2012 Revised Code of Washington
Title 43 - STATE GOVERNMENT — EXECUTIVE
43.21A Department of ecology.
43.21A.068 Federal power act licensees -- Exemption from state requirements.


WA Rev Code § 43.21A.068 (2012) What's This?

RCW 43.21A.068 Federal power act licensees — Exemption from state requirements.

(1) With respect to the safety of any dam, canal, ditch, hydraulic power plant, reservoir, project, or other work, system, or plant that requires a license under the federal power act, no licensee shall be required to:

     (a) Submit proposals, plans, specifications, or other documents for approval by the department;

     (b) Seek a permit, license, or other form, permission, or authorization from the department;

     (c) Submit to inspection by the department; or

     (d) Change the design, construction, modification, maintenance, or operation of such facilities at the demand of the department.

     (2) For the purposes of this section, "licensee" means an owner or operator, or any employee thereof, of a dam, canal, ditch, hydraulic power plant, reservoir, project, or other work, system, or plant that requires a license under the federal power act.

[1995 c 8 § 2.]

Notes:

     Findings -- 1995 c 8: See note following RCW 43.21A.064.


Disclaimer: These codes may not be the most recent version. Washington may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.