There Is a Newer Version
of
this Section
2022 Revised Code of Washington
Title 4 - Civil Procedure
Chapter 4.24 - Special Rights of Action and Special Immunities.
4.24.370 - Construction contract provision waiving, releasing, etc., rights of contractor, etc., to damages or adjustment for unreasonable delay caused by contractee, etc.—"Construction contract" defined.
Universal Citation:
WA Rev Code § 4.24.370 (2022)
Learn more
This media-neutral citation is based
on the American Association of Law Libraries Universal Citation Guide and is not
necessarily the official citation.
RCW 4.24.370
Construction contract provision waiving, releasing, etc., rights of contractor, etc., to damages or adjustment for unreasonable delay caused by contractee, etc.—"Construction contract" defined.
"Construction contract" for purposes of RCW 4.24.360 means any contract or agreement for the construction, alteration, repair, addition to, subtraction from, improvement to, or maintenance of, any building, highway, road, railroad, excavation, or other structure, project, development, or improvement attached to real estate, including moving and demolition in connection therewith.
[ 1979 ex.s. c 264 § 2.]
Disclaimer: These codes may not be the most recent version. Washington may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.