38-1a-706. Apportionment of costs -- Costs and attorney fees to subcontractor.
(1) Except as provided in Section 38-11-107, the court shall apportion costs between the owner and original contractor according to the right of the case.
(2) The court shall award a subcontractor with a valid preconstruction or construction lien:
(a) all of the subcontractor's costs, including the costs of preparing and recording the notice of preconstruction or construction lien; and
(b) the subcontractor's reasonable attorney fees incurred in preparing and recording the notice of preconstruction or construction lien.
Enacted by Chapter 278, 2012 General Session
Disclaimer: These codes may not be the most recent version. Utah may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.