Utah Title 54 — Public Utilities :: 54-15-108 — Damages And Fines For Connecting A Customer Generation System To More Than One Customer.

54-15-108. Damages and fines for connecting a customer generation system to more than one customer.
If an independent energy producer defined in Subsection 54-2-1(13) that is supplying energy to a customer under Subsection 54-2-1(16)(d)(iv) violates the limitations set forth in Subsection 54-2-1(16)(d)(iv)(B), the commission may:
(1) award damages to an electrical corporation for actual and consequential damages to the electrical corporation; and
(2) assess a fine against the independent energy producer or person responsible for the violation.

Enacted by Chapter 302, 2010 General Session