewis & Bockius LLP, of Washington, DC, argued for plaintiffs cross appellants Entergy
Nuclear Operations, Inc., et al. Of counsel on the brief
was L. JAGER SMITH, Wise, Carter, Child & Caraway,
P.A., of Jackson, Mississippi.
ANDREW P. AVERBACH, Trial Attorney, United States
Department of Justice, of Washington, DC, argued for
defendant-appellant. With him on the brief were TONY
WEST, Assistant Attorney General, JEANNE E. DAVIDSON,
Director, and HAROLD D. LESTER, JR., Assistant Director
Of counsel on the brief were MARIAN E. SULLIVAN,
JEREMIAH M. LUONGO, MARIANA T. ACEVEDO, SETH W.
GREENE, JOSEPH D. KELLER, and DANIEL G. KIM, Trial
Attorneys; and JANE K. TAYLOR, Office of General Counsel, United States Department of Energy, of Washington,
DC.
KYLE H. LANDIS-MARINELLO, Assistant Attorney General, Office of the Attorney General, State of Vermont,
Montpelier, Vermont, for amicus curiae. With him on the
brief was GAVIN J. BOYLES, Assistant Attorney General.
__________________________
Before BRYSON, MAYER, and DYK, Circuit Judges.
Opinion for the court filed by Circuit Judge DYK, in which
Circuit Judge MAYER joins except for Part I(C), and in
which Circuit Judge BRYSON joins except for Part III (B),
(D), and (F). Opinions dissenting in part filed by Circuit
Judges MAYER and BRYSON.
DYK, Circuit Judge.
This case involves the federal governmentâs breach of
a contract requiring it to accept for disposal spent nuclear
fuel generated at the Vermont Yankee Nuclear Power
3
VERMONT YANKEE NUCLEAR POWER
v. US
Station (âVYNPSâ). The government, the current owner
of VYNPS, Entergy Nuclear Vermont Yankee, LLC
(âENVYâ), 1 and the former owner of VYNPS, Vermont
Yankee Nuclear Power Corporation (âVermont Yankeeâ),
each appeal from a judgment of the Court of Federal
Claims (âClaims Courtâ) awarding damages to ENVY for
breach of the contract. Because the government agrees
that it breached the contract, all issues on appeal concern
either the assignment of the contract (or contract claims)
from Vermont Yankee to ENVY or the measure of damages.
In Part I of this opinion, we hold that Vermont Yankee validly assigned to ENVY pre-existing claims against
the government under the Standard Contract for Disposal
of Spend Nuclear Fuel and/or High-Level Radioactive
Waste, 10 C.F.R. § 961.11 (1984) (hereinafter âStandard
Contractâ). We also hold that while the partial assignment of rights and duties under the Standard Contract
from Vermont Yankee to ENVY was not valid, the government nonetheless waived its right to object to the
partial assignment.
In Part II, we hold that the scope of the assignment
from Vermont Yankee to ENVY encompassed the claims
Vermont Yankee asserted against the government, including the claim for pre-sale mitigation costs and the
claim for the diminution in value of VYNPS.
In Part III, we hold that legal and lobbying fees incurred by ENVY to secure approval from the State of
Vermont for a dry storage facility were foreseeable. We
hold, however, that other state-imposed requirements
were not foreseeable, and hence not recoverable, including
ENVYâs sister company, Entergy Nuclear Operations, Inc., also joins ENVY as a Plaintiff-Cross Appellant.
For simplicity, we refer only to ENVY in this opinion.
1
VERMONT YANKEE NUCLEAR POWER
v. US
4
payments into Vermontâs Clean Energy Development
Fund, performance of a flood analysis, and construction of
a visual barrier to the dry storage facility.
In Part IV, we hold that ENVY did not meet its burden of proof with respect to its claimed damages for the
costs of disposing of contaminated material discovered
due to the breach and the characterization of spent fuel
moved to dry storage.
In Part V, we discuss the remaining issues, which are
for the most part controlled by our recent precedents. In
accordance with those precedents, we hold that ENVY is
not entitled to recover its cost of capital to fund its mitigation activities. And while we hold that ENVY is entitled
to recover its capital suspense loader overhead costs, we
hold that, due to insufficient argument on appeal, ENVY
is not entitled to recover its Resource Code 19 payroll
loader overhead costs.
BACKGROUND
This is another in a long series of cases in which the
government breached a commitment for the disposal of
spent nuclear fuel (âSNFâ) and high-level radioactive
waste (âHLWâ). Briefly, the background is as follows. In
1983, Congress enacted the Nuclear Waste Policy Act of
1982 (âNWPAâ), Pub. L. No. 97-425, 96 Stat. 2201 (1983)
(codified as amended at 42 U.S.C. §§ 10101-10270 (2006)).
The NWPA authorized the Department of Energy (âDOEâ)
to enter into contracts with nuclear facilities for the
disposal of SNF and HLW. 42 U.S.C. § 10222. Congress
expressly mandated that, under the terms of the contracts, DOE accept SNF and HLW âbeginning not later
than January 31, 1998.â Id. § 10222(a)(5)(B). Contemplating the potential sale of nuclear facilities, the NWPA
also provided that â[t]he rights and duties of a party to a
contract entered into under this [Act] may be assignable
5
VERMONT YANKEE NUCLEAR POWER
v. US
with transfer of title to the spent nuclear fuel . . . involved.â Id. § 10222(b)(3).
Pursuant to its authority under the NWPA, DOE
promulgated regulations defining the terms of the Standard Contract to be executed with nuclear facilities. See
42 U.S.C. § 10222(a)(1); 48 Fed. Reg. 5,458 (Feb. 4, 1983)
(proposed rule); 48 Fed. Reg. 16,590 (Apr. 18, 1983) (final
rule). Consistent with section 10222(b)(3), the Standard
Contract provided: âThe rights and duties of the Purchaser may be assignable with transfer of title to the
SNF . . . involved; provided, however, that notice of any
such transfer shall be made to DOE within ninety (90)
days of transfer.â 10 C.F.R. § 961.11, art. XIV; see also
J.A. 120.
In June 1983, DOE entered into a Standard Contract
with Vermont Yankee for the disposal of SNF stored at
the VYNPS facility. In consideration for DOEâs commitment to dispose of SNF, the Standard Contract required
the utilities to pay fees to DOE. First is a one-time fee
that is based on any SNF generated prior to April 1983.
Payment of this one-time fee may be deferred with interest until anytime prior to the beginning of DOEâs performance. Vermont Yankee had been producing SNF
since 1972, and was thus obligated to pay the one-time fee
for disposal of its pre-1983 SNF. Vermont Yankee elected
to defer the payment of the one-time fee, which at the
time of this action, has not yet been paid. Second, contract holders must pay a continuing quarterly fee based
on the amount of electricity generated and sold during
that quarter by the utility. This fee has been paid by
Vermont Yankee and ENVY during the period of their
ownership of VYNPS and accepted by the government.
DOE failed to begin accepting and disposing of SNF
from Vermont Yankee and other utilities in the nuclear
VERMONT YANKEE NUCLEAR POWER
v. US
6
industry by January 31, 1998. On August 15, 2001,
Vermont Yankee entered into a Purchase and Sale
Agreement (âPSAâ) with ENVY. On July 31, 2002, the
parties completed the sale of VYNPS, including title to all
of the SNF generated and stored at VYNPS. The PSA
expressly provided that â[Vermont Yankee] shall assign to
[ENVY] the DOE Standard Contract, except for the
obligation to pay the one time fee.â J.A. 241. The PSA
further provided that Vermont Yankee transferred to
ENVY âany claims of [Vermont Yankee] related to
[DOE]âs defaults under the DOE Standard Contract
accrued as of the Closing, whether relating to periods
prior to or following the Closing.â J.A. 197. The assignment excluded âclaims as may relate to the one-time fee
with respect to fuel used to generate electricity prior to
April 7, 1983.â J.A. 197.
In a letter dated July 31, 2002, ENVY notified DOE
âthat Vermont Yankee ha[d] . . . assigned its right, title,
and interestâ under the Standard Contract to ENVY, and
that ENVY would âassume and discharge the obligations
of Vermont Yankee under the [Standard] Contract in lieu
of Vermont Yankee.â J.A. 268. In a letter dated August
21, 2002, Vermont Yankee similarly notified DOE that it
had transferred to ENVY âits title to Spent Nuclear Fuelâ
at VYNPS along with âits rights and duties under the
[Standard] Contract.â J.A. 269. The Vermont Yankee
letter also notified DOE that it had âretained the rights to
any and all damages and other remedies that might
accrue under from [DOE]âs breach of its obligations under
the [Standard] Contract to the extent of the one-time fee
for fuel used to generate electricity prior to April 7, 1983.â
J.A. 269. However, neither letter notified DOE that
Vermont Yankee had also retained the obligation to pay
the one-time fee prior to DOEâs performance. This reservation was not discovered by the government until it
7
VERMONT YANKEE NUCLEAR POWER
v. US
obtained a copy of the PSA during document production in
this case in 2006.
As a result of DOEâs breach, and as mitigation, ENVY
concluded that it should construct an on-site dry-storage
facility to provide for the interim storage of SNF at
VYNPS. Pursuant to federal regulations and ENVYâs preexisting license with the Nuclear Regulatory Commission
(âNRCâ), ENVY was permitted to construct a dry-storage
facility implementing a system that had been previously
approved by the NRC. However, as discussed below,
ENVY claims that it incurred other expenses in order to
obtain approval from the State of Vermont to construct
the facility, including: (1) legal and lobbying fees;
(2) payments into Vermontâs Clean Energy Development
Fund; (3) the cost of performing a flood analysis; and
(4) the cost of constructing a visual barrier.
On November 12, 2003, ENVY filed an action in the
Claims Court for damages caused by DOEâs breach of
contract. The Claims Court consolidated ENVYâs action
with a separate action brought by Vermont Yankee asserting claims arising out of its pre-sale ownership and
operation of VYNPS. See Entergy Nuclear Vt. Yankee,
LLC v. United States, 95 Fed. Cl. 160, 167 (2010).
We have previously held that DOEâs failure to begin
collecting SNF constituted a partial breach of the Standard Contract. Me. Yankee Atomic Power Co. v. United
States, 225 F.3d 1336, 1342 (Fed. Cir. 2000) (âThe breach
involved all the utilities that had signed the contractâthe
entire nuclear electric industry.â); see also N. States Power
Co. v. United States, 224 F.3d 1361, 1367 (Fed. Cir. 2000).
The government admitted liability for its breach of
the Standard Contract, and the Claims Court awarded
ENVY $34,895,467 in undisputed damages, the largest
portion of which was for the construction of the dry stor-
VERMONT YANKEE NUCLEAR POWER
v. US
8
age facility. However, the government, ENVY, and Vermont Yankee disputed the governmentâs liability for
various categories of damages, and this dispute continues
on appeal. 2
Through determinations at summary judgment and
after trial, the Claims Court resolved the disputed claims
as follows. 3 The Claims Court held at summary judgment
that the assignment from Vermont Yankee to ENVY of
pre-existing claims against the government was valid,
and that, contrary to the governmentâs position, the
partial assignment from Vermont Yankee to ENVY of the
rights and duties under the Standard Contract was also
valid. Vt. Yankee Nuclear Power Corp. v. United States
(âVermont Yankee Iâ), 73 Fed. Cl. 236, 240-42 (2006). The
Claims Court also held at summary judgment that Vermont Yankee had unambiguously assigned to ENVY the
claims it asserted against the government for the cost of
its pre-sale mitigation activities and the diminution in
value of VYNPS. Vt. Yankee Nuclear Power Corp. v.
United States (âVermont Yankee IIâ), 84 Fed. Cl. 339, 34647 (2008).
2
The government also disputed four categories of
damages before the Claims Court that are not involved in
this appeal.
3
Prior to the trial, Claims Court also entered a
Rule 54(b) final judgment dismissing Vermont Yankeeâs
claims. In an initial appeal, we determined that because
âVermont Yankee and ENVY have each claimed relief for
the same alleged wrong, and . . . that pursuant to the
[PSA] only one of them can recover,â âthe claims [were]
too intertwined for entry of judgment pursuant to Rule
54(b) as to only one party.â Vt. Yankee Nuclear Power
Corp. v. United States, 346 F. Appâx 589, 591 (Fed. Cir.
2009). Accordingly, we ordered the Claims Court to
vacate the Rule 54(b) judgment. Id.
9
VERMONT YANKEE NUCLEAR POWER
v. US
In addition to the undisputed portion of ENVYâs damages claim, the Claims Court awarded ENVY its claimed
costs of securing state approval for the dry storage facility, including: (1) legal and lobbying fees; (2) payments
into the Vermont Clean Energy Development fund;
(3) performance of a river flood analysis; and
(4) construction of a visual barrier to the dry-storage
facility. Entergy Nuclear, 95 Fed. Cl. at 184, 190. The
Claims Court also awarded ENVY damages for its
claimed costs of (1) disposing of contaminated material
discovered due to the breach; and (2) characterizing the
SNF moved into on-site dry storage. Id. at 190-92.
Finally, the Claims Court decided two issues that
have since been determined by our recent precedent. The
Claims Court denied damages for ENVYâs cost of capital
to fund its mitigation activities (consistent with our
precedent) and denied ENVYâs overhead costs calculated
via its capital suspense loader (contrary to our precedent).
Id. at 194-97. In addition, the Claims Court denied
damages for ENVYâs overhead costs calculated via its
Resource Code 19 payroll loader. Id. at 195-96.
The parties timely appealed. We have jurisdiction
under 28 U.S.C. § 1295(a)(3). We review legal conclusions
of the Claims Court de novo. Ind. Mich. Power Co. v.
United States, 422 F.3d 1369, 1373 (Fed. Cir. 2005).
Factual findings are reviewed for âclear error.â Id.
DISCUSSION
I Assignment
The government argues that the NWPAâs assignment
provision does not allow for either the assignment of
claims under the Standard Contract or a partial assignment of the contract itself from Vermont Yankee to
ENVY.
VERMONT YANKEE NUCLEAR POWER
v. US
10
A
The government first argues that the NWPAâs assignment provision does not allow for the assignment to
ENVY of claims against the government previously accrued by Vermont Yankee under the Standard Contract.
In general, the Assignment of Claims Act (âClaims Actâ)
bars the assignment of claims against the United States
government unless the assignment is made âafter [the]
claim is allowed, the amount of the claim is decided, and a
warrant for payment of the claim has been issued.â 31
U.S.C. § 3727(b). However, the restrictions of the Claims
Act may be waived by the government either by an express contractual provision or otherwise. See, e.g., Delmarva Power & Light Co. v. United States, 542 F.3d 889,
891-93 (Fed. Cir. 2008). With respect to the assignment
provisions in the NWPA and the Standard Contract, we
recently held that âCongressâ intent is manifest in the
plain language of the NWPA: a party to the Standard
Contract may assign its rights,â including âthe partyâs
right to collect damages incurred due to an existing,
ongoing breach.â Dominion Res., Inc. v. United States,
641 F.3d 1359, 1363 (Fed. Cir. 2011). The government
now concedes that our decision in Dominion Resources
âdisposes of the claim assignment issue.â Appellantâs
Reply Br. 16. Accordingly, we affirm the Claims Courtâs
holding that the assignment of pre-existing claims from
Vermont Yankee to ENVY was valid. 4
B
The government also argues that the NWPAâs assignment provision does not allow for the partial assignThe assignability of claims has no bearing on the
assignability of continuing rights and obligations of a
government contract, which, as discussed below, is governed by the Assignment of Contracts Act.
4
11
VERMONT YANKEE NUCLEAR POWER
v. US
ment of the rights and obligations designated in the
Standard Contract, and in particular does not allow a
partial assignment where Vermont Yankee retained the
obligation to pay the one-time fee.
For contracts with the federal government, the Assignment of Contracts Act (âContracts Actâ) provides:
No contract or order, or any interest therein, shall
be transferred by the party to whom such contract
or order is given to any other party, and any such
transfer shall cause the annulment of the contract
or order transferred, so far as the United States is
concerned. All rights of action, however, for any
breach of such contract by the contracting parties,
are reserved to the United States.
41 U.S.C. § 15(a) (2006). 5 Our precedents have established that the government may consent to or waive any
objections it may have to assignments that would otherwise be in violation of the Contracts Act. See Tuftco Corp.
v. United States, 614 F.2d 740, 745-46 (Ct. Cl. 1980).
Specifically, our predecessor court noted that the government may recognize the validity of an assignment outside
the bounds of the Contracts Act by its âcourse of conduct,
its statements to the parties and its dealings with the
assignee.â Id. at 745.
Here, the Standard Contract allows for the assignment of the rights and duties of the Standard Contract,
but says nothing about the validity of partial assignments. Further, the Standard Contract expressly re5
41 U.S.C. § 15 was recodified on January 4, 2011,
in substantially similar form, at 41 U.S.C. § 6305. Because section 15 was still in effect at the time of the
disputed assignment, we will refer to that section for the
purposes of this appeal.
VERMONT YANKEE NUCLEAR POWER
v. US
12
quires a âtransfer of title to the [SNF] . . . involvedâ along
with an assignment of the ârights and dutiesâ of the
contract holder. J.A. 120; see also 10 C.F.R. § 961.11, art.
XIV. Indeed, we have recognized that â[a] party to a
standard contract cannot transfer its rights and duties to
another party without also transferring title to the SNF.â
Dominion Res., 641 F.3d at 1363. This requirement that
the rights and duties of the Standard Contract must be
tied to the title of the involved SNF suggests that all of
the rights and duties under the Standard Contract must
be assigned together.
Moreover, under standard contract law, assignments
are generally not permitted in situations where they
would disadvantage the obligor. âA contractual right can
be assigned unless (a) the substitution of a right of the
assignee for the right of the assignor would . . . materially
increase the burden or risk imposed on him by his contract, or materially impair his chance of obtaining return
performance . . . .â Restatement (Second) of Contracts
§ 317(2) (1981). âWhat is . . . an increase in burden or
risk . . . depends on the nature of the contract and on the
circumstances.â Id. cmt. d. But at the least, âif the obligor is to perform in exchange for the promise of one
person to render a return performance at a future time,
substitution of the return promise of another impairs the
obligorâs expectation of counter-performance.â Id. Here,
the government has a strong interest in having all of the
rights and duties under the Standard Contract, including
the obligation to pay the one-time fee, reside in the same
party. Requiring any assignments of the Standard Contract to be complete would ensure that the government
would only have to deal with a single party in order to
secure return performance or to resolve potential disputes.
13
VERMONT YANKEE NUCLEAR POWER
v. US
Vermont Yankee nonetheless argues that its retention
of the obligation to pay the one-time fee puts the government at no greater risk than would exist without the
partial assignment. According to Vermont Yankee, this is
because DOE does not have to perform under the Standard Contract until after the one-time fee is paid, assuming that, unlike the present situation, the government
were otherwise willing to perform. 6 But DOE has an
overarching interest in the goals of the NWPA, that is, to
establish a federal program âfor the disposal of . . . spent
nuclear fuel.â 42 U.S.C. § 10131(b)(2). Thus, any additional risk that the SNF could not be properly disposed of
(because of a non-payment or a delayed payment of the
one-time fee) would disadvantage the government.
For these reasons, we disagree with the Claims
Courtâs conclusion that â[t]he range of assignments permitted under the NWPA . . . extends to the âpartialâ assignment of rights and duties created by the Standard
Contract.â Vermont Yankee I, 73 Fed. Cl. at 240.
C
However, an improper assignment does not automatically nullify the contract; rather it gives the government
the option to nullify the contract. See Tuftco Corp., 614
F.2d at 745. As described above, the governmentâs right
to void an assignment under the Contracts Act can be
waived. See id. at 745-46. Here, the government became
The government argued below that it had no duty
to perform, and thus could not be held liable for partially
breaching the Standard Contract until after the one-time
fee was paid. See Vermont Yankee I, 73 Fed. Cl. at 243.
However, the Claims Court held that payment of the onetime fee was not yet due, and thus Vermont Yankeeâs
deferral of the one-time fee did not excuse the governmentâs failure to perform. Id. at 244. The government
does not raise that issue on appeal.
6
VERMONT YANKEE NUCLEAR POWER
v. US
14
aware of the assignment and continued to accept postassignment payments of the quarterly fee from ENVY for
six years from 2006 (when it discovered the partial nature
of the assignment) up to the present. At the same time,
the government sought to invalidate the assignment at
summary judgment, arguing that â[b]ecause the contract
assignment to ENVY [was] defective, ENVY does not have
any privity of contract with DOE.â Defendantâs Motion
for Summary Judgment Regarding the Invalid Assignment of Plaintiffâs Standard Contract at 2, Vermont
Yankee I, 73 Fed. Cl. 236 (No. 03-2663C). While, as the
dissent points out, this course of conduct would not necessarily waive the governmentâs right to sue for damages for
breach of contract, it most assuredly prevents the government from seeking to undo (or to refuse to recognize)
the assignment of the Standard Contract from Vermont
Yankee to ENVY. The receipt of benefits is directly
inconsistent with the refusal to recognize the validity of
the assignment.
In comparable situations, it is well established that
the continued receipt of benefits under a contract bars the
non-breaching party from seeking to rescind the contract
and secure restitution. As the Supreme Court stated in
Mobil Oil Exploration & Producing Southeast, Inc. v.
United States, 530 U.S. 604, 622 (2000), âacceptance of
performance under a once-repudiated contract can constitute a waiver of the right to restitution that repudiation
would otherwise create.â Following Mobil Oil, we have
held that it âis clear that the receipt of partial performance by the plaintiff will bar restitution.â Old Stone Corp.
v. United States, 450 F.3d 1360, 1371-74 (Fed. Cir. 2006)
(finding that plaintiffâs continued receipt of benefits
waived the right to restitution, but not the right to re-
15
VERMONT YANKEE NUCLEAR POWER
v. US
cover damages). 7 The cases cited by the dissent are not to
the contrary. Each involved a situation in which the nonbreaching party was held entitled to sue for partial
breach, despite the continued receipt of benefits because
the non-breaching party supplied timely notice of the
breach. There is no inconsistency between the receipt of
benefits and a suit for partial breach. None of those cases
involved a situation in which the non-breaching party
sought to undo the contract in its entirety. 8
Accordingly, we hold that the partial assignment of
the Standard Contract from Vermont Yankee to ENVY is
effective.
See also Richard A. Lord, Williston on Contracts
§ 39:32 (4th ed. 2000) (âWhen one party commits a material breach of contract, the other party has a choice between two inconsistent rightsâhe or she can either elect
to allege a total breach, terminate the contract and bring
an action, or, instead, elect to keep the contract in force,
declare the default only a partial breach, and recover
those damages caused by that partial breachâbut the
nonbreaching party, by electing to continue receiving
benefits pursuant to the agreement, cannot then refuse to
perform his or her part of the bargain.â); id. § 40:1 (â[I]f a
party in default under a contract is allowed to continue to
perform, this precludes any right of the other party to
rescind the contract or declare a material breach and
refuse to further perform . . . .â).
8
See Westfed Holdings, Inc. v. United States, 407
F.3d 1352, 1356 (Fed. Cir. 2005) (plaintiff seeking reliance
damages); N. Helex Co. v. United States, 455 F.2d 546,
555 (Ct. Cl. 1972) (plaintiff seeking remainder of full
payment after the acceptance of partial payment); Inland
Trucking Corp. v. United States, 281 F.2d 457, 458 (Ct. Cl.
1960) (plaintiff seeking withheld portions of final payment).
7
VERMONT YANKEE NUCLEAR POWER
v. US
16
II Scope of the Partial Assignment
Vermont Yankee challenges the Claims Courtâs holding that it had transferred to ENVY each of the claims it
brought against DOE in this case. Vermont Yankee
argues that it retained its pre-closing mitigation costs
claims and its diminution-in-value claim.
Under the section entitled âTransfer of Assets,â the
PSA provided:
Upon the terms . . . contained in this Agreement,
at the Closing [Vermont Yankee] will sell, assign,
convey, transfer and deliver to [ENVY], and
[ENVY] will purchase, assume and acquire from
[Vermont Yankee], . . . all of [Vermont Yankee]âs
right, title and interest immediately prior to the
Closing in and to all of the properties and assets
constituting or used in the operation of the
[VYNPS] Facility . . . .
J.A. 195-96 (PSA § 2.1). Specifically listed amongst the
transfer of assets were the following:
(n) Subject to Section 6.11(b), any claims of [Vermont Yankee] related to the Department of Energy's defaults under the DOE Standard Contract
accrued as of the Closing, whether relating to periods prior to or following the Closing, excluding
such claims as may relate to the one-time fee with
respect to fuel used to generate electricity prior to
April 7, 1983[.]
J.A. 197 (emphasis added) (PSA § 2.1(n)). As noted in
section 2.1(n) of the PSA, the transfer of claims was
subject to section 6.11(b). That section, under the title of
âSpent Nuclear Fuel Fees,â provided:
17
VERMONT YANKEE NUCLEAR POWER
v. US
(b) [Vermont Yankee] agrees, upon receipt of at
least 30 days advance written notice from [ENVY]
of the date on which the one-time fee for fuel
burned prior to April 7, 1983 under the DOE
Standard Contract will become due and payable in
accordance with the terms of the DOE Standard
Contract, to cause such fee to be duly paid when
due, subject to any rights of set-off to which [Vermont Yankee] may be entitled by reason of the Department of Energyâs defaults under said DOE
Standard Contract.
J.A. 241 (emphasis added) (PSA § 6.11(b)). Under âExcluded Assets,â the PSA similarly listed the following:
(i) The Vermont Yankee Spent Fuel Disposal
Trust and claims of [Vermont Yankee] related or
pertaining to [DOE]âs defaults under the DOE
Standard Contract to the extent applicable to the
one-time fee with respect to fuel used to generate
electricity prior to April 7, 1983[.]
J.A. 198 (PSA § 2.2(i)).
The Claims Court found that while Vermont Yankeeâs
claims âmay stem from the pre-1983 fuel, they are unrelated to the one-time fee,â and were thus not retained by
Vermont Yankee under the terms of the PSA. Vermont
Yankee II, 84 Fed. Cl. at 347. It is not perfectly clear
what exactly is included in the âset-offâ referred to in the
âSpent Nuclear Fuel Feesâ section. But Vermont Yankee
does not argue that the claims in question are related to
the one-time fee. Rather, Vermont Yankee argues that
the âset-offâ encompassed in 6.11(b) is not limited to items
related to the one-time fee, but instead covers claims for
costs ârelated to DOEâs breach of and default on its duty
to pick up the pre-April 7, 1983 SNF for which Vermont
Yankee agreed to pay the one-time fee.â Vermont Yankee
VERMONT YANKEE NUCLEAR POWER
v. US
18
Br. 21. Vermont Yankeeâs interpretation of the PSA is not
plausible, and the PSA is clear that claims not related to
the one-time fee are not excluded from the transfer to
ENVY.
Thus, we affirm the Claims Courtâs holding that Vermont Yankee transferred to ENVY its claims for preclosing mitigation costs and diminution in value, and that
Vermont Yankee could not assert those claims in this
litigation.
III Vermont Legislation-Related Costs
The government challenges the Claims Courtâs award
of $9,608,189 in damages for the costs incurred to obtain
approval from the State of Vermont to build an on-site dry
storage facility.
A
At the time Vermont Yankee signed the Standard
Contract in 1983, Vermont required that utilities obtain
legislative approval prior to constructing a âfacility for
deposit, storage, reprocessing or disposal of spent nuclear
fuel.â Vt. Stat. Ann. tit. 10, § 6501 (1982). Vermont
Yankee enjoyed a company-specific statutory exemption
for the âtemporary storage . . . of spent nuclear fuel.â Id.
§ 6505. But after the 2002 sale of VYNPS to ENVY, the
Attorney General of Vermont rendered an opinion in 2004
stating that the statutory exemption did not extend to
ENVY as the successor of Vermont Yankee. After unsuccessfully lobbying the Vermont general assembly to
extend the exemption, ENVY commenced negotiations
with the state to gain separate legislative approval.
On June 3, 2005, the Vermont state legislature enacted the Dry Cask Storage Authorization Act (âDry
Storage Actâ). The Dry Storage Act approved the construction of a dry storage facility contingent on ENVYâs:
19
VERMONT YANKEE NUCLEAR POWER
v. US
(1) obtaining a Certificate of Public Good (âCertificateâ)
from the Vermont Public Service Board (âBoardâ) pursuant to Vt. Stat. Ann. tit. 30, § 248; and (2) complying with
the terms of a spent fuel storage Memorandum of Understanding, which had been negotiated with the Vermont
Department of Public Service and was also signed on
June 21, 2005. See Vt. Stat. Ann. tit. 10, § 6522 (2012);
see also Entergy Nuclear, 95 Fed. Cl. at 176. ENVY
received the required Certificate from the Board and
entered into the Memorandum of Understanding (âMemorandumâ). The Memorandum and the Certificate, however, imposed multiple requirements on ENVY. The
Memorandum required ENVY to pay, over the course of
several years, a total of $15,625,000 into the Clean Energy Development Fund, which was also established by
the Dry Storage Act. See Vt. Stat. Ann. tit. 10, § 6523
(2010) (recodified at Vt. Stat. Ann. tit. 30, § 8015 (2012)).
Due to the perceived inadequacy of an NRC-required flood
analysis relating to storage safety, the Certificate required ENVY to conduct an additional flood analysis to
demonstrate that the dry storage facility was not vulnerable to potential flooding. The Memorandum also required ENVY to construct a visual barrier on two sides of
the dry storage facility.
ENVY seeks: (1) $3,385,783 for legal and lobbying
costs; (2) $5,625,000 for contributions made to the Vermont Clean Energy Development Fund during the period
in question here; (3) $184,552 for the performance of a
river flood analysis; and (4) $412,854 for the construction
of a visual barrier to the dry-storage facility. Though we
affirm the award of damages for ENVYâs legal and lobbying fees, we hold that the Claims Court clearly erred in
awarding damages to ENVY for payments made into the
Vermont Clean Energy Development fund, performance of
a flood analysis, and construction of a visual barrier.
VERMONT YANKEE NUCLEAR POWER
v. US
20
B
The government challenges that these costs were not
foreseeable at the time of contracting in 1983. As we held
in Indiana Michigan, 422 F.3d at 1373, damages must be
âreasonably foreseeable by the breaching party at the
time of contracting.â See also Williston on Contracts
§ 64:29 (â[T]he defendant [must have] had reason to
foresee [the damages] as a probable result of the defendantâs breach when the contract was made.â). ENVY
contends that the foreseeability requirement for each of
the above listed categories is satisfied because the need to
construct additional on-site facilities was foreseeable.
There is no need, ENVY argues, to establish foreseeability
of each particular type of cost incurred. This is incorrect.
The Restatement and relevant treatises have uniformly set forth the relevant standard and make clear
that a plaintiff must show that the type of damages are
foreseeable as well as the fact of damage. â[D]amages are
not recoverable for loss that the party in breach did not
have reason to foresee as a probable result of the breach
when the contract was made.â Restatement (Second) of
Contracts § 351. Although this does not require âactual
foresightâ that the breach will cause a âspecific injury or a
particular amount in money[,] . . . the injury actually
suffered [still] must be one of a kind that the defendant
had reason to foresee and of an amount that is not beyond
the bounds of reasonable prediction.â Joseph M. Perillo,
11 Corbin on Contracts § 56.7, at 108 (rev. ed. 2005)
(emphasis added). â[R]emoteness in space and time and
the number of intervening events have obvious bearing on
foreseeability.â Williston on Contracts § 64:13.
These principles have been adopted in our cases.
While a âspecific lossâ need not be foreseeable, Anchor
Sav. Bank, FSB v. United States, 597 F.3d 1356, 1364
21
VERMONT YANKEE NUCLEAR POWER
v. US
(Fed. Cir. 2010), it is well-established that âa plaintiff
must prove that . . . [the] type of damages were foreseeable,â Landmark Land Co. v. FDIC, 256 F.3d 1365, 1378
(Fed. Cir. 2001) (emphasis added). Similarly, our predecessor court in Gardner Displays Co. v. United States, 346
F.2d 585, 589 (Ct. Cl. 1965), held that âconsequential
damages involves consideration of the type of loss foreseeable by the contracting parties at the time of their
agreement.â Unquestionably, âthe foreseeability prong
applies to the type of loss.â Sacramento Mun. Util. Dist.
v. United States, 293 F. Appâx 766, 771 (Fed. Cir. 2008).
In keeping with this general rule, we have held that
plaintiffs cannot recover breach of contract damages
where the type of loss was not foreseeable. For example,
in Old Stone, 450 F.3d 1360, a Winstar case, the plaintiff
holding company was forced to sell valuable subsidiary
entities in order to mitigate the governmentâs breach and
did not have those assets available to help it solve other
problems not caused by the breach. This resulted in
seizure of the thrift. We held that damages resulting
from the seizure were not foreseeable because the plaintiff
did not establish that âthis extended chain of causation
was foreseeable.â Id. at 1376. We explained:
[E]ven if the need for replacement capital was
foreseeable [as a result of the governmentâs
breach], that hardly establishes that the adverse
consequences alleged to flow from the need to
make [capital] infusions were foreseeable . . . .
â[T]he mere circumstance that some loss was foreseeable, or even that some loss of the same general kind was foreseeable, will not suffice if the
loss that actually occurred was not foreseeable.â
Id. (quoting Restatement (Second) of Contracts § 351 cmt.
a). Similarly, in Landmark Land, the plaintiff land
VERMONT YANKEE NUCLEAR POWER
v. US
22
holding company, which had acquired a struggling thrift
pursuant to a contract with the government, later transferred almost all of its land holdings to that struggling
thrift in order to receive favorable tax treatment. 256
F.3d at 1369-71. When the thrift was later seized as a
result of the governmentâs breach, we held that it was not
foreseeable at the time of contracting that the plaintiff
would have transferred essentially all of its assets to the
struggling thrift, and we therefore denied plaintiffâs
damage claim for the value of those assets. Id. at 137879; see also Anchor Savings, 597 F.3d at 1364 (explaining
that âthe mere circumstance that some loss was foreseeable may not suffice to impose liability for a particular
type of loss that was so unusual as not to be foreseeableâ
(quoting E. Allan Farnsworth, Farnsworth on Contracts
§ 12.14, at 262 (3d ed. 2004))); Prudential Ins. Co. of Am.
v. United States, 801 F.2d 1295, 1301 (Fed. Cir. 1986)
(finding government could not have foreseen that holding
over on its lease would cause the landlord to lose a tenant
for âother property in excess of that occupied by the
governmentâ). This foreseeability standard has also been
applied in SNF cases. In Indiana Michigan, we held that
the utilityâs âhigh costâ and âspeculativeâ investment in an
alternative out-of-state private storage facility, was
unforeseeable even though we also determined that âDOE
should have foreseen that its breach would force Indiana
Michigan to find alternate storage for its SNF.â 422 F.3d
at 1376.
This is not a case like Citizens Federal Bank v. United
States, 474 F.3d 1314 (Fed. Cir. 2007), another Winstar
case where the adverse tax consequences of the plaintiffsâ
mitigation activities were foreseeable because they existed in the code at the time of the transaction. Nor is
this case like Anchor Savings, where it was foreseeable
that acquiring thrifts would have to sell investments to
23
VERMONT YANKEE NUCLEAR POWER
v. US
raise regulatory capital because the government previously âneeded and expectedâ acquiring thrifts like Anchor
Savings âto leverage its [later disallowed] goodwill into
[those] profitable investments.â 597 F.3d at 1362.
C
The question is whether ENVY has established the
foreseeability of the costs incurred to secure approval for
the dry storage facility from the State of Vermont. With
respect to the legal and lobbying expenses incurred by
ENVY to secure state approval of the dry storage facility,
we agree that ENVY has established foreseeability.
At the time the Standard Contract was signed in
1983, it was foreseeable that at least some form of approval was required by the State of Vermont for the
construction of a dry storage facility at VYNPS. For
example, a Vermont statute, enacted in 1977, provided
that:
No facility for deposit, storage, reprocessing or
disposal of spent nuclear fuel elements or radioactive waste material shall be constructed or established in the state of Vermont unless the general
assembly first finds that it promotes the general
good of the state and approves, through either bill
or joint resolution, a petition for approval of the
facility.
Vt. Stat. Ann. tit. 10, § 6501(a). Although an exception to
the statute was adopted in 1979 specifically for Vermont
Yankee, see id. § 6505, and even though ENVY may have
itself believed that this exception was transferable, it was
still foreseeable that approval from the Vermont legislature might have been required for ENVY. The assignment provision in the Standard Contract shows that the
sale of VYNPS and the assignment of the Standard Con-
VERMONT YANKEE NUCLEAR POWER
v. US
24
tract was foreseeable. And the fact that the legislature
had gone so far as to create an exemption that applied
only to Vermont Yankee suggested that there may be
further legislative action in the future related to that
exemption or that the exemption would not extend to a
potential successor.
The statute required approval from the state legislature based on its finding that the dry storage facility
âpromote[d] the general good of the state.â While the
specific amount of legal and lobbying fees may not have
been foreseeable, the payment of at least some legal and
lobbying fees was foreseeable. And because the government only challenges the payment of legal and lobbying
fees in general, we have no occasion to determine whether
specific portions of those fees might have been unforeseeable (and hence not recoverable). 9 Accordingly, we affirm
the Claims Courtâs award of $3,385,783 for ENVYâs legal
and lobbying fees.
D
We hold, however, that ENVY has not established
that the government could have foreseen the unprecedented requirement that ENVY contribute money into
Vermontâs Clean Energy Development Fund. The Clean
Energy Development Fund was established in 2005 as
part of the Dry Storage Act. See Vt. Stat. Ann. tit. 30,
§ 8015. The imposed fees bear no relationship to any
costs incurred by the state or its citizens as a result of the
construction of the dry storage facility. It would not be
Thus we need not determine, for example,
whether it was foreseeable that Vt. Stat. Ann. tit. 30,
§ 248(a)(2) would apply to the construction of a dry storage facility and would require ENVY to obtain a Certificate of Public Good from the Vermont Public Service
Board.
9
25
VERMONT YANKEE NUCLEAR POWER
v. US
inaccurate to characterize the fee as a form of blackmail
for the state approval of the construction. ENVY conceded at oral argument that, at the time the Standard
Contract was signed in 1983, neither Vermont nor any
other state had imposed payments similar those into the
Clean Energy Development Fund while licensing a nuclear utility. Moreover, ENVY conceded in another case
that the Clean Energy Development Fund had ânothing to
do with dry cask storage.â J.A. 749. 10
It was particularly unforeseeable that Vermont would
require payments into the Clean Energy Development
Fund because such a requirement raised a substantial
question of preemption and was likely unconstitutional. 11
The only testimony at trial regarding the foreseeability of potential state-imposed costs was the testimony
of an Entergy Services (a sister company of ENVY) employee who stated that there may be some âhidden costs
and surprises regulatory-wiseâ if ENVY needed to transport SNF to other sites. J.A. 1059. Such testimony,
referring generally to âhidden costs and surprises,â and
only applying to situations where ENVY would need to
transport SNF generated at VYNPS off site, does not
speak to the foreseeability of the costs actually imposed
by the state.
11
The State of Vermont alleges that the government
waived its preemption argument by failing to timely
notify the state of the preemption challenge pursuant to
the notice requirements of 28 U.S.C. § 2403(b). Section
2403(b) applies to certain challenges to state statutes in a
âcourt of the United States,â which the Historical and
Statutory Notes explain âis defined in section 451 of this
title.â Id. The definition of âcourt of the United Statesâ in
28 U.S.C. § 451 includes Article III courts, but as we
recognized in Essex Electro Engineers, Inc. v. United
States, 757 F.2d 247, 251 n.1 (Fed. Cir. 1985), the Claims
Court, as an Article I court, is not included within section
451âs definition of âcourt of the United States.â Accordingly, the notice provisions of section 2403 did not apply
to this case in the Claims Court.
10
VERMONT YANKEE NUCLEAR POWER
v. US
26
Through a trilogy of cases, the Supreme Court has established a test evaluating when a state law involving nuclear power is preempted by the United States
governmentâs authority over nuclear safety. See English
v. Gen. Elec. Co., 496 U.S. 72 (1990); Silkwood v. KerrMcGee Corp., 464 U.S. 238 (1984); Pac. Gas & Elec. Co. v.
State Energy Res. Conservation & Dev. Commân, 461 U.S.
190 (1983). â[T]he Federal Government has occupied the
entire field of nuclear safety concerns, except the limited
powers expressly ceded to the States.â Pac. Gas, 461 U.S.
at 212. These limited powers include the statesâ âtraditional responsibility in the field of regulating electrical
utilities for determining questions of need, reliability, cost
and other related state concerns.â Id. at 205. In Pacific
Gas, the Court upheld Californiaâs moratorium only
because the law was based on a non-safety (i.e., economic)
rationale. Id. at 215-16. Under the Supreme Courtâs test,
a state law related to nuclear power is preempted if it: (1)
is motivated by safety concerns, id. at 213, or (2) âha[s]
some direct and substantial effect on the decisions made
by those who build or operate nuclear facilities concerning
radiological safety levels,â English, 496 U.S. at 85.
Here, the required payments into the Clean Energy
Development Fund totaled $15,625,000. This extraction
of money is significant in amount, and, as a condition of
constructing a dry storage facility, could easily deter a
utility from constructing such a facility whose construction is encouraged if not mandated by federal law. See 42
U.S.C. § 10151(a). 12 In Skull Valley Band of Goshute
42 U.S.C. § 10151(a) states: â(1) the persons owning and operating civilian nuclear power reactors have the
primary responsibility for providing interim storage of
spent nuclear fuel from such reactors, by maximizing, to
the extent practical, the effective use of existing storage
facilities at the site of each civilian nuclear power reactor,
12
27
VERMONT YANKEE NUCLEAR POWER
v. US
Indians v. Nielson, 376 F.3d 1223, 1248-50 (10th Cir.
2004), the Tenth Circuit held that state provisions requiring payments to cover the âunfunded potential liabilityâ of
the site were preempted because âit is not the states but
rather the NRC that is vested with the authority to decide
under what conditions to license an SNF storage facility.â
Unlike the non-preempted state tort claims in English
that only had âsome effectâ on radiological safety decisions, the requirement to pay money into the Clean
Energy Development Fund could have a âdirect and
substantial effectâ on decisions concerning radiological
safety. English, 496 U.S. at 85. Such a regulation of
âmatters directly affecting the radiological safety of nuclear-plant construction and operationâ is likely preempted, ââeven if [it was] enacted out of nonsafety
concerns.ââ Id. at 84 (quoting Pac. Gas, 461 U.S. at 212).
Notably, ENVY itself challenged the payments to the
Clean Energy Development Fund on preemption grounds
in a separate action before a federal district court (abandoning that challenge only after the Claims Court
awarded those fees as damages), see Entergy Nuclear Vt.
Yankee, LLC v. Shumlin, No 1:11-cv-99, 2012 WL 162400
(D. Vt. Jan. 19, 2012), and even now does not argue that
the Vermont law can escape preemption under federal
law.
ENVY argues that â[d]isputing the stateâs authority to
require the payments was not viewed as being in the best
interests of the companyâ because âthe company needed to
continue to operate and do additional business in the
and by adding new onsite storage capacity in a timely
manner where practical; [and] (2) the Federal Government
has the responsibility to encourage and expedite the effective use of existing storage facilities and the addition of
needed new storage capacity at the site of each civilian
nuclear power reactor . . . .â (emphasis added).
VERMONT YANKEE NUCLEAR POWER
v. US
28
state.â ENVY Br. 52. Thus, they argue, their choice to
acquiesce to the monetary demands of the state was
reasonable. But whether or not ENVYâs choice to acquiesce to the likely preempted state requirements was
reasonable as a business proposition does not reflect on
whether the costs incurred in complying with those requirements were foreseeable at the time the Standard
Contract was signed. A leading treatise makes clear that
reasonableness and foreseeability are separate requirements in the context of mitigation damages:
If the attempt [to mitigate] is reasonable . . . the
injured party can recover . . . [but] [t]his is subject . . . to the qualification applicable to the right
to recover consequential damages of any kind,
namely, that the defendant had reason to foresee
them as a probable result of the defendantâs
breach when the contract was made.
Williston on Contracts § 64:29. Just because it may have
been in ENVYâs best interest to maintain good relations
with the state and to agree to pay a fee that was likely
preempted by federal law does not render the fee recoverable. ENVYâs acquiescence to the state of Vermont went
so far as to agree not to challenge the requirements of the
Memorandum on preemption grounds. But ENVY cannot
agree to improper state requirements, agree not to challenge those improper requirements on preemption
grounds, and then pass the expense of complying with
those requirements to the federal government. As we
held in Hercules Inc. v. United States, a plaintiff cannot
voluntarily forego defending itself against third-party
claims that are barred as a matter of law, and then recover those costs from the government. 24 F.3d 188, 200
(Fed. Cir. 1994), affâd on other grounds, 516 U.S. 417
(1996).
29
VERMONT YANKEE NUCLEAR POWER
v. US
For these reasons, we reverse the Claims Courtâs
award to ENVY of $5,625,000 in damages for payments
made into the Clean Energy Development Fund.
E
It was similarly unforeseeable that Vermont would
require the performance of a flood analysis, which also
raises a substantial question of preemption. Here, the
flood analysis was required due to the perceived inadequacies of a previously performed NRC-required flood
analysis that âtook into account a âprobable maximum
floodâ at the site to ensure that such flooding would not
create safety issues at the plant.â Entergy Nuclear, 95
Fed. Cl. at 179 (emphasis added). ENVY has failed to
point to any evidence that, as of 1983, Vermont or any
other state had required utilities to perform additional
flood control analyses beyond those already performed
under federal regulations. In any event, because the
requirement to perform an additional analysis was directly motivated by safety concerns, it is clear that the
flood analysis requirement was likely preempted under
Pacific Gas, 461 U.S. at 215; see also ANR Pipeline Co. v.
Iowa State Commerce Commân, 828 F.2d 465, 471-72 (8th
Cir. 1987) (finding state safety regulations to be preempted by the federal regulation of gas pipelines). The
required flood analysis was thus not foreseeable. Accordingly, we reverse the Claims Courtâs award of $184,552 in
damages for the performance of the river flood analysis.
F
ENVY has also failed to meet its burden of establishing that the requirement to build a visual barrier on two
sides of the dry storage facility was foreseeable. Notably,
the Public Service Board commented that â[VYNPS] is an
industrial site, and from an aesthetic perspective, the
addition of a limited number of concrete and metal con-
VERMONT YANKEE NUCLEAR POWER
v. US
30
tainers results in little change to the overall aesthetics of
the site.â Entergy Nuclear, 95 Fed. Cl. at 178. The lack of
an impact that dry storage would have on the overall
aesthetics of a site suggests that the imposition of aesthetic requirements for a dry storage facility in particular
was not foreseeable. Moreover, ENVY has failed to point
to any evidence that, as of 1983, Vermont or any other
state had imposed such aesthetic requirements as a
prerequisite for licensing a utility. Accordingly, we reverse the Claims Courtâs award of $412,854 for the construction of the visual barrier.
IV Disposal of Contaminated Material and
Characterization of Spent Fuel
The government challenges the Claims Courtâs award
of $276,980 to ENVY for the costs of disposing contaminated soil and asphalt, and $156,000 for the costs of
performing a characterization on SNF moved into on-site
dry storage. We hold that the Claims Court clearly erred
in awarding damages to ENVY for the costs of disposing
contaminated material and for the costs of characterizing
SNF moved into on-site dry storage.
In Yankee Atomic Electric Co. v. United States, we explained that âdamages for breach of contract require a
showing of causation,â which in turn necessitates a âcomparison between the breach and non-breach worlds.â 536
F.3d 1268, 1273 (Fed. Cir. 2008). As we further explained
in Energy Northwest v. United States, it is the plaintiff
who âmust prove the extent to which his incurred costs
differ from the costs he would have incurred in the nonbreach world.â 641 F.3d 1300, 1306 (Fed. Cir. 2011).
Thus, a plaintiff is entitled to recover costs âonly to the
extent it can prove, to a reasonable certainty, that but for
the governmentâs breach they would not have been incurred.â Id. at 1307.
31
VERMONT YANKEE NUCLEAR POWER
v. US
A
During the construction of the dry-storage facility at
VYNPS, ENVY discovered contaminated soil and asphalt
and incurred $276,980 in costs having that contaminated
material disposed. The Claims Court did not find that
DOEâs breach caused the contamination, but rather found
that DOEâs breach caused ENVY to discover the contamination. The government challenges these costs on the
grounds that they would have been incurred in a nonbreach world when the site was eventually decommissioned. Without the benefit of our decision in Energy
Northwest, the Claims Court held that âit [was] the Government, not ENVY, that [bore] the burden of demonstrating that these future costs at decommissioning would
be identical.â Entergy Nuclear, 95 Fed. Cl. at 191. However, Energy Northwest clearly dictates that it was
ENVYâs burden to âsubmit a hypothetical model establishing what its costs would have been in the absence of
breach.â 641 F.3d at 1305. Because ENVY failed to prove
the amount by which its actual removal costs were different from what its removal costs would have been at
decommissioning in a non-breach world, we reverse the
Claims Courtâs award of $276,980 for the disposal of the
contaminated material.
B
In preparing SNF for on-site dry storage, ENVY incurred $156,000 in costs to characterize the SNF. Such a
characterization is required for storage in any NRCapproved cask. ENVYâs theory is âthat the fuel characterization may well be required a second timeâ for DOEsupplied casks, âwhen and if DOE performs.â ENVY Br.
57. Thus, ENVY argues that it may have to pay for two
characterizations, whereas in a non-breach world, it
would have had to pay for only a single characterization
VERMONT YANKEE NUCLEAR POWER
v. US
32
for the DOE-supplied casks. However, ENVY has not
established the likelihood that DOE will require ENVY to
incur further characterization costs upon performance. In
fact, the Claims Court noted that âENVY [itself] believes
that DOE will acceptâ the previously performed characterization before finding that it is âpossible that another
review of the spent fuel condition will be required.â
Entergy Nuclear, 95 Fed. Cl. at 182. Further, ENVY has
failed to âsubmit a hypothetical modelâ comparing what
its costs would be in breach versus non-breach worlds in
the event that DOE does eventually require further
characterization. Energy Nw., 641 F.3d at 1305. Accordingly, we reverse the Claims Courtâs award to ENVY of
$156,000 in costs incurred for the spent fuel characterization.
V Issues Resolved By Our Recent Precedent
A Cost of Capital
ENVY challenges the Claims Courtâs denial of
$7,472,866 in damages for the cost of capital to fund
ENVYâs mitigation activities. In Energy Northwest, we
held that the no-interest rule barred parties to the Standard Contract from recovering the costs of financing
mitigation projects. 641 F.3d at 1310-13 (citing 28 U.S.C.
§ 2516(a)); see also Sys. Fuels, Inc. v. United States, 666
F.3d 1306, 1310-11 (Fed. Cir. 2012). We further explained
in Boston Edison Co. v. United States that the âcommercial enterprise exceptionâ to the no-interest rule did not
apply in the context of the NWPA. 658 F.3d 1361, 1371
(Fed. Cir. 2011).
Consistent with our decisions in Energy Northwest
and Boston Edison, we affirm the Claims Courtâs denial of
ENVYâs cost of capital claims.
33
VERMONT YANKEE NUCLEAR POWER
v. US
B Overhead Costs
ENVY also challenges the Claims Courtâs denial of
$788,414 in damages for its capital suspense loader
overhead costs. Without the benefit of our recent SNFrelated decisions, the Claims Court denied ENVYâs capital
suspense loader overhead claims despite acknowledging
that â[ENVY]âs accounting practices follow Generally
Accepted Accounting Principles [GAAP] and FERC Guidelines.â Entergy Nuclear, 95 Fed. Cl. at 195. In System
Fuels, where the âPlaintiffs used accounting procedures as
mandated by FERC and consistent with [GAAP],â we held
that the plaintiffâs accounting records sufficiently âdemonstrate[d] the effect of the mitigation project on the capital
pools entitlement with reasonable particularity.â 666
F.3d at 1312 (internal quotation marks omitted); see also
Energy Nw., 641 F.3d at 1309 (allowing recovery for the
âportion of [the plaintiffâs] overhead costs fairly allocated
to support of the mitigation via generally accepted accounting practicesâ); Bos. Edison, 658 F.3d at 1370 (allowing recovery of âthe portion of overhead costs (calculated
using GAAP) that was attributable to mitigation projectsâ).
Consistent with our recent decisions, we reverse the
Claims Courtâs denial of $788,414 in damages for overhead costs allocated to ENVYâs mitigation activities via
the capital suspense loader.
However, we decline to review the Claims Courtâs
holding with respect to the Resource Code 19 payroll
loader based on ENVYâs limited arguments on appeal.
The Claims Court found that Resource Code 19 payroll
loader included, among other items, pension costs for
retired employees that could not be attributed to mitigation activity and were thus not recoverable. Entergy
Nuclear, 95 Fed. Cl. at 195-96. On appeal, ENVY has
VERMONT YANKEE NUCLEAR POWER
v. US
34
failed to develop an argument as to why Resource Code 19
payroll loader overhead costs should be considered analogous to other overhead costs that we have deemed to be
sufficiently attributed to mitigation activities and thus
recoverable. Because ENVY has not adequately briefed
its claim with respect to the Resource Code 19 payroll
loader, we affirm the Claimâs Courtâs denial of $10,013 in
damages for that particular overhead cost.
AFFIRMED IN PART, REVERSED IN PART, and
REMANDED
COSTS
No costs.
United States Court of Appeals
for the Federal Circuit
__________________________
VERMONT YANKEE NUCLEAR POWER
CORPORATION
Plaintiff-Cross Appellant,
v.
ENTERGY NUCLEAR VERMONT YANKEE, LLC,
AND ENTERGY NUCLEAR OPERATIONS, INC.,
Plaintiffs-Cross Appellants,
v.
UNITED STATES,
Defendant-Appellant.
__________________________
2011-5033, -5034, -5042
__________________________
Appeals from the United States Court of Federal
Claims in consolidated case nos. 02-CV-898 and 03-CV2664, Judge Thomas C. Wheeler.
__________________________
MAYER, Circuit Judge, dissenting-in-part.
I join the courtâs opinion, except for Part I-C, which
concludes that the government waived the right to challenge the partial assignment by Vermont Yankee Nuclear
Power Corporation (âVermont Yankeeâ) of its rights and
obligations under the Department of Energyâs Standard
Contract. There was no waiver because the government
VERMONT YANKEE NUCLEAR POWER
v. US
2
promptly and unequivocally objected to the partial assignment.
ââWaiverâ is a vague term used for a great variety of
purposes, good and bad, in the law. In any normal sense,
however, it connotes some kind of voluntary knowing
relinquishment of a right.â Green v. United States, 355
U.S. 184, 191 (1957). The government never relinquished
its right to challenge Vermont Yankeeâs partial assignment of its rights and obligations under the Standard
Contract. It was not until 2006 that the government
learned, during discovery, that Vermont Yankee breached
the Standard Contract when it assigned its right to have
the government accept spent nuclear fuel (âSNFâ), but
failed to assign the obligation to pay the substantial onetime fee for SNF generated prior to April 1983. Upon
learning of the breach, the government promptly filed a
motion for summary judgment in the Court of Federal
Claims, arguing that the partial assignment violated the
Assignment of Contracts Act, 41
