49-41B-22.2. Reapplication for permit--Discussion of commission as to applicant's burden of proof. If a second or subsequent reapplication is filed within three years, or a reapplication is filed after three years, following a denial of a permit pursuant to § 49-41B-24 or 49-41B-25, the Public Utilities Commission may in its discretion decide if an applicant shall have the burden of proof to establish all criteria required in an original application.

Source: SL 1982, ch 333, § 2.

Disclaimer: These codes may not be the most recent version. South Dakota may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.