There Is a Newer Version of the Utah Code
2011 Utah Code
Title 54 Public Utilities
Chapter 15 Net Metering of Electricity
Section 105 No additional fee or charge without governing authority approval -- Exception.
54-15-105. No additional fee or charge without governing authority approval -- Exception.(1) An electrical corporation administering a net metering program may not charge a customer participating in the program an additional standby, capacity, interconnection, or other fee or charge unless the governing authority, after appropriate notice and opportunity for public comment:
(a) determines that:
(i) the electrical corporation will incur direct costs from the interconnection or from administering the net metering program that exceed benefits, as determined by the governing authority, resulting from the program; and
(ii) public policy is best served by imposing a reasonable fee or charge on the customer participating in the net metering program rather than by allocating the fee or charge among the electrical corporation's entire customer base; and
(b) after making its determination under Subsection (1)(a), authorizes the additional reasonable fee or charge.
(2) If a cost of a net metering program is allocated among the electrical corporation's entire customer base, Subsection (1) may not be construed to prohibit an electrical corporation from charging a customer participating in the net metering program for that cost to the same extent that the electrical corporation charges a customer not participating in the program for that cost.
Disclaimer: These codes may not be the most recent version. Utah may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.