2014 US Code
Title 16 - Conservation (Sections 1 - 7304)
Chapter 12 - Federal Regulation and Development of Power (Sections 791 - 828c)
Subchapter II - Regulation of Electric Utility Companies Engaged in Interstate Commerce (Sections 824 - 824w)
Sec. 824s - Transmission infrastructure investment

View Metadata
Metadata
Publication TitleUnited States Code, 2012 Edition, Supplement 2, Title 16 - CONSERVATION
CategoryBills and Statutes
CollectionUnited States Code
SuDoc Class NumberY 1.2/5:
Contained WithinTitle 16 - CONSERVATION
CHAPTER 12 - FEDERAL REGULATION AND DEVELOPMENT OF POWER
SUBCHAPTER II - REGULATION OF ELECTRIC UTILITY COMPANIES ENGAGED IN INTERSTATE COMMERCE
Sec. 824s - Transmission infrastructure investment
Containssection 824s
Date2014
Laws In Effect As Of DateJanuary 5, 2015
Positive LawNo
Dispositionstandard
Source CreditJune 10, 1920, ch. 285, pt. II, §219, as added Pub. L. 109-58, title XII, §1241, Aug. 8, 2005, 119 Stat. 961.
Statutes at Large Reference119 Stat. 961
Public and Private LawPublic Law 109-58

Download PDF


16 U.S.C. § 824s (2014)
§824s. Transmission infrastructure investment(a) Rulemaking requirement

Not later than 1 year after August 8, 2005, the Commission shall establish, by rule, incentive-based (including performance-based) rate treatments for the transmission of electric energy in interstate commerce by public utilities for the purpose of benefitting consumers by ensuring reliability and reducing the cost of delivered power by reducing transmission congestion.

(b) Contents

The rule shall—

(1) promote reliable and economically efficient transmission and generation of electricity by promoting capital investment in the enlargement, improvement, maintenance, and operation of all facilities for the transmission of electric energy in interstate commerce, regardless of the ownership of the facilities;

(2) provide a return on equity that attracts new investment in transmission facilities (including related transmission technologies);

(3) encourage deployment of transmission technologies and other measures to increase the capacity and efficiency of existing transmission facilities and improve the operation of the facilities; and

(4) allow recovery of—

(A) all prudently incurred costs necessary to comply with mandatory reliability standards issued pursuant to section 824o of this title; and

(B) all prudently incurred costs related to transmission infrastructure development pursuant to section 824p of this title.

(c) Incentives

In the rule issued under this section, the Commission shall, to the extent within its jurisdiction, provide for incentives to each transmitting utility or electric utility that joins a Transmission Organization. The Commission shall ensure that any costs recoverable pursuant to this subsection may be recovered by such utility through the transmission rates charged by such utility or through the transmission rates charged by the Transmission Organization that provides transmission service to such utility.

(d) Just and reasonable rates

All rates approved under the rules adopted pursuant to this section, including any revisions to the rules, are subject to the requirements of sections 824d and 824e of this title that all rates, charges, terms, and conditions be just and reasonable and not unduly discriminatory or preferential.

(June 10, 1920, ch. 285, pt. II, §219, as added Pub. L. 109–58, title XII, §1241, Aug. 8, 2005, 119 Stat. 961.)

Disclaimer: These codes may not be the most recent version. The United States Government Printing Office may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the US site. Please check official sources.