Article 1a - Preconstruction and Construction Liens
Section 405 - Preconstruction liens on equal footing.


UT Code § 38-1a-405 (2012) What's This?

38-1a-405. Preconstruction liens on equal footing.

(1) Each preconstruction lien on a project property is on equal footing with every other preconstruction lien on the project property, regardless of:

(a) when the claimant submitted the claimant's notice of preconstruction service for recording;

(b) when the claimant submitted the claimant's notice of preconstruction lien for recording; or

(c) when the preconstruction service related to the lien occurs.

(2) Subsection (1) does not affect the priority of a construction lender's mortgage or trust deed, as established under this chapter.


Enacted by Chapter 464, 2013 General Session

Disclaimer: These codes may not be the most recent version. Utah may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.