Section 29-5-60. Proration of payments among lienors.

Universal Citation: SC Code § 29-5-60 (2017)

(A) In the event the amount due the contractor by the owner is insufficient to pay all the lienors acquiring liens as herein provided it is the duty of the owner to prorate among all just claims the amount due the contractor.

(B) In the event the amount due a subcontractor by the contractor is insufficient to pay all the lienors acquiring liens under Section 29-5-20 as a result of supplying labor, materials, or services to that subcontractor, all just liens must be prorated by the contractor among sub-subcontractors and suppliers to that subcontractor.

HISTORY: 1962 Code Section 45-256; 1952 Code Section 45-256; 1942 Code Section 8731; 1932 Code Section 8731; Civ. C. '22 Section 5643; 1916 (29) 686; 1992 Act No. 368, Section 2.

Disclaimer: These codes may not be the most recent version. South Carolina may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.