2012 South Dakota Codified Laws
Title 49 PUBLIC UTILITIES AND CARRIERS
Chapter 41B. Energy Conversion And Transmission Facilities
§49-41B-4 Permit required before construction of facility after certain date.


SD Codified L § 49-41B-4 (through 2012) What's This?


49-41B-4. Permit required before construction of facility after certain date. No utility may begin construction of a facility in the state on or after July 1, 1979, without first having obtained a permit issued with respect to such facility by the Public Utilities Commission pursuant to this chapter. No such permit is required for an associated facility to be constructed for the purpose of transporting water if the water management board has issued a permit to appropriate water for the use to be made by that facility. Any facility, with respect to which a permit is required, shall thereafter be constructed, operated, and maintained in conformity with such permit including any terms, conditions, or modifications contained therein.

Source: SL 1977, ch 390, § 4; SL 1983, ch 349.

Disclaimer: These codes may not be the most recent version. South Dakota may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.