Section 2537 - Selected Acquisition Reports and independent cost estimates on life extension programs and new nuclear facilities
Publication Title | United States Code, 2012 Edition, Title 50 - WAR AND NATIONAL DEFENSE |
Category | Bills and Statutes |
Collection | United States Code |
SuDoc Class Number | Y 1.2/5: |
Contained Within | Title 50 - WAR AND NATIONAL DEFENSE CHAPTER 42 - ATOMIC ENERGY DEFENSE PROVISIONS SUBCHAPTER II - NUCLEAR WEAPONS STOCKPILE MATTERS Part A - Stockpile Stewardship and Weapons Production Sec. 2537 - Selected Acquisition Reports and independent cost estimates on life extension programs and new nuclear facilities |
Contains | section 2537 |
Date | 2012 |
Laws in Effect as of Date | January 15, 2013 |
Positive Law | No |
Disposition | standard |
Source Credit | Pub. L. 107-314, div. D, title XLII, §4217, as added Pub. L. 112-239, div. C, title XXXI, §3162(a), Jan. 2, 2013, 126 Stat. 2204. |
Statutes at Large Reference | 126 Stat. 2204 |
Public Law References | Public Law 107-314, Public Law 112-239 |
Download PDF
(1) At the end of each fiscal-year quarter, the Secretary of Energy, acting through the Administrator, shall submit to the congressional defense committees a report on each nuclear weapon system undergoing life extension. The reports shall be known as Selected Acquisition Reports for the weapon system concerned.
(2) The information contained in the Selected Acquisition Report for a fiscal-year quarter for a nuclear weapon system shall be the information contained in the Selected Acquisition Report for such fiscal-year quarter for a major defense acquisition program under section 2432 of title 10, expressed in terms of the nuclear weapon system.
(b) Independent cost estimates(1) The Secretary, acting through the Administrator, shall submit to the congressional defense committees and the Nuclear Weapons Council established under section 179 of title 10 an independent cost estimate of the following:
(A) Each nuclear weapon system undergoing life extension at the completion of phase 6.2A, relating to design definition and cost study.
(B) Each nuclear weapon system undergoing life extension before initiation of phase 6.5, relating to first production.
(C) Each new nuclear facility within the nuclear security enterprise that is estimated to cost more than $500,000,000 before such facility achieves critical decision 2 in the acquisition process.
(2) A cost estimate for purposes of this subsection may not be prepared by the Department of Energy or the Administration.
(c) Authority for further assessmentsUpon the request of the Administrator, the Secretary of Defense, acting through the Director of Cost Assessment and Program Evaluation and in consultation with the Administrator, may conduct an independent cost assessment of any initiative or program of the Administration that is estimated to cost more than $500,000,000.
(Pub. L. 107–314, div. D, title XLII, §4217, as added Pub. L. 112–239, div. C, title XXXI, §3162(a), Jan. 2, 2013, 126 Stat. 2204.)
Disclaimer: These codes may not be the most recent version. The United States Government Printing Office may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the US site. Please check official sources.