Section Text (a) Duty of Secretary of Energy

The Secretary of Energy, in consultation with the Administrator of each Federal Power Marketing Administration, shall assess each effect of, and risk resulting from, global climate change with respect to water supplies that are required for the generation of hydroelectric power at each Federal water project that is applicable to a Federal Power Marketing Administration.

(b) Access to appropriate data (1) In general

In carrying out each assessment under subsection (a), the Secretary of Energy shall consult with the United States Geological Survey, the National Oceanic and Atmospheric Administration, the program, and each appropriate State water resource agency, to ensure that the Secretary of Energy has access to the best available scientific information with respect to presently observed impacts and projected future impacts of global climate change on water supplies that are used to produce hydroelectric power.

(2) Access to data for certain assessments

In carrying out each assessment under subsection (a), with respect to the Bonneville Power Administration and the Western Area Power Administration, the Secretary of Energy shall consult with the Commissioner to access data and other information that—

(A) is collected by the Commissioner; and

(B) the Secretary of Energy determines to be necessary for the conduct of the assessment.

(c) Report

Not later than 2 years after March 30, 2009, and every 5 years thereafter, the Secretary of Energy shall submit to the appropriate committees of Congress a report that describes—

(1) each effect of, and risk resulting from, global climate change with respect to—

(A) water supplies used for hydroelectric power generation; and

(B) power supplies marketed by each Federal Power Marketing Administration, pursuant to—

(i) long-term power contracts;

(ii) contingent capacity contracts; and

(iii) short-term sales; and


(2) each recommendation of the Administrator of each Federal Power Marketing Administration relating to any change in any operation or contracting practice of each Federal Power Marketing Administration to address each effect and risk described in paragraph (1), including the use of purchased power to meet long-term commitments of each Federal Power Marketing Administration.

(d) Authority

The Secretary of Energy may enter into contracts, grants, or other agreements with appropriate entities to carry out this section.

(e) Costs (1) Nonreimbursable

Any costs incurred by the Secretary of Energy in carrying out this section shall be nonreimbursable.

(2) PMA costs

Each Federal Power Marketing Administration shall incur costs in carrying out this section only to the extent that appropriated funds are provided by the Secretary of Energy for that purpose.

(f) Authorization of appropriations

There are authorized to be appropriated such sums as are necessary to carry out this section for each of fiscal years 2009 through 2023, to remain available until expended.

Source Credit

(Pub. L. 111–11, title IX, §9505, Mar. 30, 2009, 123 Stat. 1336.)

Publication Title United States Code, 2018 Edition, Title 42 - THE PUBLIC HEALTH AND WELFARE
Category Bills and Statutes
Collection United States Code
SuDoc Class Number Y 1.2/5:
Contained Within Title 42 - THE PUBLIC HEALTH AND WELFARE
CHAPTER 109B - SECURE WATER
Sec. 10365 - Hydroelectric power assessment
Contains section 10365
Date 2018
Laws In Effect As Of Date January 14, 2019
Positive Law No
Disposition standard
Statutes at Large References 123 Stat. 1336
Public Law References Public Law 111-11
Disclaimer: These codes may not be the most recent version. United States may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.