54-18-304. Review of land use application.
(1) (a) A land use authority shall grant or deny a public utility's land use permit within 60 days after filing in accordance with the provisions of Title 10, Chapter 9a, Municipal Land Use, Development, and Management Act, and Title 17, Chapter 27a, County Land Use, Development, and Management Act.
(b) The Utility Facility Review Board may review a land use authority's land use permit decision in accordance with Title 54, Chapter 14, Part 3, Utility Facility Review Board.
(2) Notwithstanding Subsection (1), if a public utility does not satisfy the notice of intent requirements in accordance with Section 54-18-301 and public workshop requirements in accordance with Section 54-18-302, a land use authority may withhold a decision on a public utility's land use permit until the public utility satisfies the notification and public workshop requirements.

Disclaimer: These codes may not be the most recent version. Utah may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.