2011 Wyoming Statutes
TITLE 16 - CITY, COUNTY, STATE AND LOCAL POWERS
CHAPTER 6 - PUBLIC PROPERTY
16-6-708. Responsibilities under alternative delivery contracts.
(a) Any construction manager agent, construction manager at risk or design-builder contract awarded shall comply with any reporting and administrative requirements as required by the public entity of the recipient of a design, bid and build contract, including retainage, payment and performance bonding and default of contract.
(b) All bids received under this section including subcontractor bids, shall be opened in public following reasonable public notice.
Disclaimer: These codes may not be the most recent version. Wyoming may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.