2006 Utah Code - 38-1-6 — Priority over claims of creditors of original contractor or subcontractor.

     38-1-6.   Priority over claims of creditors of original contractor or subcontractor.
     No attachment, garnishment or levy under an execution upon any money due to an original contractor from the owner of any property subject to lien under this chapter shall be valid as against any lien of a subcontractor or materialman, and no such attachment, garnishment or levy upon any money due to a subcontractor or materialman from the contractor shall be valid as against any lien of a laborer employed by the day or piece.

No Change Since 1953

Disclaimer: These codes may not be the most recent version. Utah may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.