Filed 9/29/04
CERTIFIED FOR PUBLICATION
IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA
FIRST APPELLATE DISTRICT
DIVISION FOUR
NACIMIENTO REGIONAL WATER
MANAGEMENT ADVISORY
COMMITTEE,
A104687
Plaintiff and Appellant,
(San Francisco County
Super. Ct. No. CPF-02-501972)
v.
MONTEREY COUNTY WATER
RESOURCES AGENCY,
Defendant and Respondent.
The question presented on appeal is whether a trial court must grant relief from a
dismissal entered for failing to request a hearing on the merits in a California
Environmental Quality Act (CEQA) case when the failure was caused by an attorney’s
inexcusable mistake or neglect. (Code Civ. Proc., § 473, subd. (b) (§ 473(b)); Pub.
Resources Code, § 21167.4, subd (a) (§ 21167.4(a)).) The superior court concluded that
relief is unavailable under these circumstances. We agree with the superior court and
affirm the judgment.
FACTS
Plaintiff Nacimiento Regional Water Management Advisory Committee
(NRWMAC) is a nonprofit corporation representing property owners residing near Lake
Nacimiento in San Luis Obispo County. Defendant Monterey County Water Resources
Agency (Water Resources Agency) manages water resources for Monterey County. On
June 4, 2002, the Water Resources Agency certified an environmental impact report
(EIR), prepared pursuant to CEQA, for the Salinas Valley Water Project (Project). (Pub.
1
Resources Code, § 21000 et seq.) The Project proposes modifications at Lake
Nacimiento. NRWMAC alleges that the Project will damage the lake and surrounding
area, and that the Water Resources Agency ignored these adverse impacts when
approving the EIR.
On July 3, 2002, NRWMAC filed a joint petition for writ of mandate and
complaint for injunctive and declaratory relief in San Luis Obispo County alleging
CEQA violations.1 Pursuant to the parties’ stipulation, the case was transferred to San
Francisco County. On October 4, 2002, the San Luis Obispo court ordered the case
transferred, and issued notice of transfer on October 21, 2002. On October 31, 2002, the
San Francisco Superior Court sent notice that the case had been accepted and filed with
the court. When transferring the case between counties, the parties had stipulated that
NRWMAC would serve and file its request for hearing on the merits of the petition by
December 1, 2002. NRWMAC failed to request a hearing. (§ 21167.4(a).) As of April
2003, four months after the stipulated deadline, no request for a hearing had been filed.
The Water Resources Agency moved to dismiss the action for noncompliance with the
requirement that a timely request for hearing be made. (§ 21167.4 (a).)
NRWMAC admitted that dismissal was mandated under section 21167.4(a), and
the trial court dismissed the action. NRWMAC then moved for relief under section
473(b) and attached its proposed request for hearing. NRWMAC made no claim of
excusable mistake, but founded its motion entirely upon its counsel’s declaration of
inexcusable mistake. NRWMAC’s counsel stated that he failed to calendar the stipulated
December 1, 2002 deadline for requesting a hearing, and also failed to realize that the
statutory time for requesting a hearing ran from the date that the petition was filed and
not the date of record completion. Counsel declared that NRWMAC “is in this disastrous
procedural position due solely to my inexcusable neglect.”
1
NRWMAC named the Water Resources Agency and the U.S. Army Engineer
District, San Francisco District, as defendants. This appeal concerns the Water
Resources Agency alone.
2
The trial court denied NRWMAC’s motion upon concluding that section 473(b)
relief for inexcusable mistake is not available following mandatory dismissal under
section 21167.4(a). NRWMAC appeals the order denying relief from dismissal.
DISCUSSION
CEQA requires assessment of the environmental consequences of activities
approved or carried out by public agencies. (Pub. Resources Code, § 21000 et seq.;
Laurel Heights Improvement Assn. v. Regents of University of California (1988) 47
Cal.3d 376, 390-392.) Allegations that the public agency failed in its duty to make an
adequate environmental assessment must be expeditiously resolved, and CEQA contains
a number of procedural provisions evidencing legislative intent that the public interest is
not served unless CEQA challenges are promptly filed and diligently prosecuted. (Board
of Supervisors v. Superior Court (1994) 23 Cal.App.4th 830, 836-837.) For example,
CEQA sets short statutes of limitations of only 30 to 180 days in length, requires a
settlement conference within 45 days of service of the petition, and grants trial preference
over all other civil actions. (Id. at p. 837; Pub. Resources Code, §§ 21167, 21167.1,
subd. (a), 21167.8.) “Patently, there is legislative concern that CEQA challenges, with
their obvious potential for financial prejudice and disruption, must not be permitted to
drag on to the potential serious injury of the real party in interest.” (Board of Supervisors
v. Superior Court, supra, 23 Cal.App.4th at p. 837.)
Section 21167.4(a), at issue in this case, is among the procedural provisions
designed to expedite CEQA litigation: “In any action or proceeding alleging
noncompliance with [CEQA], the petitioner shall request a hearing within 90 days from
the date of filing the petition or shall be subject to dismissal on the court’s own motion or
on the motion of any party interested in the action or proceeding.” This District Court
has held that “dismissal of a CEQA claim under Public Resources Code section 21167.4
is mandatory when a petitioner has failed to request a hearing on the writ within 90 days
and a party or the court, sua sponte, moves to dismiss.” (San Franciscans for Reasonable
Growth v. City and County of San Francisco (1987) 189 Cal.App.3d 498, 504.) The
3
hearing that must be requested is a hearing on the merits of the petition, and a hearing on
provisional remedies or other collateral matters does not satisfy the statutory requirement
that a hearing be requested. (Miller v. City of Hermosa Beach (1993) 13 Cal.App.4th
1118, 1135.) “[T]he statutory scheme, which is designed to promote prompt resolution of
CEQA matters, can only be served if a request for a hearing or trial on the ultimate merits
of the petition for writ of mandate is made within 90 days of filing of the petition.”
(Ibid.)
NRWMAC filed its CEQA writ petition on July 3, 2002, and thus its request for a
hearing on the merit of its petition was statutorily due by October 1, 2002. However, the
Water Resources Agency stipulated on September 30, 2002, to extend the deadline to
December 1, 2002, to permit time for the action to be transferred to another county.2
NRWMAC did not request a hearing by the extended deadline and concedes that
dismissal was mandated under CEQA.
However, NRWMAC contends that the Code of Civil Procedure entitles it to relief
from that dismissal because the dismissal was caused by attorney error, even though the
error was admittedly inexcusable. Discretionary relief under section 473(b) for a section
21167.4(a) dismissal caused by an excusable mistake is unquestionably available.
(Miller v. City of Hermosa Beach, supra, 13 Cal.App.4th at pp. 1135-1138; McCormick
v. Board of Supervisors (1988) 198 Cal.App.3d 352, 359.) The issue here, however, is
whether mandatory relief under section 473 for a section 21167.4 dismissal caused by an
inexcusable mistake is required.
In 1988, the Legislature added a provision to section 473 mandating relief for
defaults caused by attorney mistake or neglect upon timely application for relief, without
demonstration that the attorney error was excusable. (Stats. 1988, ch. 1131, § 1, p. 3631;
Leader v. Health Industries of America, Inc. (2001) 89 Cal.App.4th 603, 617-618.) The
2
The parties have not questioned the validity of a party stipulation extending the
time to request a CEQA hearing and we make no determination on that issue.
4
mandatory relief provision for attorney errors was extended to dismissals in 1992.3
(Stats. 1992, ch. 876, § 4, pp. 4071-4072; Leader, supra, at p. 617.) This extension of
mandatory relief to dismissals has created difficulties in application because dismissals
are entered under diverse circumstances and statutory authority, and the purposes of some
dismissal statutes would be defeated if an attorney’s affidavit of fault were sufficient to
vacate every dismissal. The courts have thus had to reconcile section 473(b)’s broadly
stated provision granting relief for attorney-caused dismissals with the many statutes
authorizing dismissal.
“Although the language of the mandatory provision of section 473, subdivision
(b), on its face, ‘affords relief from unspecified “dismissal” caused by attorney neglect,
our courts have, through judicial construction, prevented it from being used
indiscriminately by plaintiffs’ attorneys as a “perfect escape hatch” to undo dismissals of
civil cases.’ ” (Gotschall v. Daley (2002) 96 Cal.App.4th 479, 483.) For example,
“[c]ourts have held the mandatory provision [of section 473(b)] is inapplicable to
voluntary dismissals (Huens v. Tatum [1997] 52 Cal.App.4th [259, 264]) and dismissals
for lapsing of the statute of limitations (Castro v. Sacramento County Fire Protection
Dist. (1996) 47 Cal.App.4th 927, 933), failure to serve a complaint in a timely manner
(Bernasconi Commercial Real Estate v. St. Joseph’s Regional Healthcare System (1997)
57 Cal.App.4th 1078, 1080), failure to prosecute (Peltier [v. McCloud River R.R. Co.
3
Section 473(b) now provides, in pertinent part: “The court may, upon any terms
as may be just, relieve a party or his or her legal representative from a judgment,
dismissal, order, or other proceeding taken against him or her through his or her mistake,
inadvertence, surprise, or excusable neglect. . . . Notwithstanding any other requirements
of this section, the court shall, whenever an application for relief is made no more than
six months after entry of judgment, is in proper form, and is accompanied by an
attorney’s sworn affidavit attesting to his or her mistake, inadvertence, surprise, or
neglect, vacate any (1) resulting default entered by the clerk against his or her client, and
which will result in entry of a default judgment, or (2) resulting default judgment or
dismissal entered against his or her client, unless the court finds that the default or
dismissal was not in fact caused by the attorney’s mistake, inadvertence, surprise, or
neglect.”
5
(1995)] 34 Cal.App.4th [1809, 1817]), and failure to file an amended complaint after a
demurrer has been sustained with leave to amend. (Leader, supra, 89 Cal.App.4th at
p. 620.” (Gotschall, supra, 96 Cal.App.4th at pp. 483-484.)
In Peltier, the court rejected a literal reading of section 473(b)’s mandatory relief
provision and held that section 473(b) was intended to reach only those discretionary
dismissals for delays in prosecution under Code of Civil Procedure section 583.410
(section 583.410) “which occur through failure to oppose a dismissal motion—the only
dismissals which are procedurally equivalent to a default.” (Peltier v. McCloud River
R.R. Co., supra, 34 Cal.App.4th at pp. 1815-1817.) This narrow interpretation of section
473(b)’s mandatory relief provision is consistent with the provision’s “purpose of treating
dismissed plaintiffs and defaulted defendants equally.” (Id. at p. 1819.) The court
observed that a broad reading of section 473(b) to mandate relief for any section 583.410
dismissal would undermine the dismissal statute. “[N]early every discretionary dismissal
is caused by the mistake, inadvertence or neglect of the plaintiff’s attorney,” and thus a
literal application of section 473(b)’s mandatory relief provision would almost nullify the
discretionary dismissal statutes, “as few dismissals entered thereunder would ever
assuredly be final.” (Peltier v. McCloud River R.R. Co., supra, at p. 1816.) Such a result
is insupportable: “the repeal or abrogation of statutes by implication is disfavored, as is
any construction of a statute which would render related statutes a nullity.” (Id. at
pp. 1821-1822.)
The same reasoning applies here. Nearly every section 21167.4 dismissal for
failing to request a hearing on alleged CEQA violations is caused by the mistake,
inadvertence, or neglect of the plaintiff’s attorney, and thus few dismissals would be final
if mandatory relief under section 473 were applied to such dismissals. The CEQA
dismissal statute would effectively be nullified, and the legislative intent that CEQA
challenges be promptly resolved and diligently prosecuted would be defeated. (Board of
Supervisors v. Superior Court, supra, 23 Cal.App.4th at pp. 836-837.)
CEQA sets strict time requirements to protect the public interest in speedy
resolution of CEQA challenges. CEQA requires that a petitioner request a hearing within
6
90 days from the date a petition alleging CEQA noncompliance is filed, or be subject to
dismissal. (§ 21167.4(a).) The trial court establishes a briefing schedule upon receiving
the request for a hearing, with briefing completed 90 days from the date of the request
absent good cause for delay. (§ 21167.4, subd. (c).) To the extent feasible, the hearing is
held within 30 days of the completion of briefing. (Ibid.) The legislature thus plainly
intended that a CEQA challenge be heard within 210 days of commencement, or roughly
seven months, absent exceptional circumstances.
Application of section 473(b)’s mandatory relief provision to CEQA dismissals for
failing to request a hearing within the prescribed 90-day time period would undermine
CEQA’s design for expedited litigation. Section 473(b) authorizes mandatory relief if it
is requested within six months after entry of judgment. If mandatory relief were
available to a CEQA petitioner who failed to request a hearing within 90 days of filing
his or her petition, nine months or more could pass before a request for a hearing was
ever filed. Briefing would be similarly delayed, and resolution would well exceed the
time period set by the legislature for resolution of CEQA challenges.
This case itself demonstrates the frustration of CEQA’s goal of expedited
litigation if mandatory relief under section 473(b) were available for section 21167.4(a)
dismissals. NRWMAC’s request for a hearing was statutorily due October 1, 2002, and
extended by stipulation to December 1, 2002 to allow time for transfer between counties.
NRWMAC failed to meet that deadline, but the Water Resources Agency did not move to
dismiss until April 25, 2003. The court dismissed the action on June 18, 2003, with a
formal order entered later. NRWMAC, to its credit, acted quickly and moved for relief
from the dismissal on July 8, 2003. However, a motion for mandatory relief is timely if
made within six months after entry of judgment of dismissal, so that application of the
mandatory relief provision in this case would have permitted relief from dismissal as late
as December 2003. (§ 473(b).) The deadline for requesting a CEQA hearing would thus
have been extended an entire year, from December 2002 to December 2003. Plainly, the
Legislature’s carefully crafted plan for prompt resolution of CEQA litigation would be
undermined by application of section 473(b)’s mandatory relief provision to dismissals
7
entered for delay in prosecuting a CEQA action under section 21167.4(a). The trial court
properly denied NRWMAC’s motion for relief from dismissal.
DISPOSITION
The judgment of dismissal is affirmed.
_________________________
Sepulveda, J.
We concur:
_________________________
Kay, P.J.
_________________________
Reardon, J.
8
Trial Court:
San Francisco County Superior Court
Trial Judge:
Honorable Ronald Quidachay
Counsel for Appellant:
David Robert Hunt
Hunt & Associates APC
Counsel for Respondent
Monterey County Water
Resources:
Steven Paul Saxton
Kevin M. O’
Downey Brand LLP
Counsel for Association of
Lisabeth D. Rothman
California Water Agencies and Hatch & Parent
League of California Cities,
Amicus Curiae for Respondent:
Counsel for California
Stephen L. Kostka
Building Industry Association, Joshua Safran
Amicus Curiae for Respondent: Bingham McCutchen LLP
9
Daniel Sheldon Hentschke
SD County Water
Authority