(1) A contractor or subcontractor who, for other purposes than paying the money loaned upon such contract, transfers, invests or expends and fails to pay to a laborer, subcontractor, or materialman out of the money received as provided in Section 29-7-10 is guilty of a misdemeanor and, upon conviction, when the consideration for the work and material exceeds the value of one hundred dollars must be fined not less than five hundred dollars nor more than one thousand dollars or imprisoned not less than three months nor more than six months and when such consideration does not exceed the value of one hundred dollars must be fined not more than five hundred dollars or imprisoned not longer than thirty days.

(2) Any person who wilfully and intentionally certifies to any owner or lending institution by affidavit or otherwise that all persons, firms, or corporations including subcontractors and materialmen having furnished services, labor, or materials or extra items used in the construction, improvement, or repair to the owner's building or real property have been paid in full, when such persons have not been paid in full, except with regard to services or materials concerning which all lien rights have been waived in writing, shall be deemed guilty of a misdemeanor and, upon conviction, shall be fined not more than five thousand dollars or imprisoned not more than sixty days, or both. Provided, however, that an agreement to waive the right to file or claim a lien for labor and materials is against public policy and is unenforceable unless payment substantially equal to the amount waived is actually made.

(3) Unless otherwise provided in an agreement between the parties, a contractor or subcontractor may set off, against the money upon which a laborer, subcontractor, or materialman has a lien as provided by Section 29-7-10, any debt claimed to be owed to the contractor by such laborer, subcontractor, or materialman, based upon a good faith claim that those services and materials for which payment is claimed by the laborer, subcontractor, or materialman were defective. In order to make such a set-off, a declaration and accounting thereof must be included in any certificate submitted with an application for payment and a copy thereof or a separate notarized original of the declaration must be sent by certified mail to the affected laborer, subcontractor, or materialman at the time the certificate is submitted.

HISTORY: 1962 Code Section 45-302; 1952 Code Section 45-302; 1942 Code Section 1278; 1932 Code Sections 1278, 8770; Civ. C. '22 Sections 173, 5682; Civ. C. '12 Sections 451, 4152; Civ. C. '02 Sections 338, 3047; 1896 (22) 198; 1897 (22) 487; 1976 Act No. 545, Section 1; 1991 Act No. 247, Section 2.

Disclaimer: These codes may not be the most recent version. South Carolina may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.