63H-2-302 - Approval of qualifying transmission project.

63H-2-302. Approval of qualifying transmission project.
(1) To approve a qualifying transmission project, the board shall determine that the transmission project:
(a) contributes to the economy of the state and the one or more communities where the transmission project is located;
(b) is strategically situated to maximize connections to a renewable energy source project located in the state that is:
(i) existing;
(ii) under construction;
(iii) planned; or
(iv) foreseeable;
(c) is supported by a business case for providing the revenue necessary to:
(i) service an authority bond issued to finance the transmission project; and
(ii) finance the construction and operation of a transmission project;
(d) is supported by a transmission project plan related to:
(i) engineering;
(ii) environmental issues;
(iii) energy production;
(iv) load capacity; and
(v) any other issue related to the building and operation of a transmission line; and
(e) complies with the regulations of the following regarding the building of a transmission line or connection:
(i) the Federal Energy Regulatory Commission;
(ii) the North American Electric Reliability Council; and
(iii) the Public Service Commission of Utah.
(2) This chapter may not be used to compel interconnection to or use of a transmission or interconnection line or facility that belongs to another person.

Enacted by Chapter 378, 2009 General Session

Disclaimer: These codes may not be the most recent version. Utah may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.