Section 3143 - Termination of work on failure to pay agreed wages
View MetadataPublication Title | United States Code, 2006 Edition, Supplement 5, Title 40 - PUBLIC BUILDINGS, PROPERTY, AND WORKS |
Category | Bills and Statutes |
Collection | United States Code |
SuDoc Class Number | Y 1.2/5: |
Contained Within | Title 40 - PUBLIC BUILDINGS, PROPERTY, AND WORKS SUBTITLE II - PUBLIC BUILDINGS AND WORKS PART A - GENERAL CHAPTER 31 - GENERAL SUBCHAPTER IV - WAGE RATE REQUIREMENTS Sec. 3143 - Termination of work on failure to pay agreed wages |
Contains | section 3143 |
Date | 2011 |
Laws in Effect as of Date | January 3, 2012 |
Positive Law | Yes |
Disposition | standard |
Source Credit | Pub. L. 107-217, Aug. 21, 2002, 116 Stat. 1151. |
Statutes at Large References | 46 Stat. 1494 49 Stat. 1012 116 Stat. 1151 |
Public Law Reference | Public Law 107-217 |
Download PDF
Every contract within the scope of this subchapter shall contain a provision that if the contracting officer finds that any laborer or mechanic employed by the contractor or any subcontractor directly on the site of the work covered by the contract has been or is being paid a rate of wages less than the rate of wages required by the contract to be paid, the Federal Government by written notice to the contractor may terminate the contractor's right to proceed with the work or the part of the work as to which there has been a failure to pay the required wages. The Government may have the work completed, by contract or otherwise, and the contractor and the contractor's sureties shall be liable to the Government for any excess costs the Government incurs.
(Pub. L. 107–217, Aug. 21, 2002, 116 Stat. 1151.)
Revised Section | Source (U.S. Code) | Source (Statutes at Large) |
---|---|---|
3143 | 40:276a–1. | Mar. 3, 1931, ch. 411, §2, 46 Stat. 1494; Aug. 30, 1935, ch. 825, 49 Stat. 1012. |
The words “The Government may have the work completed” are substituted for “and to prosecute the work to completion . . . thereby” for clarity.
Disclaimer: These codes may not be the most recent version. The United States Government Printing Office may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the US site. Please check official sources.