Earl Dean McWhorter v. L. J. Perot
Annotate this Case
Download PDF
DIVISION IV
ARKANSAS COURT OF APPEALS
NOT DESIGNATED FOR PUBLICATION
R OBERT J. G LADWIN, Judge
CA05-1330
S EPTEMBER 13, 2006
EARL DEAN McWHORTER
APPELLANT
APPEAL FRO M THE PULASK I
COUNTY CIRCUIT COURT
[NO. CV 04-13762]
V.
HON. BARRY SIMS,
JUDGE
L. J. PEROT
APPELLEE
AFFIRMED
This appeal arises from a lawsuit filed by appellee L. J. Perot against appellant Earl
McWhorter for breach of contract and unjust enrichment. Subsequent to filing his answer
to the complaint, appellant filed a counterclaim against appellee alleging unjust enrichment.
Following a bench trial, the trial court awarded appellee $10,901.83, and dismissed
appellant’s counterclaim. On appeal, appellant asserts that the trial court erred by awarding
excessive damages on the breach-of-contract claim and by dismissing his counterclaim
against appellee. Finding no error, we affirm.
On or about May 30, 2002, the parties entered into a contract for appellant to provide
construction services related to the deck/patio area at appellee’s residence. Although part of
the work was completed, the project was never finished. During the time work was being
performed on the contracted project, appellant and appellee had several other unwritten
agreements for appellant to complete various additional improvements around the property.
Payment for work on certain of those improvements appears to be the subject of appellant’s
counterclaim in this matter.
While it is undisputed that the contract did not specify a date for completion of the
contracted project, the parties discussed the progress on numerous occasions over the two
years of activity. Communication between the parties became contentious on or about May
2, 2004, during a phone conversation in which appellant explained that, due to a shortage of
laborers, he could not finish the contracted project prior to appellee’s requested date of May
28, 2004.1 That conversation abruptly halted all negotiations and work between the parties.
Appellee filed her complaint on December 22, 2004. Appellant filed his answer on
January 19, 2005, and his counterclaim on March 16, 2005. A bench trial was held on
August 10, 2005, and the trial court entered an order in favor of appellee and dismissing
appellant’s counterclaim on August 24, 2005. Appellant filed his notice of appeal on
September 19, 2005.
When a case is tried with the circuit court sitting as the trier of fact, the standard of
review on appeal is not whether there is substantial evidence to support the finding of the
court, but whether the circuit court’s findings were clearly erroneous.
1
See White v.
Appellee had an event scheduled at her home on that date, for which she
eventually had to rent other space at a cost of $1,000.00.
-2-
McGowen, __ Ark. __, __ S.W.3d __ (Jan. 12, 2006). A finding is clearly erroneous when,
although there is evidence to support it, the reviewing court, after reviewing the entire
evidence, is left with a firm conviction that a mistake has been committed.
See id.
Resolution of disputed facts and determinations of credibility are within the province of the
fact-finder. See id.
I. Breach-of-Contract Damages
Where an award of damages is alleged to be excessive, this court reviews the proof
and all reasonable inferences most favorably to the appellee and determines whether the
verdict is so great as to shock the conscience of the court or demonstrate passion or prejudice
on the part of the trier of fact. Health Facilities Mgmt. Corp. v. Hughes, __ Ark. __, __
S.W.3d __ (Feb. 9, 2006). Remittitur is appropriate when the compensatory damages
awarded are excessive and cannot be sustained by the evidence. Id. The standard of review
in such a case is that appropriate for a new trial motion, i.e., whether there is substantial
evidence to support the verdict. Id. (citing Ark. R. Civ. P. 59(a)(5) (stating a new trial may
be granted on the ground that there was error in the assessment of the amount of recovery,
whether too large or too small)). Moreover, Arkansas Rule of Civil Procedure 59(a)(4)
provides as one ground for a new trial “excessive damages appearing to have been given
under the influence of passion or prejudice.”
This court has held that when a contractor refuses to perform, damages may be
recovered against him for the difference between his bid and the cost of having the work
-3-
performed by others. MDH Builders, Inc. v. Nabholz Constr. Corp., 70 Ark. App. 284, 17
S.W.3d 97 (2000). This court has also determined that where a contractor failed to complete
work on a project, the property owners were entitled to the cost of reasonable repairs as an
appropriate measure of damages for breach of construction contract. Jocon, Inc. v. Hoover,
61 Ark. App. 10, 964 S.W.2d 213 (1998).
Appellant asserts that the judgment awarded in this case was not supported by the
evidence and is subject to remittitur. While he acknowledges that the entire $15,000.00 price
of the contract was paid to him by appellee, he contends that the work he performed was
worth far more than the $4,098.17 net amount he was left with after the circuit court’s
judgment. He testified that it would only cost him between three and four thousand dollars
to complete the remaining work on the contract and that the only other findings made with
regard to cost related to the completion of the contract were the $427.25 appellee paid to
Staley Electric and the $193.00 she paid for lights. Appellant asserts that appellee is entitled
merely to the contract rate of completing the contracted project rather than the inflated price
charged by a third party. He claims that damages in a breach-of-contract case are those that
would place the injured party in the position they would have been if the contract had not
been breached. He testified that he was willing to complete the work without additional
charge and now requests that the judgment should be reversed and remanded with
instructions for remittitur.
-4-
Not surprisingly, appellee had no interest in appellant completing the contracted
project. Appellant failed to complete the patio, did not put in steps or drains for the hot tub,
and hauled off only part of the trash and debris from the site. He poured concrete over the
location for the drains and performed faulty electrical work that had to be fixed by someone
else. Appellee provided two witnesses that testified as to what it would cost to complete the
project: (1) Mr. Rowland quoted a cost of completion of $8,891.25, based primarily on the
cost of the stone and the labor to install it over the concrete slab, and (2) Mr. McKissick
quoted a cost of $10,500.00 to finish the patio, not what it would have cost to build it from
the beginning.
The two bids presented by appellee’s witnesses were roughly close in amount, and
justifiable based upon similar cases; accordingly, we hold that the trial court’s award was not
clearly erroneous. While it is difficult to determine exactly what figures the trial judge
included in his specific award of $10,901.83, appellant failed to request further findings
pursuant to Rule 52(b), which governs situations where a party requests that a court amend
its findings or make further findings. While such a request is not mandatory in this case
because it was a bench trial,2 the failure to request further findings makes it difficult to
determine the exact basis for the award. Consequently, appellant faces a more difficult
challenge in his attempt to prove that the award was excessive. Numerous dollar amounts
2
See Cogburn v. Wolfenbarger, 85 Ark. App. 206, 148 S.W.3d 787 (2004) (stating
that, in a bench trial, the sufficiency of the evidence to support the trial court’s findings
may be raised whether or not any objection was made below).
-5-
were presented by both parties as well as their witnesses, including Mr. McKissick’s
testimony that the contract slab work done by appellant as part of the contract would be
worth approximately $4,500.00. Based upon our review of the evidence and all reasonable
inferences most favorable to the appellee, we determine that the damages award is not so
great as to shock our conscience or demonstrate passion or prejudice on the part of the trier
of fact.
II. Dismissal of Counterclaim
Appellant contends that he performed work that was separate and apart from the
contract in the amount of $8,103.75. He claims that he was never paid for his materials or
labor and filed a counterclaim against appellee for unjust enrichment. To make such a
finding in appellant’s favor, the circuit court would have had to find that appellee received
something of value from appellant, to which she was not entitled. Our supreme court has
stated that one who is free from fault cannot be held to be unjustly enriched merely because
one has chosen to exercise a legal or contractual right. See Rigsby v. Rigsby, 356 Ark. 311,
149 S.W.3d 318 (2004). Appellant points out that his testimony regarding the counterclaim
was not disputed or rebutted and asserts that it therefore must be given strong weight by the
court. At the very least, he claims that he is entitled to a set-off of $8,103.75 and requests
that the judgment be reversed and remanded for an appropriate determination of damages
and/or set-off.
-6-
Appellee admitted that, in addition to the previously discussed contract, she and
appellant entered into several valid oral agreements for additional home improvements
during the same time period. She explained several amounts that she paid to appellant,
including: $2,025.00 for work completed on her gutters; $100.00 for work on her kitchen
cabinets; $800.00 for additional fence work around the back yard.3
The invoice for
$8,103.75, dated January 24, 2005, was prepared by appellant and received by appellee after
she filed suit against appellant, and appellant admitted on cross-examination that he prepared
the invoice because she sued him. Appellee asserts that some of the items included in the
amount sought by appellant were either: (1) not agreed upon by the parties; (2) agreed upon
by the parties but not completed by appellant; (3) part of the $15,000.00 contract; (4) agreed
upon by the parties, not fixed by appellant, and eventually fixed by someone else at
appellee’s expense; (5) duplicated expenses for which he had been paid. Appellee contends
that appellant’s counterclaim was wholly unsubstantiated and that the trial court made the
correct decision in dismissing it.
Given the great deal of conflicting testimony between the parties in this case, and that
the findings of disputed facts and the determination of the credibility of witnesses are within
the province of the trial judge who has the opportunity to observe the witnesses during trial,
see White v. White, __ Ark. App. __, __ S.W.3d __ (May 24, 2006), we cannot say that the
3
Appellant stated that the $800.00 was for tree-removal, but he produced no
supporting documentary evidence to support that assertion.
-7-
trial court erred in dismissing appellant’s counterclaim. Accordingly, we affirm on this point
as well.
Affirmed.
P ITTMAN, C.J., and G LOVER, J., agree.
-8-
Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.