2014 US Code
Title 42 - The Public Health and Welfare (Sections 1 - 18445)
Chapter 85 - Air Pollution Prevention and Control (Sections 7401 - 7671q)
Subchapter V - Permits (Sections 7661 - 7661f)
Sec. 7661b - Permit applications

View Metadata
Metadata
Publication TitleUnited States Code, 2012 Edition, Supplement 2, Title 42 - THE PUBLIC HEALTH AND WELFARE
CategoryBills and Statutes
CollectionUnited States Code
SuDoc Class NumberY 1.2/5:
Contained WithinTitle 42 - THE PUBLIC HEALTH AND WELFARE
CHAPTER 85 - AIR POLLUTION PREVENTION AND CONTROL
SUBCHAPTER V - PERMITS
Sec. 7661b - Permit applications
Containssection 7661b
Date2014
Laws In Effect As Of DateJanuary 5, 2015
Positive LawNo
Dispositionstandard
Source CreditJuly 14, 1955, ch. 360, title V, §503, as added Pub. L. 101-549, title V, §501, Nov. 15, 1990, 104 Stat. 2641.
Statutes at Large Reference104 Stat. 2641
Public and Private LawPublic Law 101-549

Download PDF


42 U.S.C. § 7661b (2014)
§7661b. Permit applications(a) Applicable date

Any source specified in section 7661a(a) of this title shall become subject to a permit program, and required to have a permit, on the later of the following dates—

(1) the effective date of a permit program or partial or interim permit program applicable to the source; or

(2) the date such source becomes subject to section 7661a(a) of this title.

(b) Compliance plan

(1) The regulations required by section 7661a(b) of this title shall include a requirement that the applicant submit with the permit application a compliance plan describing how the source will comply with all applicable requirements under this chapter. The compliance plan shall include a schedule of compliance, and a schedule under which the permittee will submit progress reports to the permitting authority no less frequently than every 6 months.

(2) The regulations shall further require the permittee to periodically (but no less frequently than annually) certify that the facility is in compliance with any applicable requirements of the permit, and to promptly report any deviations from permit requirements to the permitting authority.

(c) Deadline

Any person required to have a permit shall, not later than 12 months after the date on which the source becomes subject to a permit program approved or promulgated under this subchapter, or such earlier date as the permitting authority may establish, submit to the permitting authority a compliance plan and an application for a permit signed by a responsible official, who shall certify the accuracy of the information submitted. The permitting authority shall approve or disapprove a completed application (consistent with the procedures established under this subchapter for consideration of such applications), and shall issue or deny the permit, within 18 months after the date of receipt thereof, except that the permitting authority shall establish a phased schedule for acting on permit applications submitted within the first full year after the effective date of a permit program (or a partial or interim program). Any such schedule shall assure that at least one-third of such permits will be acted on by such authority annually over a period of not to exceed 3 years after such effective date. Such authority shall establish reasonable procedures to prioritize such approval or disapproval actions in the case of applications for construction or modification under the applicable requirements of this chapter.

(d) Timely and complete applications

Except for sources required to have a permit before construction or modification under the applicable requirements of this chapter, if an applicant has submitted a timely and complete application for a permit required by this subchapter (including renewals), but final action has not been taken on such application, the source's failure to have a permit shall not be a violation of this chapter, unless the delay in final action was due to the failure of the applicant timely to submit information required or requested to process the application. No source required to have a permit under this subchapter shall be in violation of section 7661a(a) of this title before the date on which the source is required to submit an application under subsection (c) of this section.

(e) Copies; availability

A copy of each permit application, compliance plan (including the schedule of compliance), emissions or compliance monitoring report, certification, and each permit issued under this subchapter, shall be available to the public. If an applicant or permittee is required to submit information entitled to protection from disclosure under section 7414(c) of this title, the applicant or permittee may submit such information separately. The requirements of section 7414(c) of this title shall apply to such information. The contents of a permit shall not be entitled to protection under section 7414(c) of this title.

(July 14, 1955, ch. 360, title V, §503, as added Pub. L. 101–549, title V, §501, Nov. 15, 1990, 104 Stat. 2641.)

Disclaimer: These codes may not be the most recent version. The United States Government Printing Office may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the US site. Please check official sources.