2010 Utah Code
Title 63H - Independent State Entities
Chapter 02 - Utah Generated Renewable Energy Electricity Network Authority Act
63H-2-301 - Prioritization of transmission projects.

63H-2-301. Prioritization of transmission projects.
(1) The board shall review the location and availability of renewable energy sources serving electric loads in the state.
(2) The board shall:
(a) determine if there is adequate transmission infrastructure and capacity to bring renewable energy sources to market;
(b) prioritize transmission projects on the basis of:
(i) location;
(ii) supporting potential renewable energy source development;
(iii) feasibility of development; and
(iv) economic development factors; and
(c) provide available funding to develop energy resource plans to provide for connecting to transmission lines a renewable energy source, including development of an integrated resource plan.

Enacted by Chapter 378, 2009 General Session

Disclaimer: These codes may not be the most recent version. Utah may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.