2012 US Code
Title 41 - Public Contracts
Subtitle III - Contract Disputes (§§ 7101 - 7109)
Chapter 71 - CONTRACT DISPUTES (§§ 7101 - 7109)
Section 7104 - Contractor's right of appeal from decision by contracting officer

View Metadata
Metadata
Publication TitleUnited States Code, 2012 Edition, Title 41 - PUBLIC CONTRACTS
CategoryBills and Statutes
CollectionUnited States Code
SuDoc Class NumberY 1.2/5:
Contained WithinTitle 41 - PUBLIC CONTRACTS
Subtitle III - Contract Disputes
CHAPTER 71 - CONTRACT DISPUTES
Sec. 7104 - Contractor's right of appeal from decision by contracting officer
Containssection 7104
Date2012
Laws in Effect as of DateJanuary 15, 2013
Positive LawYes
Dispositionstandard
Source CreditPub. L. 111-350, §3, Jan. 4, 2011, 124 Stat. 3820.
Statutes at Large References92 Stat. 2385, 2388
96 Stat. 49
106 Stat. 4516
124 Stat. 3820
Public Law ReferencesPublic Law 95-563, Public Law 97-164, Public Law 102-572, Public Law 111-350

Download PDF

CONTRACT DISPUTES - 41 U.S.C. § 7104 (2012)
§7104. Contractor's right of appeal from decision by contracting officer

(a) Appeal to Agency Board.—A contractor, within 90 days from the date of receipt of a contracting officer's decision under section 7103 of this title, may appeal the decision to an agency board as provided in section 7105 of this title.

(b) Bringing an Action De Novo in Federal Court.—

(1) In general.—Except as provided in paragraph (2), and in lieu of appealing the decision of a contracting officer under section 7103 of this title to an agency board, a contractor may bring an action directly on the claim in the United States Court of Federal Claims, notwithstanding any contract provision, regulation, or rule of law to the contrary.

(2) Tennessee valley authority.—In the case of an action against the Tennessee Valley Authority, the contractor may only bring an action directly on the claim in a district court of the United States pursuant to section 1337 of title 28, notwithstanding any contract provision, regulation, or rule of law to the contrary.

(3) Time for filing.—A contractor shall file any action under paragraph (1) or (2) within 12 months from the date of receipt of a contracting officer's decision under section 7103 of this title.

(4) De novo.—An action under paragraph (1) or (2) shall proceed de novo in accordance with the rules of the appropriate court.

(Pub. L. 111–350, §3, Jan. 4, 2011, 124 Stat. 3820.)

Historical and Revision Notes
Revised

Section

Source (U.S. Code)Source (Statutes at Large)
7104(a) 41:606. Pub. L. 95–563, §7, Nov. 1, 1978, 92 Stat. 2385.
7104(b) 41:609(a). Pub. L. 95–563, §10(a), Nov. 1, 1978, 92 Stat. 2388; Pub. L. 97–164, title I, §161(10), Apr. 2, 1982, 96 Stat. 49.

In subsection (a), the words “of contract appeals” are omitted as unnecessary because of the definition of “agency board” in section 7101 of the revised title.

In subsection (b)(1), the words “United States Court of Federal Claims” are substituted for “United States Claims Court” because of section 902(b)(1) of the Federal Courts Administration Act of 1992 (Pub. L. 102–572, 106 Stat. 4516, 28 U.S.C. 171 note).

Disclaimer: These codes may not be the most recent version. The United States Government Printing Office may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the US site. Please check official sources.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.