2012 Wyoming Statutes
TITLE 35 - PUBLIC HEALTH AND SAFETY
CHAPTER 11 - ENVIRONMENTAL QUALITY
35-11-313. Carbon sequestration; permit requirements.


WY Stat § 35-11-313 (through 2012) What's This?

(a) The geologic sequestration of carbon dioxide is prohibited unless authorized by a permit issued by the department.

(b) The injection of carbon dioxide for purposes of a project for enhanced recovery of oil or other minerals approved by the Wyoming oil and gas conservation commission shall not be subject to the provisions of this chapter.

(c) If an oil and gas operator converts to geologic sequestration upon the cessation of oil and gas recovery operations, then regulation of the geologic sequestration facility and the geologic sequestration site shall be transferred to the department. If the oil and gas operator does not convert to geologic sequestration, the wells shall be plugged and abandoned according to the rules of the Wyoming oil and gas conservation commission.

(d) Temporary time limited permits for pilot scale testing of technologies for geologic sequestration shall be issued by the department based upon current rules and regulations.

(e) Permit requirements for geologic sequestration of carbon dioxide shall be as defined by department rules.

(f) The administrator of the water quality division of the department of environmental quality, after receiving public comment and after consultation with the state geologist, the Wyoming oil and gas conservation commission and the advisory board created under this act, shall recommend to the director rules, regulations and standards for:

(i) The creation of subclasses of wells within the existing Underground Injection Control (UIC) program administered by the United States Environmental Protection Agency under Part C of the Safe Drinking Water Act to protect human health, safety and the environment and allow for the permitting of the geologic sequestration of carbon dioxide;

(ii) Requirements for the content of applications for geologic sequestration permits. Such applications shall include:

(A) A description of the general geology of the area to be affected by the injection of carbon dioxide including geochemistry, structure and faulting, fracturing and seals, stratigraphy and lithology including petrophysical attributes;

(B) A characterization of the injection zone and aquifers above and below the injection zone which may be affected including applicable pressure and fluid chemistry data to describe the projected effects of injection activities;

(C) The identification of all other drill holes and operating wells that exist within and adjacent to the proposed sequestration site;

(D) An assessment of the impact to fluid resources, on subsurface structures and the surface of lands that may reasonably be expected to be impacted and the measures required to mitigate such impacts;

(E) Plans and procedures for environmental surveillance and excursion detection, prevention and control programs. For purposes of this section, "excursion" shall mean the detection of migrating carbon dioxide at or beyond the boundary of the geologic sequestration site;

(F) A site and facilities description, including a description of the proposed geologic sequestration facilities and documentation sufficient to demonstrate that the applicant has all legal rights, including but not limited to the right to surface use, necessary to sequester carbon dioxide and associated constituents into the proposed geologic sequestration site. The department may issue a draft permit contingent on obtaining a unitization order pursuant to W.S. 35-11-314 through 35-11-317;

(G) Proof that the proposed injection wells are designed at a minimum to the construction standards set forth by the department and the Wyoming oil and gas conservation commission;

(H) A plan for periodic mechanical integrity testing of all wells;

(J) A monitoring plan to assess the migration of the injected carbon dioxide and to insure the retention of the carbon dioxide in the geologic sequestration site;

(K) Proof of bonding or financial assurance to ensure that geologic sequestration sites and facilities will be constructed, operated and closed in accordance with the purposes and provisions of this act and the rules and regulations promulgated pursuant to this act;

(M) A detailed plan for post-closure monitoring, verification, maintenance and mitigation;

(N) Proof of notice to surface owners, mineral claimants, mineral owners, lessees and other owners of record of subsurface interests as to the contents of such notice. Notice requirements shall at a minimum require:

(I) The publishing of notice of the application in a newspaper of general circulation in each county of the proposed operation at weekly intervals for four (4) consecutive weeks;

(II) A copy of the notice shall also be mailed to all surface owners, mineral claimants, mineral owners, lessees and other owners of record of subsurface interests which are located within one (1) mile of the proposed boundary of the geologic sequestration site.

(O) A certificate issued by an insurance company authorized to do business in the United States certifying that the applicant has a public liability insurance policy in force for the geologic sequestration operations for which the permit is sought, or evidence that the applicant has satisfied other state or federal self insurance requirements. The policy shall provide for personal injury and property damage protection in an amount and for a duration as established by regulations.

(iii) Requirements for the operator to provide immediate verbal notice to the department of any excursion after the excursion is discovered, followed by written notice to all surface owners, mineral claimants, mineral owners, lessees and other owners of record of subsurface interests within thirty (30) days of when the excursion is discovered;

(iv) Procedures for the termination or modification of any applicable Underground Injection Control (UIC) permit issued under Part C of the Safe Drinking Water Act if an excursion cannot be controlled or mitigated;

(v) Such other conditions and requirements as necessary to carry out this section;

(vi) Requirements for bonding and financial assurance for geologic sequestration facilities and geologic sequestration sites including:

(A) Procedures to establish the type and amount of the bond or financial assurance instrument to assure that the operator faithfully performs all requirements of this chapter, complies with all rules and regulations and provides adequate financial resources to pay for mitigation or reclamation costs that the state may incur as a result of any default by the permit holder, provided that, any insurance instruments submitted for financial assurance purposes shall include the state of Wyoming as an additional insured, which inclusion shall not be deemed a waiver of sovereign immunity;

(B) Annual or other periodic reporting by the permittee during geologic sequestration and reclamation activities to allow the administrator to confirm or adjust the amount or type of the bond or other financial assurance requirements consistent with the site, facility and operation specific risks and conditions;

(C) Procedures to require proof of compliance from any permittee ordered by the administrator to adjust a bond or other financial assurance, including procedures for permit suspension or termination procedures following notice and an opportunity for a hearing if adequate bonding or financial assurance cannot be demonstrated;

(D) Procedures for replacement of a bond or financial assurance instrument if notice of cancellation is provided or notice that the license to do business in Wyoming of the surety or insurance company issuing a bond or other financial assurance pursuant to this chapter is suspended or revoked;

(E) Procedures for the director to forfeit the bond or to make a claim against any insurance instrument providing financial assurance, including the right of the attorney general to bring suit to recover costs if the bond or financial assurance is inadequate, to pay for closure, mitigation, reclamation, measurement, monitoring, verification and pollution control, where recovery is deemed possible;

(F) Procedures, including public notice and a public hearing if requested, for the release of bonds or the termination of insurance instruments not less than ten (10) years after the date when all wells excluding monitoring wells have been appropriately plugged and abandoned, all subsurface operations and activities have ceased and all surface equipment and improvements have been removed or appropriately abandoned, or so long thereafter as necessary to obtain a completion and release certificate from the administrator certifying that plume stabilization as defined by rule has been achieved without the use of control equipment based on a minimum of three (3) consecutive years of monitoring data, and that the operator has completed site reclamation and all required monitoring and remediation sufficient to show that the carbon dioxide injected into the geologic sequestration site will not harm or present a risk to human health, safety or the environment, including drinking water supplies, consistent with the purposes of this chapter and the rules and regulations adopted by the council;

(G) Requirements for the operator to record an affidavit in the office of the county clerk of the county or counties in which a geologic sequestration site is located, which affidavit shall be reasonably calculated to alert a person researching the title of a particular tract that such tract is underlain by a site permitted for geologic sequestration.

(vii) Requirements for fees to be paid by all permittees of geologic sequestration sites and facilities, which may include a per ton injection fee or a closure fee, during the period of injection of carbon dioxide and associated constituents into subsurface geologic formations in Wyoming, which fees shall be deposited in the geologic sequestration special revenue account created by W.S. 35-11-318 for use as provided therein.

(g) Repealed By Laws 2010, Ch. 52, 3.

(h) At the time a permit application is filed, an applicant shall pay a fee to be determined by the director based upon the estimated costs of reviewing, evaluating, processing, serving notice of an application and holding any hearings. The fee shall be credited to a separate account and shall be used by the division as required to complete the tasks necessary to process, publish and reach a decision on the permit application. Unused fees shall be returned to the applicant.

(j) The director shall recommend to the council any changes that may be required to provide consistency and equivalency between the rules or regulations promulgated under this section and any promulgated for the regulation of carbon dioxide sequestration by the United States environmental protection agency.

(k) The Wyoming oil and gas conservation commission shall have jurisdiction over any subsequent extraction of sequestered carbon dioxide that is intended for commercial or industrial purposes.

(m) Nothing in this section shall be construed to create any liability by the state for failure to comply with this section.

Disclaimer: These codes may not be the most recent version. Wyoming may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.