Sec. 412 - Prerequisites to initiation of project or division of project
Download PDF
43 U.S.C. § 412 (2019) |
§412. Prerequisites to initiation of project or division of project |
After December 5, 1924, no new project or new division of a project shall be approved for construction or estimates submitted therefor by the Secretary until information in detail shall be secured by him concerning the water supply, the engineering features, the cost of construction, land prices, and the probable cost of development, and he shall have made a finding in writing that it is feasible, that it is adaptable for actual settlement and farm homes, and that it will probably return the cost thereof to the United States. |
(Dec. 5, 1924, ch. 4, §4, subsec. B, 43 Stat. 702.) |
DEFINITIONS
The definitions in section 371 of this title apply to this section. |
United States Code, 2018 Edition, Supplement 1, Title 43 - PUBLIC LANDS |
Bills and Statutes |
United States Code |
Y 1.2/5: |
Title 43 - PUBLIC LANDS CHAPTER 12 - RECLAMATION AND IRRIGATION OF LANDS BY FEDERAL GOVERNMENT SUBCHAPTER III - INSTITUTION AND CONSTRUCTION OF PROJECTS Sec. 412 - Prerequisites to initiation of project or division of project |
section 412 |
2019 |
January 24, 2020 |
No |
standard |
43 Stat. 702 |
Disclaimer: These codes may not be the most recent version. United States may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google
Privacy Policy and
Terms of Service apply.