2012 US Code
Title 50 - War and National Defense
Chapter 42 - ATOMIC ENERGY DEFENSE PROVISIONS (§§ 2501 - 2822)
Subchapter VII - BUDGET AND FINANCIAL MANAGEMENT MATTERS (§§ 2741 - 2772)
Part A - Recurring National Security Authorization Provisions (§§ 2741 - 2753)
Section 2744 - Limits on construction projects

View Metadata
Metadata
Publication TitleUnited States Code, 2012 Edition, Title 50 - WAR AND NATIONAL DEFENSE
CategoryBills and Statutes
CollectionUnited States Code
SuDoc Class NumberY 1.2/5:
Contained WithinTitle 50 - WAR AND NATIONAL DEFENSE
CHAPTER 42 - ATOMIC ENERGY DEFENSE PROVISIONS
SUBCHAPTER VII - BUDGET AND FINANCIAL MANAGEMENT MATTERS
Part A - Recurring National Security Authorization Provisions
Sec. 2744 - Limits on construction projects
Containssection 2744
Date2012
Laws in Effect as of DateJanuary 15, 2013
Positive LawNo
Dispositionstandard
Source CreditPub. L. 107-314, div. D, title XLVII, §4704, formerly div. C, title XXXVI, §3623, Dec. 2, 2002, 116 Stat. 2758; renumbered div. D, title XLVII, §4704, by Pub. L. 108-136, div. C, title XXXI, §3141(j)(2)(A)-(C), Nov. 24, 2003, 117 Stat. 1781.
Statutes at Large References116 Stat. 2758
117 Stat. 1781
Public Law ReferencesPublic Law 107-314, Public Law 108-136

Download PDF

Recurring National Security Authorization Provisions - 50 U.S.C. § 2744 (2012)
§2744. Limits on construction projects (a) Construction cost ceiling

Except as provided in subsection (b), construction on a construction project which is in support of national security programs of the Department of Energy and was authorized by a DOE national security authorization may not be started, and additional obligations in connection with the project above the total estimated cost may not be incurred, whenever the current estimated cost of the construction project exceeds by more than 25 percent the higher of—

(1) the amount authorized for the project; or

(2) the amount of the total estimated cost for the project as shown in the most recent budget justification data submitted to Congress.

(b) Exception where notice-and-wait given

An action described in subsection (a) may be taken if—

(1) the Secretary of Energy has submitted to the congressional defense committees a report on the actions and the circumstances making such action necessary; and

(2) a period of 30 days has elapsed after the date on which the report is received by the committees.

(c) Computation of days

In the computation of the 30-day period under subsection (b), there shall be excluded any day on which either House of Congress is not in session because of an adjournment of more than three days to a day certain.

(d) Exception for minor projects

Subsection (a) does not apply to a construction project with a current estimated cost of less than the minor construction threshold.

(Pub. L. 107–314, div. D, title XLVII, §4704, formerly div. C, title XXXVI, §3623, Dec. 2, 2002, 116 Stat. 2758; renumbered div. D, title XLVII, §4704, by Pub. L. 108–136, div. C, title XXXI, §3141(j)(2)(A)–(C), Nov. 24, 2003, 117 Stat. 1781.)

Codification

Section was formerly classified to section 7386c of Title 42, The Public Health and Welfare, prior to renumbering by Pub. L. 108–136.

Disclaimer: These codes may not be the most recent version. The United States Government Printing Office may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the US site. Please check official sources.