Section 205 - Approvals void after one year if construction delayed -- Exceptions.

UT Code § 73-5a-205 (2016) What's This?
73-5a-205. Approvals void after one year if construction delayed -- Exceptions.
  • (1) Any approval granted under Section 73-5a-203 is void one year after the date of approval if construction has not started.
  • (2) The state engineer may extend the approval in one year increments:
    • (a) upon a showing of reasonable cause for delay; and
    • (b) provided state-of-the-art design criteria has not changed in the intervening period.


Enacted by Chapter 319, 1990 General Session

Disclaimer: These codes may not be the most recent version. Utah may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.