RCW 64.34.452

Warranties of quality—Breach—Actions for construction defect claims.

(1) A judicial proceeding for breach of any obligations arising under RCW 64.34.443, 64.34.445, and 64.34.450 must be commenced within four years after the cause of action accrues: PROVIDED, That the period for commencing an action for a breach accruing pursuant to subsection (2)(b) of this section shall not expire prior to one year after termination of the period of declarant control, if any, under *RCW 64.34.308(4). Such periods may not be reduced by either oral or written agreement, or through the use of contractual claims or notice procedures that require the filing or service of any claim or notice prior to the expiration of the period specified in this section.

(2) Subject to subsection (3) of this section, a cause of action or [for] breach of warranty of quality, regardless of the purchaser's lack of knowledge of the breach, accrues:

(a) As to a unit, the date the purchaser to whom the warranty is first made enters into possession if a possessory interest was conveyed or the date of acceptance of the instrument of conveyance if a nonpossessory interest was conveyed; and

(b) As to each common element, at the latest of (i) the date the first unit in the condominium was conveyed to a bona fide purchaser, (ii) the date the common element was completed, or (iii) the date the common element was added to the condominium.

(3) If a warranty of quality explicitly extends to future performance or duration of any improvement or component of the condominium, the cause of action accrues at the time the breach is discovered or at the end of the period for which the warranty explicitly extends, whichever is earlier.

(4) If a written notice of claim is served under RCW 64.50.020 within the time prescribed for the filing of an action under this chapter, the statutes of limitation in this chapter and any applicable statutes of repose for construction-related claims are tolled until sixty days after the period of time during which the filing of an action is barred under RCW 64.50.020.

(5) Nothing in this section affects the time for filing a claim under chapter 64.35 RCW.

[ 2004 c 201 § 7; 2002 c 323 § 11; 1990 c 166 § 14.]

NOTES:

*Reviser's note: RCW 64.34.308 was amended by 2011 c 189 § 2, changing subsection (4) to subsection (5), effective January 1, 2012.

Effective date—1990 c 166: See note following RCW 64.34.020.

Disclaimer: These codes may not be the most recent version. Washington may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.