2006 Utah Code - 73-26-302 — Construction contingent upon sale or lease of water -- Preconstruction may proceed.

     73-26-302.   Construction contingent upon sale or lease of water -- Preconstruction may proceed if funded.
     (1) Except as provided in Subsection (3), the division may not expend monies for construction costs on any phase of a project until:
     (a) contracts have been made for the sale or lease of at least 70% of the water developed by that phase; and
     (b) all permits required by the environmental impact statement have been obtained.
     (2) Construction of the project and implementation of the environmental mitigation plan shall proceed concurrently.
     (3) The division may make expenditures for preconstruction costs if monies are expressly appropriated or earmarked by statute for that purpose by the Legislature.

Amended by Chapter 84, 2006 General Session

Disclaimer: These codes may not be the most recent version. Utah may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.