Section 24403 - Project management oversight
Publication Title | United States Code, 2012 Edition, Title 49 - TRANSPORTATION |
Category | Bills and Statutes |
Collection | United States Code |
SuDoc Class Number | Y 1.2/5: |
Contained Within | Title 49 - TRANSPORTATION SUBTITLE V - RAIL PROGRAMS PART C - PASSENGER TRANSPORTATION CHAPTER 244 - INTERCITY PASSENGER RAIL SERVICE CORRIDOR CAPITAL ASSISTANCE Sec. 24403 - Project management oversight |
Contains | section 24403 |
Date | 2012 |
Laws in Effect as of Date | January 15, 2013 |
Positive Law | Yes |
Disposition | standard |
Source Credit | Added Pub. L. 110-432, div. B, title III, §301(a), Oct. 16, 2008, 122 Stat. 4941. |
Statutes at Large Reference | 122 Stat. 4941 |
Public Law Reference | Public Law 110-432 |
Download PDF
(a)
(1) adequate recipient staff organization with well-defined reporting relationships, statements of functional responsibilities, job descriptions, and job qualifications;
(2) a budget covering the project management organization, appropriate consultants, property acquisition, utility relocation, systems demonstration staff, audits, and miscellaneous payments the recipient may be prepared to justify;
(3) a construction schedule for the project;
(4) a document control procedure and recordkeeping system;
(5) a change order procedure that includes a documented, systematic approach to handling the construction change orders;
(6) organizational structures, management skills, and staffing levels required throughout the construction phase;
(7) quality control and quality assurance functions, procedures, and responsibilities for construction, system installation, and integration of system components;
(8) material testing policies and procedures;
(9) internal plan implementation and reporting requirements;
(10) criteria and procedures to be used for testing the operational system or its major components;
(11) periodic updates of the plan, especially related to project budget and project schedule, financing, and ridership estimates; and
(12) the recipient's commitment to submit periodically a project budget and project schedule to the Secretary.
(b)
(1) The Secretary may use no more than 1 percent of amounts made available in a fiscal year for capital projects under this chapter to enter into contracts to oversee the construction of such projects.
(2) The Secretary may use amounts available under paragraph (1) of this subsection to make contracts for safety, procurement, management, and financial compliance reviews and audits of a recipient of amounts under paragraph (1).
(3) The Federal Government shall pay the entire cost of carrying out a contract under this subsection.
(c)
(Added Pub. L. 110–432, div. B, title III, §301(a), Oct. 16, 2008, 122 Stat. 4941.)
Disclaimer: These codes may not be the most recent version. The United States Government Printing Office may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the US site. Please check official sources.