2017 South Carolina Code of Laws
Title 29 - Mortgages and Other Liens
CHAPTER 5 - MECHANICS' LIENS
Section 29-5-20. Lien of laborer, mechanic, subcontractor or materialman; limits on aggregate amount of liens filed by sub-subcontractor or supplier; limits on total aggregate amount of liens; exceptions; settlement of action to enforce lien.

Universal Citation: SC Code § 29-5-20 (2017)

(A) Every laborer, mechanic, subcontractor, or person furnishing material for the improvement of real estate when the improvement has been authorized by the owner has a lien thereon, subject to existing liens of which he has actual or constructive notice, to the value of the labor or material so furnished, including the costs of the action and a reasonable attorney's fee which must be determined by the court in which the action is brought but only if the party seeking to enforce the lien prevails. If the party defending against the lien prevails, the defending party must be awarded costs of the action and a reasonable attorney's fee as determined by the court. The fee and the court costs may not exceed the amount of the lien. The lien may be enforced as herein provided.

(B) In no event shall the aggregate amount of any liens filed by a sub-subcontractor or supplier exceed the amount due by the contractor to the subcontractor to whom the sub-subcontractor or supplier has supplied labor, material, or services unless the sub-subcontractor or supplier has provided notice of furnishing labor or materials by certified or registered mail to the contractor. Such notice of furnishing labor or materials shall include:

(1) the name of the sub-subcontractor or supplier who claims payment;

(2) the name of the person with whom the claimant contracted or by whom he was employed;

(3) a description of the labor, services, or materials furnished and the contract price or value thereof. Materials specially fabricated by a person other than the one giving notice and the contract price or value thereof shall be separately stated in the notice;

(4) a description of the project where labor, services, or materials were used sufficient for identification;

(5) the date when the first and the last item of labor or service or materials was actually furnished or scheduled to be furnished; and

(6) the amount claimed to be due, if any.

After receiving such notice, no payment by the contractor to the subcontractor will lessen the amount recoverable by the person so giving notice. However, in no event shall the total aggregate amount of liens on the improvement exceed the amount due by the owner.

(C) Not less than fifteen days before the first term of court at which the trial is set, either party may file and serve on the other party an offer of settlement, and within ten days thereafter the party served may respond by filing and serving his offer of settlement. The offer shall state that it is made under this section and specify the amount, exclusive of interest and costs, which the party serving the offer is willing to agree constitutes a settlement of the lien. If the action is not reached for trial, then not less than fifteen days before the next term of court and subsequent terms of court at which the trial is set, either party may file and serve on the other party an offer of settlement or an amendment of a prior offer of settlement and, within ten days after that, the party served may respond by filing and serving his offer or amended offer of settlement. The offer supersedes any offer previously made under this section by the same party.

An offer of settlement is considered rejected unless an acceptance in writing is filed and served on the party making the offer five days before the commencement of the term.

If the offer or amended offer is rejected, it may not be referred to for any purpose at the trial but may be considered solely for the purpose of awarding costs and litigation expenses under this section.

For purposes of the award of attorney's fees, the determination of the prevailing party is based on one verdict in the action. One verdict assumes some entitlement to the mechanic's lien and the consideration of compulsory counterclaims. The party whose offer of settlement is closer to the verdict reached is considered the prevailing party in the action. If the difference between both offers and the verdict is equal, neither party is considered to be the prevailing party for purposes of determining the award of costs and attorney's fees. If the plaintiff makes no written offer of settlement, the amount prayed for in his complaint is considered to be his final offer of settlement.

If the defendant makes no written offer of settlement, the value of his counterclaim is considered to be his negative offer of settlement. If the defendant has not asserted a counterclaim, his offer of settlement is considered to be zero.

(D) Subsection (B) does not apply to individual laborers when the amount of their lien is less than two thousand dollars.

HISTORY: 1962 Code Section 45-252; 1952 Code Section 45-252; 1942 Code Section 8728; 1932 Code Section 8728; Civ. C. '22 Section 5640; Civ. C. '12 Section 4114; Civ. C. '02 Section 3009; R. S. 2466; 1896 (22) 197; 1916 (29) 686; 1973 (58) 80; 1986 Act No. 408, Section 2; 1992 Act No. 368, Section 1; 1995 Act No. 140, Section 1; 1999 Act No. 83, Section 2.

Disclaimer: These codes may not be the most recent version. South Carolina may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.