2015 US Code
Title 33 - Navigation and Navigable Waters (Sections 1 - 4009)
Chapter 36 - Water Resources Development (Sections 2201 - 2352)
Subchapter V - General Provisions (Sections 2280 - 2352)
Sec. 2282c - Vertical integration and acceleration of studies

View Metadata
Metadata
Publication TitleUnited States Code, 2012 Edition, Supplement 3, Title 33 - NAVIGATION AND NAVIGABLE WATERS
CategoryBills and Statutes
CollectionUnited States Code
SuDoc Class NumberY 1.2/5:
Contained WithinTitle 33 - NAVIGATION AND NAVIGABLE WATERS
CHAPTER 36 - WATER RESOURCES DEVELOPMENT
SUBCHAPTER V - GENERAL PROVISIONS
Sec. 2282c - Vertical integration and acceleration of studies
Containssection 2282c
Date2015
Laws In Effect As Of DateJanuary 3, 2016
Positive LawNo
Dispositionstandard
Source CreditPub. L. 113-121, title I, §1001, June 10, 2014, 128 Stat. 1196.
Statutes at Large Reference128 Stat. 1196
Public and Private LawPublic Law 113-121

Download PDF


33 U.S.C. § 2282c (2015)
§2282c. Vertical integration and acceleration of studies(a) In general

To the extent practicable, a feasibility study initiated by the Secretary, after June 10, 2014, under section 2282(a) of this title shall—

(1) result in the completion of a final feasibility report not later than 3 years after the date of initiation;

(2) have a maximum Federal cost of $3,000,000; and

(3) ensure that personnel from the district, division, and headquarters levels of the Corps of Engineers concurrently conduct the review required under that section.

(b) Extension

If the Secretary determines that a feasibility study described in subsection (a) will not be conducted in accordance with subsection (a), the Secretary, not later than 30 days after the date of making the determination, shall—

(1) prepare an updated feasibility study schedule and cost estimate;

(2) notify the non-Federal feasibility cost-sharing partner that the feasibility study has been delayed; and

(3) provide written notice to the Committee on Environment and Public Works of the Senate and the Committee on Transportation and Infrastructure of the House of Representatives as to the reasons the requirements of subsection (a) are not attainable.

(c) Termination of authorization

A feasibility study for which the Secretary has issued a determination under subsection (b) is not authorized after the last day of the 1-year period beginning on the date of the determination if the Secretary has not completed the study on or before such last day.

(d) Exception(1) In general

Notwithstanding the requirements of subsection (c), the Secretary may extend the timeline of a study by a period not to exceed 3 years, if the Secretary determines that the feasibility study is too complex to comply with the requirements of subsections (a) and (c).

(2) Factors

In making a determination that a study is too complex to comply with the requirements of subsections (a) and (c), the Secretary shall consider—

(A) the type, size, location, scope, and overall cost of the project;

(B) whether the project will use any innovative design or construction techniques;

(C) whether the project will require significant action by other Federal, State, or local agencies;

(D) whether there is significant public dispute as to the nature or effects of the project; and

(E) whether there is significant public dispute as to the economic or environmental costs or benefits of the project.

(3) Notification

Each time the Secretary makes a determination under this subsection, the Secretary shall provide written notice to the Committee on Environment and Public Works of the Senate and the Committee on Transportation and Infrastructure of the House of Representatives as to the results of that determination, including an identification of the specific 1 or more factors used in making the determination that the project is complex.

(4) Limitation

The Secretary shall not extend the timeline for a feasibility study for a period of more than 7 years, and any feasibility study that is not completed before that date shall no longer be authorized.

(e) Reviews

Not later than 90 days after the date of the initiation of a study described in subsection (a) for a project, the Secretary shall—

(1) take all steps necessary to initiate the process for completing federally mandated reviews that the Secretary is required to complete as part of the study, including the environmental review process under section 1005;

(2) convene a meeting of all Federal, tribal, and State agencies identified under section 2348(e) of this title that may be required by law to conduct or issue a review, analysis, or opinion on or to make a determination concerning a permit or license for the study; and

(3) take all steps necessary to provide information that will enable required reviews and analyses related to the project to be conducted by other agencies in a thorough and timely manner.

(f) Interim report

Not later than 18 months after June 10, 2014, the Secretary shall submit to the Committee on Environment and Public Works of the Senate and the Committee on Transportation and Infrastructure of the House of Representatives and make publicly available a report that describes—

(1) the status of the implementation of the planning process under this section, including the number of participating projects;

(2) a review of project delivery schedules, including a description of any delays on those studies participating in the planning process under this section; and

(3) any recommendations for additional authority necessary to support efforts to expedite the feasibility study process for water resource projects.

(g) Final report

Not later than 4 years after June 10, 2014, the Secretary shall submit to the Committee on Environment and Public Works of the Senate and the Committee on Transportation and Infrastructure of the House of Representatives and make publicly available a report that describes—

(1) the status of the implementation of this section, including a description of each feasibility study subject to the requirements of this section;

(2) the amount of time taken to complete each feasibility study; and

(3) any recommendations for additional authority necessary to support efforts to expedite the feasibility study process, including an analysis of whether the limitation established by subsection (a)(2) needs to be adjusted to address the impacts of inflation.

(Pub. L. 113–121, title I, §1001, June 10, 2014, 128 Stat. 1196.)

REFERENCES IN TEXT

Section 1005, referred to in subsec. (e)(1), is section 1005 of Pub. L. 113–121, which enacted section 2349 of this title and amended generally section 2348 of this title.

CODIFICATION

Section was enacted as part of the Water Resources Reform and Development Act of 2014, and not as part of the Water Resources Development Act of 1986 which comprises this chapter.

"SECRETARY" DEFINED

Secretary means the Secretary of the Army, see section 2 of Pub. L. 113–121, set out as a note under section 2201 of this title.

Disclaimer: These codes may not be the most recent version. The United States Government Printing Office may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the US site. Please check official sources.