American Horse Protection Association, Inc., and the Humanesociety of the United States, Plaintiffs-appellants, v. James Watt, Secretary of the Department of Interior, Frankgregg, Director, Department of Interior, Edwardhastey, Associate Director, Departmentof Interior, et al.,defendants-appellees, 679 F.2d 150 (9th Cir. 1982)

Annotate this Case
US Court of Appeals for the Ninth Circuit - 679 F.2d 150 (9th Cir. 1982) Argued and Submitted Jan. 15, 1982. Decided June 7, 1982

Russell J. Gaspar, Washington, D. C., argued, for plaintiffs-appellants; David M. Barrett, Joseph E. Schuler, Barrett, Hanna, Daly & Gaspar, Washington, D. C., on brief.

David H. Shilton, Atty., U. S. Dept. of Justice, Washington, D. C., argued, for defendants-appellees; Dirk Snel, Washington, D. C., on brief.

Appeal from the United States District Court for the District of Nevada.

Before BROWNING, Chief Judge, SKOPIL and NORRIS, Circuit Judges.

PER CURIAM:


We are asked to review the district court's refusal to enjoin an "interim" wild-horse roundup prior to the filing of an Environmental Impact Statement. The facts are sufficiently outlined in prior opinions on this matter. American Horse Protection Ass'n v. Andrus, 460 F. Supp. 880 (D. Nev. 1978), aff'd in part, vacated in part and remanded, 608 F.2d 811 (9th Cir. 1979). On remand, the district court refused to enjoin a roundup scheduled for September 15, 1980. Appellants filed this appeal on October 24, 1980. They unsuccessfully sought a stay pending appeal from the district court. The roundup originally scheduled for September 15 was completed on November 12, 1980 while this appeal was pending. On February 5, 1981, we granted Appellants' motion to enjoin further roundups pending appeal.

The Secretary contends the case is moot. We agree. Only the September 15 roundup can be challenged as lacking an EIS or as having violated the Wild Free-Roaming Horses and Burros Act, and that roundup has been completed. We cannot order its effects undone. Friends of the Earth, Inc. v. Bergland, 576 F.2d 1377, 1379 (9th Cir. 1978). An EIS has since been filed. Appellants' argument that the EIS is inadequate is not before us since it has not been presented to a district court.

Appellants assert this case involves actions capable of repetition yet evading review. Twelve EIS's are planned for the State of Nevada and only one, for the Tonopah District, has been completed. The twelfth will not be completed until 1988. It is undisputed that additional "interim" roundups are planned. Repetition of the complained-of action is therefore likely.

We are unconvinced, however, that a repetition will evade review. Although the record does not contain the decree, the district court's order notes that "the parties were directed to formulate a decree providing for appropriate notice to AHPA of proposed actions ... and giving to AHPA a reasonable opportunity to challenge BLM action ...." The district court has, therefore, specifically provided for judicial review before action is taken. In the event of an adverse ruling by the district court, plaintiffs can seek a stay pending appeal. Where prompt application for a stay pending appeal can preserve an issue for appeal, the issue is not one that will evade review. Marshall v. Whittaker Corp., Berwick Forge & Fabricating Co., 610 F.2d 1141, 1146 (3d Cir. 1979).

Dismissed.

Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.