Sec. 2235 - Construction permits and operating licenses

View Metadata
Metadata
Publication TitleUnited States Code, 2012 Edition, Supplement 2, Title 42 - THE PUBLIC HEALTH AND WELFARE
CategoryBills and Statutes
CollectionUnited States Code
SuDoc Class NumberY 1.2/5:
Contained WithinTitle 42 - THE PUBLIC HEALTH AND WELFARE
CHAPTER 23 - DEVELOPMENT AND CONTROL OF ATOMIC ENERGY
Division A - Atomic Energy
SUBCHAPTER XV - JUDICIAL REVIEW AND ADMINISTRATIVE PROCEDURE
Sec. 2235 - Construction permits and operating licenses
Containssection 2235
Date2014
Laws In Effect As Of DateJanuary 5, 2015
Positive LawNo
Dispositionstandard
Source CreditAug. 1, 1946, ch. 724, title I, §185, as added Aug. 30, 1954, ch. 1073, §1, 68 Stat. 955; renumbered title I and amended Pub. L. 102-486, title IX, §902(a)(8), title XXVIII, §2801, Oct. 24, 1992, 106 Stat. 2944, 3120.
Presidential Document NumberExecutive Order 12129
Statutes at Large References68 Stat. 955, 919
106 Stat. 2944, 3121
Public and Private LawsPublic Law 102-486

Download PDF


42 U.S.C. § 2235 (2014)
§2235. Construction permits and operating licenses

(a) All applicants for licenses to construct or modify production or utilization facilities shall, if the application is otherwise acceptable to the Commission, be initially granted a construction permit. The construction permit shall state the earliest and latest dates for the completion of the construction or modification. Unless the construction or modification of the facility is completed by the completion date, the construction permit shall expire, and all rights thereunder be forfeited, unless upon good cause shown, the Commission extends the completion date. Upon the completion of the construction or modification of the facility, upon the filing of any additional information needed to bring the original application up to date, and upon finding that the facility authorized has been constructed and will operate in conformity with the application as amended and in conformity with the provisions of this chapter and of the rules and regulations of the Commission, and in the absence of any good cause being shown to the Commission why the granting of a license would not be in accordance with the provisions of this chapter, the Commission shall thereupon issue a license to the applicant. For all other purposes of this chapter, a construction permit is deemed to be a "license".

(b) After holding a public hearing under section 2239(a)(1)(A) of this title, the Commission shall issue to the applicant a combined construction and operating license if the application contains sufficient information to support the issuance of a combined license and the Commission determines that there is reasonable assurance that the facility will be constructed and will operate in conformity with the license, the provisions of this chapter, and the Commission's rules and regulations. The Commission shall identify within the combined license the inspections, tests, and analyses, including those applicable to emergency planning, that the licensee shall perform, and the acceptance criteria that, if met, are necessary and sufficient to provide reasonable assurance that the facility has been constructed and will be operated in conformity with the license, the provisions of this chapter, and the Commission's rules and regulations. Following issuance of the combined license, the Commission shall ensure that the prescribed inspections, tests, and analyses are performed and, prior to operation of the facility, shall find that the prescribed acceptance criteria are met. Any finding made under this subsection shall not require a hearing except as provided in section 2239(a)(1)(B) of this title.

(Aug. 1, 1946, ch. 724, title I, §185, as added Aug. 30, 1954, ch. 1073, §1, 68 Stat. 955; renumbered title I and amended Pub. L. 102–486, title IX, §902(a)(8), title XXVIII, §2801, Oct. 24, 1992, 106 Stat. 2944, 3120.)

REFERENCES IN TEXT

This chapter, referred to in text, was in the original "this Act", meaning act Aug. 1, 1946, ch. 724, as added by act Aug. 30, 1954, ch. 1073, §1, 68 Stat. 919, known as the Atomic Energy Act of 1954, which is classified principally to this chapter. For complete classification of this Act to the Code, see Short Title note set out under section 2011 of this title and Tables.

AMENDMENTS

1992—Pub. L. 102–486, §2801, inserted "and operating licenses" after "permits" in section catchline, designated existing text as subsec. (a), and added subsec. (b).

EFFECTIVE DATE OF 1992 AMENDMENT

Pub. L. 102–486, title XXVIII, §2806, Oct, 24, 1992, 106 Stat. 3121, provided that: "Sections 185 b. and 189 a. (1)(B) of the Atomic Energy Act of 1954 [subsec. (b) of this section and section 2239(a)(1)(B) of this title], as added by sections 2801 and 2802 of this Act, shall apply to all proceedings involving a combined license for which an application was filed after May 8, 1991, under such sections."

EXECUTIVE ORDER NO. 12129

Ex. Ord. No. 12129, Apr. 5, 1979, 44 F.R. 21001, which established a Critical Energy Facility Program, was revoked by Ex. Ord. No. 12553, Feb. 25, 1986, 51 F.R. 7237.

Disclaimer: These codes may not be the most recent version. The United States Government Printing Office may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the US site. Please check official sources.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.