2006 Utah Code - 54-8-24 — Payment to utilities -- Allowable costs.

     54-8-24.   Payment to utilities -- Allowable costs.
     In determining the conversion costs included in the costs and feasibility report required by Section 54-8-7, the public utility corporations shall be entitled to amounts sufficient to repay them for the following, as computed and reflected by the uniform system of accounts approved by the Public Service Commission, Federal Communications Commission or Federal Power Commission:
     (1) The original costs less depreciation taken of the existing overhead electric and communication facilities to be removed.
     (2) The estimated costs of removing such overhead electric and communication facilities, less the salvage value of the facilities removed.
     (3) If the estimated cost of constructing underground facilities exceeds the original cost of existing overhead electric and communication facilities, then the cost difference between the two.
     (4) The cost of obtaining new easements when technical considerations make it reasonably necessary to utilize easements for the underground facilities different from those used for aboveground facilities, or where the pre-existing easements are insufficient for the underground facilities.
     However, in the event the conversion costs are included in tariffs, rules or regulations filed with or promulgated by the Public Service Commission such conversion costs shall be the costs included in the costs and feasibility report.

Enacted by Chapter 157, 1969 General Session

Disclaimer: These codes may not be the most recent version. Utah may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.