2018 Vermont Statutes
Title 10 - Conservation and Development
Chapter 170 - Department Of Environmental Conservation; Standard Procedures
§ 7703 Rules; additional notice or procedures

Universal Citation: 10 V.S.A. § 7703

§ 7703. Rules; additional notice or procedures

(a) Rules.

(1) Implementing rules. The Secretary may adopt rules to implement this chapter.

(2) Complex projects; preapplication process. The Secretary shall adopt rules to determine when a project requiring a permit is large and complex. These rules shall provide that an applicant proposing such a project, prior to filing an application for a permit, shall initiate a project scoping process pursuant to 3 V.S.A. § 2828 or shall hold an informational meeting that is open to the public. The rules shall ensure that:

(A) Written notice of an informational meeting under this section is sent to the owner of the land where the project is located if the applicant is not the owner; the municipality in which the project is located; the municipal and regional planning commissions for any municipality in which the project is located; if the project site is located on a boundary, any Vermont municipality adjacent to that boundary and the municipal and regional planning commissions for that municipality; and each adjoining property owner. At the time this written notice is sent, the Secretary also shall post the notice to the environmental notice bulletin.

(B) The notice to adjoining property owners informs them of how they can continue to receive notices and information through the environmental notice bulletin concerning the project as it is reviewed by the Secretary.

(C) The applicant furnishes by affidavit to the Secretary the names of those furnished notice and certifies compliance with the notice requirements of this subsection.

(D) The applicant and the Secretary or designee shall attend the meeting. The applicant shall respond to questions from other attendees.

(b) Additional notice.

(1) The Secretary may require, by rule or in an individual case, measures in addition to those directed by this chapter using any method reasonably calculated to give direct notice to persons potentially affected by a decision on the application.

(2) In an individual case, the Secretary may determine to apply the procedures of section 7713 (Type 2) of this chapter to the issuance of a permit otherwise subject to the procedures of section 7715 (Type 4) or section 7716 (Type 5) of this chapter.

(c) Extension of deadlines. A person may request that the Secretary extend any deadline for comment or requesting a public informational meeting established by this chapter. The person shall submit the request before the deadline and include a brief explanation of why the extension is justified. If the request is granted, the Secretary shall provide notice of the new deadline through the environmental notice bulletin. (Added 2015, No. 150 (Adj. Sess.), § 1, eff. Jan. 1, 2018.)

Disclaimer: These codes may not be the most recent version. Vermont may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.