2015 South Carolina Code of Laws
Title 11 - Public Finance
CHAPTER 35 - SOUTH CAROLINA CONSOLIDATED PROCUREMENT CODE
Section 11-35-3015. Source selection methods assigned to project delivery methods.

SC Code § 11-35-3015 (2015) What's This?

(1) Scope. This section specifies the source selection methods applicable to procurements for the project delivery methods identified in Section 11-35-3005 (Project delivery methods authorized), except as provided in Sections 11-35-1550 (Small Purchases), 11-35-1560 (Sole Source Procurement), and 11-35-1570 (Emergency Procurements).

(2) Design-bid-build:

(a) Design. Architect-engineer, construction management, and land surveying services. The qualifications based selection process in Section 11-35-3220 (Qualifications Based Selection Procedures) must be used to procure architect-engineer, construction management, and land surveying services, unless those services are acquired in conjunction with construction using one of the project delivery methods provided in Section 11-35-3015 (3), (5), (6), (7), and (8).

(b) Construction. Competitive sealed bidding, as provided in Section 11-35-1520 (Competitive Sealed Bidding), must be used to procure construction in design-bid-build procurements.

(3) Construction Management at-risk. Contracts for construction management at-risk must be procured as provided in either Section 11-35-1520 (Competitive Sealed Bidding) or Section 11-35-1530 (Competitive Sealed Proposals).

(4) Operations and Maintenance. Contracts for operations and maintenance must be procured as set forth in Section 11-35-1510 (Methods of Source Selection).

(5) Design-build. Contracts for design-build must be procured by competitive sealed proposals, as provided in Section 11-35-1530 (Competitive Sealed Proposals), except that the regulations may describe the circumstances under which a particular design-build procurement does not require the submission of proposal development documents as required in Section 11-35-3024(2)(b).

(6) Design-build-operate-maintain. Contracts for design-build-operate-maintain must be procured by competitive sealed proposals, as provided in Section 11-35-1530 (Competitive Sealed Proposals).

(7) Design-build-finance-operate-maintain. Contracts for design-build-finance-operate-maintain must be procured by competitive sealed proposals, as provided in Section 11-35-1530 (Competitive Sealed Proposals).

(8) Other. Contracts for an alternate project delivery method approved pursuant to Section 11-35-3005(2) must be procured by a source selection method provided in Section 11-35-1510, as specified by the authority approving the alternative project delivery method.

HISTORY: 2008 Act No. 174, Section 3.

Editor's Note

2008 Act No. 174, Section 21, provides as follows:

"This act takes effect upon approval by the Governor and applies to solicitations issued on or after January 1, 2008."

Disclaimer: These codes may not be the most recent version. South Carolina may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.