2015 US Code
Title 14 - Coast Guard (Sections 1 - 894)
Part I - Regular Coast Guard (Sections 1 - 693)
Chapter 15 - Acquisitions (Sections 561 - 581)
Subchapter II - Improved Acquisition Process and Procedures (Sections 571 - 577)
Sec. 577 - Advance procurement funding

View Metadata
Metadata
Publication TitleUnited States Code, 2012 Edition, Supplement 3, Title 14 - COAST GUARD
CategoryBills and Statutes
CollectionUnited States Code
SuDoc Class NumberY 1.2/5:
Contained WithinTitle 14 - COAST GUARD
PART I - REGULAR COAST GUARD
CHAPTER 15 - ACQUISITIONS
SUBCHAPTER II - IMPROVED ACQUISITION PROCESS AND PROCEDURES
Sec. 577 - Advance procurement funding
Containssection 577
Date2015
Laws In Effect As Of DateJanuary 3, 2016
Positive LawYes
Dispositionstandard
Source CreditAdded Pub. L. 112-213, title II, §211(a), Dec. 20, 2012, 126 Stat. 1551.
Statutes at Large References126 Stat. 1551
127 Stat. 377
128 Stat. 3038
Public and Private LawsPublic Law 112-213, Public Law 113-6, Public Law 113-281

Download PDF


14 U.S.C. § 577 (2015)
§577. Advance procurement funding

(a) In General.—With respect to any Coast Guard vessel for which amounts are appropriated and any amounts otherwise made available for vessels for the Coast Guard in any fiscal year, the Commandant of the Coast Guard may enter into a contract or place an order, in advance of a contract or order for construction of a vessel, for—

(1) materials, parts, components, and labor for the vessel;

(2) the advance construction of parts or components for the vessel;

(3) protection and storage of materials, parts, or components for the vessel; and

(4) production planning, design, and other related support services that reduce the overall procurement lead time of the vessel.


(b) Use of Materials, Parts, and Components Manufactured in the United States.—In entering into contracts and placing orders under subsection (a), the Commandant may give priority to persons that manufacture materials, parts, and components in the United States.

(Added Pub. L. 112–213, title II, §211(a), Dec. 20, 2012, 126 Stat. 1551.)

MULTIYEAR PROCUREMENT AUTHORITY FOR OFFSHORE PATROL CUTTERS

Pub. L. 113–281, title II, §223, Dec. 18, 2014, 128 Stat. 3038, provided that: "In fiscal year 2015 and each fiscal year thereafter, the Secretary of the department in which the Coast Guard is operating may enter into, in accordance with section 2306b of title 10, United States Code, multiyear contracts for the procurement of Offshore Patrol Cutters and associated equipment."

LONG LEAD TIME MATERIALS AND VESSEL PRODUCTION; IMMEDIATE AVAILABILITY OF FUNDING

Pub. L. 113–6, div. D, title V, §557, Mar. 26, 2013, 127 Stat. 377, provided that:

"(a) Notwithstanding Office of Management and Budget Circular A–11, funds made available in fiscal year 2013, or any fiscal year thereafter, under Department of Homeland Security, Coast Guard, 'Acquisition, Construction, and Improvements' for—

"(1) long lead time materials, components, and designs of a vessel of the Coast Guard shall be immediately available and allotted to make a contract award notwithstanding the availability of funds for production, outfitting, post-delivery activities, and spare or repair parts; and

"(2) production of a vessel of the Coast Guard shall be immediately available and allotted to make a contract award notwithstanding the availability of funds for outfitting, post-delivery activities, and spare or repair parts.

"(b) The Secretary of Homeland Security shall develop fiscal policy that prescribes Coast Guard budgetary policies, procedures and technical direction necessary to comply with subsection (a) of this section and consistent with the Department of Defense Financial Management Regulation (Volume 2A, Chapter 1 C. Procedures for Full Funding) to include the costs associated with outfitting and post-delivery activities; spare and repair parts; and long lead time materials. The requirement set forth in this section shall not preclude the immediate availability or allotment of funds for fiscal year 2013, pursuant to subsection (a).

"(c) In this section—

"(1) the term 'long lead time items' means components, parts, material, or effort which must be procured in advance of the production award in order to maintain the production schedule;

"(2) the term 'outfitting' means procurement or installation of onboard repair parts, other secondary items, equipage, and recreation items; precommissioning crew support; general use consumables furnished to the shipbuilder; the fitting out activity to fill a vessel's initial allowances; and contractor-furnished spares; and

"(3) the term 'post-delivery activities' means design, planning, Government-furnished material, and related labor for non-production and non-long lead time items contract activities and other work, including certifications, full operational capability activities and other equipment installation; spares, logistics, technical analysis, and support; correction of Government-responsible defects and deficiencies identified during builders trials, acceptance trials, and testing during the post-delivery period; costs of all work required to correct defects or deficiencies identified during the post-delivery period; and costs of all work required to correct trial card deficiencies on a vessel of a particular class, as well as on subsequent vessels of that class (whether or not delivered) until the corrective action for that cutter class is completed."

Disclaimer: These codes may not be the most recent version. The United States Government Printing Office may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the US site. Please check official sources.