Brown, et al. v. Nuclear Regulatory Comm'n, et al., No. 11-1441 (8th Cir. 2011)
Annotate this CasePetitioners sought review of a decision by the Nuclear Regulatory Commission (NRC) under the Atomic Energy Act, 42 U.S.C. 2201 et seq., to renew the operating license of the Duane Arnold Energy Center (DAEC) in Palo, Iowa. The court held that the NRC order at issue was entered on December 16, 2010, and the petition for review was not filed until February 28, 2011. Therefore, the petition was filed 14 days late and accordingly, the court dismissed the petition for review as untimely.
Court Description: Civil case - Appeal from the Nuclear Regulatory Commission. Appeal is untimely and the case is dismissed.