2012 South Dakota Codified Laws
Title 49 PUBLIC UTILITIES AND CARRIERS
Chapter 41B. Energy Conversion And Transmission Facilities
§49-41B-24 Large facility or pipeline permit--Complete findings required by commission within year of receipt of application.


SD Codified L § 49-41B-24 (through 2012) What's This?


49-41B-24. Large facility or pipeline permit--Complete findings required by commission within year of receipt of application. Within twelve months of receipt of the initial application for a permit for the construction of energy conversion facilities, AC/DC conversion facilities, substations of two hundred fifty kilovolts or more, transmission lines of two hundred fifty kilovolts or more, or transmission lines for coal, gas, liquid hydrocarbons, liquid hydrocarbon products, or carbon dioxide, the commission shall make complete findings in rendering a decision regarding whether a permit should be granted, denied, or granted upon such terms, conditions or modifications of the construction, operation, or maintenance as the commission deems appropriate.

Source: SL 1977, ch 390, § 18; SL 1980, ch 328, § 2; SL 1981, ch 341; SL 2006, ch 242, § 5; SL 2009, ch 243, § 3.

Disclaimer: These codes may not be the most recent version. South Dakota may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.