1996 US Code
Title 10 - ARMED FORCES
Subtitle A - General Military Law
PART IV - SERVICE, SUPPLY, AND PROCUREMENT
CHAPTER 137 - PROCUREMENT GENERALLY
Sec. 2305a - Design-build selection procedures

View Metadata
Metadata
Publication TitleUnited States Code, 1994 Edition, Supplement 2, Title 10 - ARMED FORCES
CategoryBills and Statutes
CollectionUnited States Code
SuDoc Class NumberY 1.2/5:
Contained WithinTitle 10 - ARMED FORCES
Subtitle A - General Military Law
PART IV - SERVICE, SUPPLY, AND PROCUREMENT
CHAPTER 137 - PROCUREMENT GENERALLY
Sec. 2305a - Design-build selection procedures
Containssection 2305a
Date1996
Laws in Effect as of DateJanuary 6, 1997
Positive LawYes
Dispositionstandard
Source CreditAdded Pub. L. 104-106, div. D, title XLI, §4105(a)(1), Feb. 10, 1996, 110 Stat. 645.
Statutes at Large References86 Stat. 1278
110 Stat. 645
Public Law ReferencesPublic Law 92-582, Public Law 104-106


§2305a. Design-build selection procedures

(a) Authorization.—Unless the traditional acquisition approach of design-bid-build established under the Brooks Architect-Engineers Act (41 U.S.C. 541 et seq.) 1 is used or another acquisition procedure authorized by law is used, the head of an agency shall use the two-phase selection procedures authorized in this section for entering into a contract for the design and construction of a public building, facility, or work when a determination is made under subsection (b) that the procedures are appropriate for use.

(b) Criteria for Use.—A contracting officer shall make a determination whether two-phase selection procedures are appropriate for use for entering into a contract for the design and construction of a public building, facility, or work when the contracting officer anticipates that three or more offers will be received for such contract, design work must be performed before an offeror can develop a price or cost proposal for such contract, the offeror will incur a substantial amount of expense in preparing the offer, and the contracting officer has considered information such as the following:

(1) The extent to which the project requirements have been adequately defined.

(2) The time constraints for delivery of the project.

(3) The capability and experience of potential contractors.

(4) The suitability of the project for use of the two-phase selection procedures.

(5) The capability of the agency to manage the two-phase selection process.

(6) Other criteria established by the agency.


(c) Procedures Described.—Two-phase selection procedures consist of the following:

(1) The agency develops, either in-house or by contract, a scope of work statement for inclusion in the solicitation that defines the project and provides prospective offerors with sufficient information regarding the Government's requirements (which may include criteria and preliminary design, budget parameters, and schedule or delivery requirements) to enable the offerors to submit proposals which meet the Government's needs. If the agency contracts for development of the scope of work statement, the agency shall contract for architectural and engineering services as defined by and in accordance with the Brooks Architect-Engineers Act (40 U.S.C. 541 et seq.).

(2) The contracting officer solicits phase-one proposals that—

(A) include information on the offeror's—

(i) technical approach; and

(ii) technical qualifications; and


(B) do not include—

(i) detailed design information; or

(ii) cost or price information.


(3) The evaluation factors to be used in evaluating phase-one proposals are stated in the solicitation and include specialized experience and technical competence, capability to perform, past performance of the offeror's team (including the architect-engineer and construction members of the team) and other appropriate factors, except that cost-related or price-related evaluation factors are not permitted. Each solicitation establishes the relative importance assigned to the evaluation factors and subfactors that must be considered in the evaluation of phase-one proposals. The agency evaluates phase-one proposals on the basis of the phase-one evaluation factors set forth in the solicitation.

(4) The contracting officer selects as the most highly qualified the number of offerors specified in the solicitation to provide the property or services under the contract and requests the selected offerors to submit phase-two competitive proposals that include technical proposals and cost or price information. Each solicitation establishes with respect to phase two—

(A) the technical submission for the proposal, including design concepts or proposed solutions to requirements addressed within the scope of work (or both), and

(B) the evaluation factors and subfactors, including cost or price, that must be considered in the evaluations of proposals in accordance with paragraphs (2), (3), and (4) of section 2305(a) of this title.


The contracting officer separately evaluates the submissions described in subparagraphs (A) and (B).

(5) The agency awards the contract in accordance with section 2305(b)(4) of this title.


(d) Solicitation to State Number of Offerors To Be Selected for Phase Two Requests for Competitive Proposals.—A solicitation issued pursuant to the procedures described in subsection (c) shall state the maximum number of offerors that are to be selected to submit competitive proposals pursuant to subsection (c)(4). The maximum number specified in the solicitation shall not exceed 5 unless the agency determines with respect to an individual solicitation that a specified number greater than 5 is in the Government's interest and is consistent with the purposes and objectives of the two-phase selection process.

(e) Requirement for Guidance and Regulations.—The Federal Acquisition Regulation shall include guidance—

(1) regarding the factors that may be considered in determining whether the two-phase contracting procedures authorized by subsection (a) are appropriate for use in individual contracting situations;

(2) regarding the factors that may be used in selecting contractors; and

(3) providing for a uniform approach to be used Government-wide.

(Added Pub. L. 104–106, div. D, title XLI, §4105(a)(1), Feb. 10, 1996, 110 Stat. 645.)

References in Text

The Brooks Architect-Engineers Act, referred to in subsecs. (a) and (c)(1), is title IX of act June 30, 1949, ch. 288, as added by act Oct. 27, 1972, Pub. L. 92–582, 86 Stat. 1278, as amended, which is classified generally to subchapter VI (§541 et seq.) of chapter 10 of Title 40, Public Buildings, Property, and Works. For complete classification of this Act to the Code, see Short Title note set out under section 541 of Title 40 and Tables.

Prior Provisions

A prior section 2305a was renumbered section 2438 of this title.

Effective Date

For effective date and applicability of section, see section 4401 of Pub. L. 104–106, set out as an Effective Date of 1996 Amendment note under section 251 of Title 41, Public Contracts.

1 See References in Text note below.

Disclaimer: These codes may not be the most recent version. The United States Government Printing Office may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the US site. Please check official sources.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.